Assessment indicator system of the project management target responsibility statement (project cost responsibility statement): main cost indicators + itemized costs + other management targets

The project management target responsibility statement is a document signed between the enterprise management level and the project management organization, specifying the cost/quality/schedule/safety/environmental targets to be achieved and serving as the basis for assessment (GB/T 50326-2017, Clause 2.0.12). The main cost assessment indicators are the cost reduction amount and the cost reduction rate (Clause 11.6.2), itemized into direct cost (labor, materials, machinery, measure costs) and indirect cost (management fee) reduction amounts/rates (RISN-TG 012-2011, Clause 8.5.1), assessed at two levels — the overall project target and the special-purpose responsibility targets (Clause 8.5.2); supplemented by performance indicators such as quality, schedule, safety, contract fulfillment rate, project payment recovery rate, and green construction (Clause 19.2.2).

Applicable Codes

  • GB/T 50326-2017 建设工程项目管理规范
  • RISN-TG 012-2011 建设工程项目经理执业导则

Topic Positioning

This card answers "which assessment indicators a project cost responsibility statement (standard name: project management target responsibility statement) should contain". Per GB/T 50326-2017 and RISN-TG 012-2011, it sorts out the indicator framework and calculation formulas of the responsibility statement, directly usable for preparing and reviewing responsibility statements or designing project assessment schemes.

Core Conclusions

The project management target responsibility statement is a document signed between the enterprise management level and the project management organization, specifying the management targets and responsibilities to be achieved in cost, quality, schedule, safety, and environment, and serving as the basis for assessment and evaluation after project completion (GB/T 50326-2017, Clause 2.0.12). The indicator system has three tiers:

  1. Main cost indicators: cost reduction amount and cost reduction rate (Clause 11.6.2). Reduction amount = responsibility target cost − actual cost; reduction rate = reduction amount ÷ responsibility target cost × 100% (RISN-TG 012-2011, Clause 8.5.2).
  2. Itemized cost indicators: direct cost reduction amount/rate (calculated from planned targets vs actual occurrences of labor cost, material cost, machinery usage cost, and measure costs) + indirect cost reduction amount/rate (on the basis of the project management department's management fee, Clause 8.5.1).
  3. Responsibility decomposition basis: reduction amount/rate of the overall project responsibility target cost, plus the reduction amounts/rates of each special-purpose responsibility target cost (Clause 8.5.2). Supporting management targets: performance indicators such as quality, schedule, occupational health and safety, contract fulfillment rate, project payment recovery rate, and green construction (Clause 19.2.2). The responsibility statement must also specify the division of responsibilities, powers and interests, resource acquisition and accounting methods, risk bearing, reward and penalty bases, defect liability period requirements, etc. (GB/T 50326-2017, Clause 4.5.4), and clarify the purpose, timing, scope, objects, methods, bases, and indicators of assessment, organizational leadership, and the principles of evaluation, rewards, and penalties (Clause 11.6.1).

Applicable Boundaries

Cost reduction amount/rate is the common main assessment indicator for construction enterprises; other project stakeholders may adopt it by reference or use other indicators (Clause 11.6.2, note). Cost indicators must be quantified to an accountable level and linked with the project cost accounting ledger (Clause 11.4.1) before assessment can be implemented; this card gives only the indicator framework, without specific target values.

Further Reading

GB/T 50326-2017, Code for Construction Project Management, Clauses 2.0.12, 4.5.4, 11.6.1, 11.6.2; RISN-TG 012-2011, Guideline for the Practice of Construction Project Managers, Clauses 8.5.1, 8.5.2, 19.2.2; for responsibility cost decomposition see GB/T 50903-2013 Clause 6.5.1 and RISN-TG 012-2011 Clause 8.2.2.