Positioning, distinguishing, and linking target cost, responsibility cost, and planned cost (the GB/T 50326-2017 Clause 11.2.4 procedure)

The three form a chain of "targets passed down level by level, responsibilities compacted level by level": target cost sets the envelope (enterprise-level total target) → planned cost sets the path (the concretization of target cost, total ≤ target cost) → responsibility cost sets the responsible persons (planned cost cut by responsibility scope, sum = planned cost). The linking procedure is the six steps of GB/T 50326-2017 Clause 11.2.4: forecast cost → set the overall cost target → prepare the overall cost plan → decompose by responsibility scope → formulate control measures → hierarchical approval (the project management responsibility statement). For control, the planned cost serves as the target value of construction cost for periodic comparison and correction (GB/T 50502-2009 Clause 2.0.15).

Applicable Codes

  • GB/T 50326-2017 建设工程项目管理规范 第11.2.2、11.2.4条
  • GB/T 50502-2009 建筑施工组织设计规范 第2.0.15、7.6.2条
  • DBJ/T 15-153-2019 广东省建设项目全过程造价管理规范 第5.7.3条
  • GB/T 50875-2013 工程造价术语标准 第3.1.1条

Topic Positioning

This card covers the positioning, distinction, and linkage chain of the three concepts target cost, responsibility cost, and planned cost (numerical reconciliation, timing linkage, control linkage, responsibility linkage), with the cost plan preparation procedure of GB/T 50326-2017 Code for Management of Construction Projects, Clause 11.2.4, as the spine.

Core Conclusions

The three form one chain of "targets passed down level by level, responsibilities compacted level by level": ① target cost = the project envelope (set at enterprise level from the winning price, the separation of tender price from internal target cost, and target profit calculation); ② planned cost = the concretization of target cost (prepared by the project department around the project execution plan (construction methodology and site organization), in three cuts — by cost composition, by project structure, by implementation stage, total not exceeding the target cost); ③ responsibility cost = the projection of planned cost cut by responsibility scope (project management organization + enterprise functional departments + unit works / sub-divisional works), the sum of responsibility costs = planned cost. The linking procedure is the six steps of 11.2.4: forecast cost → set the overall cost target → prepare the overall cost plan → decompose by responsibility scope → formulate control measures → hierarchical approval (project management responsibility statement). Four linkage mechanisms: numerical reconciliation (target cost ≥ planned cost total = Σ responsibility costs — exceeding it means the decomposition is out of control); timing linkage (target cost set upon award → plan and responsibility decomposition completed before commencement → dynamic revision during implementation); control linkage (planned cost as the target value of construction cost, with actual vs. target compared periodically and deviations corrected, GB/T 50502-2009 Clause 2.0.15); responsibility linkage (responsibility cost landed on specific persons via the project management responsibility statement).

Applicable Boundaries

Applies to construction project cost planning and responsibility decomposition. The target cost is in essence one form of estimate (GB/T 50875-2013 Clause 3.1.1); when commissioning, its concept, preparation bases, content, and calculation basis must be clarified first, otherwise actual cost easily deviates from target; the target cost should be decomposed along the cost management system, contract sections, and responsible departments (DBJ/T 15-153-2019 Clause 5.7.3); decomposition granularity adjusts with the project management model, and contribution-rate / target-profit bases vary by enterprise.

Further Reading

GB/T 50326-2017 Code for Management of Construction Projects, Clause 11.2.4 (cost plan preparation procedure, construction cost plan content) and Clause 11.2.2 (preparing by cost composition / project structure / implementation stage); GB/T 50502-2009 Code for Project Execution Plan of Building Works, Clause 2.0.15 (cost management plan terminology) and Clause 7.6.2 (five elements of the cost management plan); DBJ/T 15-153-2019 Clause 5.7.3; GB/T 50875-2013 Standard for Terminology of Engineering Cost, Clause 3.1.1.