Preliminaries bid at zero - can an increase be claimed at final account? (principle-plus-exception framework, with clarification of Clause 10.3.3)

Ordinary preliminaries bid at zero constitute a lump-sum price and are not reimbursed at final account (GB/T 50500-2024, 6.2.3, 6.1.5, 7.3.1); judicial practice treats this as a concession. 'Recalculation and determination' at final account under 10.3.3 only means recalculating all preliminaries contained in the executed works under Section 7.3 and Chapter 8 - amounts listed in interim settlement by construction stage are not a basis, and the zero bid remains effective. However, a zero bid for mandatory health, safety and environmental (HSE) provisions (railway term: statutory work safety levy (earmarked funds)) violates the non-competitive rule (3.2.5) and must be topped up at the standard rate; substantive changes caused by variations (7.4.4, implementation plan subject to employer approval) or employer-caused deferred use, dismantling/re-erection, addition or re-provision of preliminary items (3.3.7) may be adjusted through the prescribed procedure.

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准(第3.2.5、3.3.7、6.1.5、6.2.3、6.2.6、7.3.1、7.4.4、10.3.3条)
  • TB 10801-2024(铁路口径安全生产费,第3.11.11条)

Topic Positioning

Whether preliminaries bid at zero at tender can be recovered at final account is a high-frequency issue in final account audits and cost disputes. This card sets out the complete principle-plus-exceptions framework with the supporting clauses and clarifies the common misreading of the 'recalculation and determination' of preliminaries under Clause 10.3.3.

Core Conclusions

General principle: preliminaries are on a lump-sum basis (Clause 3.3.7: 'the preliminaries are on a lump-sum basis, and the contractor shall bear the risk of increases in preliminaries caused by its own adjustments to the construction method statement ... except for variations, works within provisional sums that could not be fully foreseen or specified, and deferred use, dismantling/re-erection, addition or re-provision of preliminary items provided by the contractor caused by the employer ... no other adjustment shall be made'); item-priced items are lump-sum and shall not be adjusted in construction payment settlement (interim + final) (Clause 6.2.3, 'unless otherwise agreed in the contract'); the completeness and accuracy of the bill of preliminaries and the risk of its pricing being unreasonable rest with the bidder (Clause 6.1.5); preliminary items in the priced bill of quantities (BOQ) shall not be measured or adjusted (Clause 7.3.1, with only five exceptions: (i) preliminary works listed in the divisional BOQ and items contractually subject to measurement; (ii) statutory safety provisions per the contract; (iii) changes in preliminary items caused by variations; (iv) changes in preliminary items caused by errors and omissions in the BOQ; (v) changes in preliminary items caused by works within provisional sums that could not be fully foreseen or specified; the preliminaries of specialist subcontracted works within provisional sums for nominated specialist subcontract works are already included in the subcontract total and shall not be measured again). Judicial practice is consistent: a zero bid is deemed to have been absorbed into other prices or a voluntary concession, and later claims for an increase are generally not supported; a zero bid is not an omission from the BOQ and cannot be recovered on the ground of an 'omission'.

Key clarification (Clause 10.3.3): at final account 'the employer and contractor shall recalculate and determine the preliminaries and the main contractor's attendance and coordination provisions in the documents for interim settlement by construction stage', but the same clause provides that 'preliminaries listed in interim settlement by construction stage shall not serve as the basis for final account' - the recalculation computes all preliminaries contained in the executed works (including adjustments to statutory safety provisions) under Section 7.3 and Chapter 8; it does not change the effect of a zero bid, i.e. a lump sum of zero, and cannot be invoked to recover zero-bid preliminaries.

Three exceptions allowing an increase: (i) a zero bid for statutory safety provisions (railway term: statutory work safety levy (earmarked funds)) - Clause 3.2.5 makes it a non-competitive item whose pricing must comply with national, provincial and sectoral regulations; Clause 6.2.6 likewise provides that when the bidder prices autonomously, 'statutory safety provisions shall comply with national, provincial and sectoral regulations'; a zero bid violates the non-competitive rule and must be topped up at the standard rate; (ii) changes in preliminary items caused by variations - under Clause 7.4.4, measured per 'the implementation plan prepared by the contractor specifically for the variation and approved by the employer, or the content actually occurring'; new measures are measured per the types, actual quantities and usage durations of new temporary works and the models, numbers and consumed plant-shifts of new construction plant in the approved plan; the increased costs of deferred use of existing preliminary items and management staff caused by variations off the critical path may be left unmeasured (deemed included in the contract total); before a variation, the implementation plan must be submitted in writing and approved by the employer - late submission may be deemed a waiver of rights; (iii) employer-caused deferred use, dismantling/re-erection, addition or re-provision of preliminary items - the increased costs shall be borne by the employer per Clause 3.3.7.

Applicable Boundaries

Applies to general employer-contractor projects priced on a bill of quantities basis (GB/T 50500-2024); where the contract expressly provides a lump sum or otherwise regulates adjustment of preliminaries, ordinary preliminaries have virtually no room for increase (Clauses 6.2.3 and 7.3.1 both yield to contrary agreement). The exception for mandatory health, safety and environmental (HSE) provisions presupposes that they are separately listed as required and are a non-competitive cost; sectoral works such as railway works follow sectoral pricing rules (for the railway treatment of the statutory work safety levy, see TB 10801-2024). GB/T 50500-2024 is a recommendatory standard; specific contractual agreements prevail; determination follows the tender documents, contract clauses and the text of the standard.

Further Reading

See GB/T 50500-2024, Clauses 3.2.5, 3.3.7, 6.1.5, 6.2.3, 6.2.6, 7.3.1, 7.4.4 and 10.3.3 and Chapter 8 (Section 8.9 valuation of variations; 8.2.2/8.2.3 adjustment for errors and omissions in the BOQ; 7.7.2 provisional sums); for measurement exceptions for preliminary items and procedural time limits, see Clauses 7.2.1/7.2.2 and 8.9.4-8.9.7; for the railway treatment of the statutory work safety levy, see TB 10801-2024, Clause 3.11.11; for judicial positions, compare the Supreme People's Court Interpretation (I) on Legal Issues Concerning the Trial of Cases of Construction Project Construction Contract Disputes and related judgments.