Estimating and apportioning the protection-of-finished-work cost (protection cost of completed works and equipment): two paths — the percentage-rate method and the actual-cost method
The protection-of-finished-work cost belongs to preliminaries (GB/T 50500-2024 Clause 3.2.6). Two estimating paths: (1) the percentage-rate method = base to which percentage rates are applied × percentage rate — under the BOQ basis, on the base of divisional-works costs at range percentage rates from local quota norms; under the railway basis it is merged into construction preliminaries and calculated at (base-period labour cost + base-period plant and small tools cost) × percentage rate (TB 10801-2024 Section 3.6); (2) the actual-cost method = Σ(protection quantity × unit price) + guarding labour + demolition and removal, item by item per the protection scheme, with materials amortized over turnovers. Apportionment may merge into preliminaries for unified charging, be a separately billed item, or amortize into the all-in unit rates of the protected objects; the basis must be agreed in advance in the tender contract.
Applicable Codes
- GB/T 50500-2024
- GB/T 50875-2013
- JGJ/T 427-2018
- T/CBDA 36-2020
- T/YJXB 0001-2023
- TB 10801-2024
- SJG 77-2020
Topic Positioning
This card covers the estimation and apportionment of the protection-of-finished-work cost (protection cost of completed works and equipment): first set the calculation path (percentage-rate method or actual-cost method), then the apportionment vehicle (merged into preliminaries, as a separately billed item, or amortized into all-in unit rates) — applicable to building decoration and railway works pricing.
Core Conclusions
- Cost nature: the protection-of-finished-work cost belongs to preliminaries. GB/T 50500-2024 Clause 3.2.6 includes finished-work protection and completion cleaning in preliminaries; GB/T 50875-2013 defines the completed-works protection cost as the cost of necessary protective measures for completed works and equipment before taking-over (completion acceptance); JGJ/T 427-2018 requires protection of completed items during both construction and the warranty period.
- Percentage-rate method (rough estimate for bidding/price control): protection cost = base to which percentage rates are applied × percentage rate. Under BOQ-based pricing the base is divisional-works costs, and local norms for on-costs and expenses often give range percentage rates (building decoration around 0~0.1%, determined by the compiler per actual conditions); under the railway basis it is not a separately billed item but is merged into construction preliminaries, calculated at (base-period labour cost + base-period plant and small tools cost) × percentage rate (TB 10801-2024 Section 3.6).
- Actual-cost method (settlement/fine estimation): computed item by item per the finished-work protection scheme — Σ(protection quantity × protection unit price) + guarding labour cost + demolition and removal cost; protective materials such as floor film and corner guards are amortized over turnovers. T/YJXB 0001-2023 gives two bases — the actual-expenditure method and the rule-standard method; T/CBDA 36-2020 requires protective materials to be in flexible contact with the protected finish, be easy to remove, and not stain the finish.
- Apportionment: collect and amortize into the all-in unit rates of the corresponding divisional items by protected object (whoever benefits pays), be a separately billed item under preliminary items at percentage rates, or merge into construction preliminaries for unified charging (railway); with multi-trade crossing construction, divide by interfaces to avoid double charging among subcontractors.
Applicable Boundaries
The percentage-rate method suits rough estimating and price control, with wide ranges needing case-by-case determination; the actual-cost method requires the protection scheme (scope, materials, labour, duration) on file as the basis for settlement. This card is a general method framework; specific percentage rates and protection unit prices follow the current local norms for on-costs and expenses of the project and the contract; if warranty-period protection responsibility is agreed in the contract, its cost should be reserved in preliminaries or risk funds.
Further Reading
GB/T 50500-2024 Clause 3.2.6; GB/T 50875-2013 Clause 2.2.56; JGJ/T 427-2018 Clause 3.0.1; T/CBDA 36-2020 Clause 8.6.3; T/YJXB 0001-2023 Clause 5.0.1; TB 10801-2024 Section 2.6 (cost composition), Section 3.6 (construction preliminaries); SJG 77-2020 Clauses 5.1.3, 5.10.2 (listing of preliminary items).
Keywords
- 成品保护费
- protection of completed works
- 成品保护
- preliminaries
- 保护费用测算
- 费率法
- 实算法