Estimating traffic diversion (traffic relief) costs of municipal works: pricing attribution and two estimation paths
Traffic diversion cost is a preliminary item charged in the bill of preliminaries. Two estimation paths: (1) scheme-quantity method (mainstream) — item-by-item quantity take-off and pricing per the approved project execution plan/special diversion scheme (temporary roads, temporary bridges, hoarding, signs, markings, separation, signal lights, traffic wardens, efficiency loss, removal and restoration, etc.); (2) percentage-rate fallback — without a specific scheme, charge traffic management provisions as a percentage of the divisional-work BOQ total per local rules. GB/T 50903-2013 Clause 6.7.1 requires compiling traffic organization measures, which underpin the estimation.
Applicable Codes
- GB/T 50857-2024 市政工程工程量计算标准 App. M 措施项目
- GB 50861-2013 城市轨道交通工程工程量计算规范 Table N.10
- GB/T 50903-2013 市政工程施工组织设计规范 6.7.1
- SJG 84-2020 市政维修工程消耗量标准 总则
Topic Positioning
The pricing attribution and estimation method of traffic diversion/relief costs for municipal works (incl. urban rail): what kind of fee this money is, how to calculate it, and on what basis.
Core Conclusions
- Nature: traffic diversion is a preliminary item, listed in the bill of preliminaries. GB/T 50857-2024 Appendix M (code 041201) provides preliminary items measured per "item" such as temporary roads and temporary bridges (work content includes site leveling, laying and compaction, removal and cleanup); the urban-rail caliber may reference GB 50861-2013 Table N.10 (code 081310) "traffic and pedestrian interference and traffic diversion additions", with item descriptions of road class + impact scope and work content including alternating construction and additional personnel.
- Scheme basis: GB/T 50903-2013 Clause 6.7.1 requires compiling traffic organization measures for the work zone and surrounding traffic (covering current traffic and traffic organization arrangements) — the premise of diversion cost estimation.
- Path A (scheme-quantity method, mainstream): item-by-item quantity take-off and applying quota items or market prices per the approved project execution plan/special scheme; items generally include: diversion temporary road construction (m2), temporary bridges (m/unit), hoarding (linear meter x month, incl. erection/removal and rental amortization), temporary signs (count), markings (m2, incl. removal), separation facilities (count/linear meter x month, mostly rented), mobile signal lights and lighting (unit-month), traffic wardens (person-month), construction efficiency-loss compensation, and post-diversion removal and restoration.
- Path B (percentage-rate fallback): where the design is unclear and no specific scheme exists, charge traffic management provisions as a percentage of the divisional-work BOQ total per local standards (rates differ by region; e.g., one local standard charges 2%, for reference only).
Applicable Boundaries
Applies to municipal road/utility/urban-rail construction projects with traffic-relief needs; the quantity method requires an approved project execution plan or special diversion scheme, and the percentage-rate method requires a local standard provision. Efficiency-loss/interference fees require a concrete traffic-maintenance scheme as basis; local rate calibers differ greatly and cannot be applied directly across regions; temporary road/bridge type preliminary items include removal and cleanup — do not omit them in pricing.
Further Reading
See GB/T 50857-2024 "Standard for measurement of municipal works" Appendix M preliminary items (code 041201); GB 50861-2013 "Code for measurement of urban rail transit works" Table N.10 (code 081310); GB/T 50903-2013 "Code for project execution plan of municipal works" Clause 6.7.1; for local calibers see SJG 84-2020 "Consumption standard for municipal maintenance works" general provisions 0.1.12, 0.4.18.