Charging the cost of fine-decoration show flats (model rooms): classifying by nature to determine the cost-attribution path (process → measure costs / delivery → divisional works / display → other-item costs or separate award)
Show-flat costs are charged by first classifying nature, then setting the path: workmanship show flats → preliminaries or amortized into all-in unit rates; delivery-standard show flats → formally listed into divisional-works costs; marketing display show flats → other-item costs (provisional sums etc.) or separately awarded. Show flats are a mandatory pre-procedure of decoration (GB 50210-2018 Clause 3.3.8), and cost attribution follows the GB/T 50500-2024 framework + contract agreement.
Applicable Codes
- GB 50210-2018 建筑装饰装修工程质量验收标准
- GB/T 50500-2024 建设工程工程量清单计价标准
- GB/T 50875-2013 工程造价术语标准
- T/CBDA 75-2024 建筑装饰装修项目质量管理标准
- TB 10801-2024 铁路基本建设工程设计概(预)算编制办法
- SJG 77-2020 房屋建筑工程造价文件分部分项和措施项目划分标准
Topic Positioning
The compliant framework for charging the costs of fine-decoration show flats: first classify by nature (process/delivery/marketing display), then map to the cost-attribution path — applicable to pricing and settlement disputes of building and railway station building decoration.
Core Conclusions
Show-flat construction is a pre-procedure of decoration (GB 50210-2018 Clause 3.3.8: before construction there shall be material samples or a show flat confirmed by all parties; T/CBDA 75-2024 Clause 6.5.5 divides them into four types — design effect/material application/workmanship/comprehensive), and its cost must have a source. With no unified special account nationally, costs are charged per the GB/T 50500-2024 framework + contract agreement: (1) Workmanship show flats (sample walls/segments/procedures, usually demolished after acceptance) → non-physical consumption, listed under preliminaries (the "incurred for completing the works in full" framework of GB/T 50500-2024 Clause 3.2.6) or amortized into all-in unit rates; (2) Delivery-standard show flats (final delivery) → formally listed into divisional-works costs, measured as executed, with methods differing from the large-area parts (high-grade stone/wood veneer etc.) listed separately; (3) Marketing display show flats → listed under other-item costs (provisional sums/provisional sum for specified materials or nominated works/dayworks, GB/T 50875-2013 Clause 2.2.57) or awarded separately (including soft furnishing, entering development cost, not the general contractor's cost of works (construction and installation)). Five must-checks: the contract states the attribution path; the demolition/restoration cost of process show flats has a source; when main-material grades exceed the large-area standard, clarify employer- or contractor-supply; soft furnishing and furniture purchase costs listed separately; where earlier than BOQ publication, use provisional sums adjusted as executed or fixed all-in unit rates.
Applicable Boundaries
Applies to building fine decoration and railway station building works; specific unit prices follow the project contract and local quota norms. Railway caliber: the cost composition of TB 10801-2024 has no special "show flat" account; station building decoration show flats enter the individual estimate of building works as formal decoration, workmanship samples amortize into quota line items or preliminaries, and special items are subject to the construction employer's approval. Not applicable to simple decoration without show-flat requirements.
Further Reading
GB 50210-2018 Clause 3.3.8; GB/T 50500-2024 Clause 3.2.6; GB/T 50875-2013 Clause 2.2.57; T/CBDA 75-2024 Clause 6.5.5; TB 10801-2024 Section 2.6 (cost item composition and the individual estimate/budget calculation procedure); SJG 77-2020 Clause 5.10.2 (fine-decoration preliminary items reminder).
Keywords
- 样板间费用
- 精装修样板间
- 样板房
- preliminaries
- 其他项目费
- provisional sums
- 交付样板间
- 样板间计取