Fine-decoration cost collection: a spatial-dimension matrix of room → unit type → floor → building, with apportionment and reconciliation
Fine-decoration cost collection builds a two-dimensional matrix of "spatial part × cost element": the room is the smallest accounting unit (divisional items collected per GB/T 50854-2024 Appendices L/M/N/H/Q); elevator lobbies and other public areas go directly to the floor; vertical transport and super-height surcharges are apportioned to unit types by gross floor area (GFA); public areas are apportioned by the ratio of within-unit areas (the basis fixed in advance); reconciliation checks Σrooms = unit type, Σunit types + shared = floor, and floor-by-floor totals = the grand total, with cost accounting keeping the three synchronizations of physical progress, output-value statistics, and cost collection.
Applicable Codes
- GB/T 50500-2024
- GB/T 50854-2024
- GB/T 50903-2013
- GB/T 50326-2017
- T/CBDA 80-2024
- GB/T 51290-2018
- DBJ/T 15-153-2019
Topic Positioning
The cost collection method for fine-decoration works: by the two-dimensional matrix of "spatial part × cost element", vertically cut into room → unit type → floor → building blocks and horizontally grouped into labour/materials/machinery/attributable preliminaries/on-costs (indirect costs), cross-locking every cost unit and reconciling level by level. Applicable to cost accounting, target costing, and benchmarking of residential batch fine decoration and decoration works divisible by space.
Core Conclusions
- Dimension system: the room is the smallest accounting unit, coded as "building-floor-unit type-room number"; each component belongs to exactly one room, preventing double collection.
- Room-level collection: classify the items within a room per GB/T 50854-2024 appendices — floors (L.1.1 monolithic finishes, L.2.1 block paving), wall/column faces (M.1.1 plaster, M.3.1 tiling), ceilings (N.1.1 plaster, N.2.1 suspended ceiling), doors/windows (H.8.1 trim), fixed furniture and partitions (Q.1.1, M.7.1); luminaires, switches, and sockets first divide the decoration/installation interface to avoid counting on both sides.
- Floors and apportionment: public areas such as elevator lobbies, corridors, and pipe shafts go directly to the floor; vertical transport and super-height surcharges are apportioned to unit types by gross floor area (GFA); public areas by the ratio of within-unit areas (or evenly by household) — the apportionment basis must be agreed in advance in the cost management system (DBJ/T 15-153-2019, Clause 8.3.3).
- Unit-type application: unit-type cost = Σrooms + shared apportionment + floor apportionment + indirect apportionment; unit cost bases (within-unit/including shared) unified; benchmark the same unit type across buildings to find differences; measured show-flat costs serve as the unit-type target-cost benchmark.
- Reconciliation checks: Σrooms = unit type, Σunit types + shared = floor, Σfloors = building = the grand total; cost accounting keeps the three synchronizations of physical progress, output-value statistics, and cost collection (GB/T 50326-2017, Clause 11.4.3).
Applicable Boundaries
Applies to batch fine decoration divisible into stable unit types; single-unit-type standalone projects may omit the floor dimension. Apportionment rules and indicator bases must be fixed in advance; the decoration/installation interface is divided first. BOQ-based pricing/rate build-up themselves are not covered.
Further Reading
GB/T 50500-2024 Clause 2.0.2 (definition of divisional works), Clause 3.2.6 (listing of preliminary items); GB/T 50854-2024 Appendices L/M/N/H/Q; GB/T 50903-2013 Clause 6.5.1 (responsibility-centre cost cross-cutting on two lines); T/CBDA 80-2024 Clause 10.2.5 (BIM splitting and checking by zone/system/material); GB/T 51290-2018 Table C.2.2 (main quantity indicators of building decoration); SJG 77-2020 Clause 5.10.2 (fine-decoration preliminary items).