Determining the baseline value for project cost assessment: bases, preparation path and tiered reconciliation (baseline = the approved responsibility target cost)
The cost assessment baseline is the approved responsibility target cost (planned cost): its bases are the cost indicators in the project management target responsibility statement (ceiling), the contractor's in-house norms (consumption), market prices of production factors (prices), and the project execution plan (construction methodology and site organization) (RISN-TG 012-2011, Clause 8.2.1); the cost management plan is prepared on the basis of the construction budget (quantities from the contractor's in-house norms, prices from market prices), the planned cost is summarized and decomposed by tiers, and it takes effect after approval by the enterprise's authorized person (GB/T 50326-2017, Clause 11.2.4); reconciliation: Σ special-purpose baselines = direct cost baseline + indirect cost baseline = overall responsibility target cost, with assessment by cost reduction amount/rate (RISN-TG 012-2011, Clauses 8.5.1, 8.5.2).
Applicable Codes
- GB/T 50326-2017 建设工程项目管理规范
- GB/T 50502-2009 建筑施工组织设计规范
- RISN-TG 012-2011 建设工程项目经理执业导则
- GB/T 51235-2017 建筑信息模型施工应用标准
- DBJ04/T 422-2021 建筑信息模型施工应用标准
Topic Positioning
This card answers "how the baseline value for project cost assessment is determined": baseline = the approved responsibility target cost (planned cost), giving the complete procedure from determination bases and preparation path through the tiered system to approval and taking effect.
Core Conclusions
- Essence of the baseline: the planned cost serves as the target value of the construction cost, periodically compared with actual values for correction (GB/T 50502-2009, Clause 2.0.15); the main assessment indicators — cost reduction amount/rate — are calculated against this baseline (GB/T 50326-2017, Clause 11.6.2).
- Five determination bases (RISN-TG 012-2011, Clause 8.2.1): ① cost indicators set in the project management target responsibility statement (the ceiling issued by the company); ② the contractor's in-house norms or related quota norms (source of consumption); ③ market prices of production factors (source of prices); ④ the project execution plan (construction methodology and site organization); ⑤ empirical data from similar projects.
- Preparation path: prepare the cost management plan on the basis of the construction budget (GB/T 50502-2009, Clause 7.6.1) — quantities from the contractor's in-house norms and prices from current market prices, distinct from the external-basis construction-drawing based budget (pre-tender estimate) (national quota norms + published price information); summarize direct + indirect costs to form the planned cost; check and consolidate against the responsibility statement; prepare by tiers of cost composition / project structure / implementation stage (GB/T 50326-2017, Clause 11.2.2); takes effect after approval by the enterprise's authorized person (Clause 11.2.4 — an unapproved plan has no assessment effect).
- Tiered reconciliation: Σ special-purpose responsibility baselines = direct cost baseline (labour/materials/machinery, preliminaries) + indirect cost baseline (management fee) = overall responsibility target cost (RISN-TG 012-2011, Clause 8.5.1); reduction amount = responsibility target cost − actual cost, reduction rate = reduction amount ÷ responsibility target cost × 100% (Clause 8.5.2); baselines at each tier must interlock up and down.
Applicable Boundaries
Applies to construction enterprise project cost management (the construction cost plan is prepared by the contractor); the baseline is an internal management measure, not the tender price (competitive price cuts and risk reserves should be removed); major changes require the formal procedure to adjust the baseline; the assessment object is mainly the contractor, with other stakeholders adopting by reference.
Further Reading
See GB/T 50326-2017 Clauses 11.2.2, 11.2.4, 11.6.2; GB/T 50502-2009 Clauses 2.0.15, 7.6.1, 7.6.2; RISN-TG 012-2011 Clauses 8.2.1, 8.2.2, 8.5.1, 8.5.2; GB/T 51235-2017 Clause 9.3.5 (contract budget cost determined on the basis of the construction-drawing based budget (pre-tender estimate)); DBJ04/T 422-2021 Clause 8.5.4 (extracting quantities via BIM to prepare the construction budget).
Keywords
- 成本考核基准值
- 责任目标成本
- 成本管理计划
- 施工预算
- contractor's in-house norms
- 成本降低额
- 成本降低率
- 计划成本