Monthly project cost analysis template: mandatory elements per the codes, section structure, and the three-cost comparison workflow

A monthly cost analysis report has three mandatory elements: completion status of cost indicators, analysis of profit/loss causes, and proposed measures (RISN-TG 012-2011, Clause 8.3.2 — organized monthly or by construction node with a written report); the analysis covers five dimensions: time nodes, WBS work units, organizational units, individual indicators, and comprehensive projects (GB/T 50326-2017, Clause 11.5.2); accounting keeps the "three synchronizations" of physical progress, output value statistics, and cost collection (Clause 11.4.3). Template skeleton: basic information → physical progress and output value → three-cost comparison summary (budget/target/actual, month + cumulative) → profit/loss by work item → quantity-price analysis of cost elements → earned value (CV/SV) → variance causes → corrective measures → responsibility cost assessment → next month's cost plan → approval signature chain.

Applicable Codes

  • GB/T 50326-2017 建设工程项目管理规范
  • RISN-TG 012-2011 建设工程项目经理执业导则
  • GB/T 50502-2009 建筑施工组织设计规范
  • T/ZSQX 023-2023 城镇给排水项目工程总承包管理规程
  • GB/T 51235-2017 建筑信息模型施工应用标准
  • GB/T 50358-2017 建设项目工程总承包管理规范

Topic Positioning

This card shows how to build a monthly project cost analysis template (cost analysis report): the mandatory content required by the codes, a recommended section structure, and the estimate-budget-final account comparison basis, for direct use by project cost management staff.

Core Conclusions

Three mandatory elements of the monthly cost analysis report: ① completion status of cost indicators; ② analysis of profit/loss causes; ③ proposed measures (RISN-TG 012-2011, Clause 8.3.2 — organized monthly or by construction node with a written report). The analysis must cover five dimensions: time nodes, WBS work units, organizational units, individual indicators, and comprehensive projects (GB/T 50326-2017, Clause 11.5.2); the bases are the cost plan, cost accounting records, and accounting/statistical/business accounting data (Clause 11.5.1); accounting keeps the three synchronizations of physical progress, output value statistics, and cost collection (Clause 11.4.3). Recommended template sections: ① basic information → ② physical progress and output value → ③ estimate-budget-final account comparison summary (budget/target/actual, current month + cumulative; variance = actual − target) → ④ profit/loss by work item → ⑤ cost element analysis (labor/materials/machinery/measures/equipment procurement/on-costs — six items, each with quantity and price variances, watching labor subcontract execution, material requisition against quota limits, machinery idle time, amortization of temporary works and site establishment costs) → ⑥ earned value analysis (CV = BCWP − ACWP, SV = BCWP − BCWS) → ⑦ variance causes → ⑧ corrective measures → ⑨ responsibility-centre cost assessment (cost reduction amount/rate) → ⑩ next month's cost plan → ⑪ approval signature chain. Analysis methods: basic methods (comparison, factor analysis, difference analysis, ratio analysis) + composite methods (work-item, annual/quarterly/monthly, and completion cost analyses).

Applicable Boundaries

Applies to routine monthly (or node-based) cost management by construction enterprises' project departments; the basis must be consistent with the approved cost plan and responsibility-centre target cost; in BIM scenarios, the cost management model can auto-extract quantities for the estimate-budget-final account comparison. Not applicable to enterprise-level financial final accounts, settlement audits, or single-point cost consulting; monthly analysis focuses on project-controllable costs (direct costs and on-costs), collected by unit work, strictly separating enterprise operating costs from project production costs.

Further Reading

See RISN-TG 012-2011 Clauses 8.3.1, 8.3.2, 8.5.1, 8.5.2; GB/T 50326-2017 Clauses 11.3.2, 11.4.1, 11.4.3, 11.5.1–11.5.3, 11.6.1–11.6.2; GB/T 50502-2009 Clauses 7.6.1–7.6.2 (cost management plan content); T/ZSQX 023-2023 Clause 14.4.2 (six cost analysis items); GB/T 51235-2017 Clauses 9.3.1, 9.3.5 (BIM estimate-budget-final account comparison); GB/T 50358-2017 Clause 2.0.8 (earned value parameter definitions).