Engineering Knowledge Cards.
Confidence HighUpdated 2026-10-25

Within preliminaries: the composition, charging method and calculation bases of mandatory HSE provisions (statutory safety provisions), temporary works and site establishment costs, and the additional cost of night work, compared; plus the clause basis of the non-competitive status of mandatory HSE provisions and the item listing rules

Mandatory HSE provisions comprise four heads - environmental protection, site order, safe construction, and temporary works and site establishment (Jian Ban [2005] No. 89 article 4 citing Jian Biao [2003] No. 206); temporary works cost is thus a sub-head and must not be listed again as a separate item and double charged. GB/T 50500-2024 clause 3.2.5 makes statutory safety provisions a non-competitive item, and GB 50722-2011 clause 5.2.9 provides that mandatory HSE provisions and work injury insurance for migrant workers must not be treated as competitive costs: the tenderer may not require a discount on them and tenderers may not subject them to market competition. All three heads are lump-sum preliminaries not readily measurable, charged as calculation base x percentage rate; the base for mandatory HSE provisions is the quota base price (norm-based elemental works cost plus measurable preliminaries), the norm-based labour cost, or the norm-based labour cost plus norm-based plant cost; the additional cost of night work is charged on the base of the labour and plant costs incurred for the night work, and only where night work actually occurs under technologically required continuous construction or an approved night work plan may it be charged (statutory night runs 22:00 to 6:00 the next day).

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准 第2.0.4条、第3.2.5条
  • GB 50722-2011 城市轨道交通建设项目管理规范 第5.2.9条
  • GB/T 50875-2013 工程造价术语标准 第2.2.52条、第2.2.53条
  • 建办〔2005〕89号 建筑工程安全防护、文明施工措施费用及使用管理规定 第四、五、六条
  • 建标〔2003〕206号 建筑安装工程费用项目组成
  • TB 10801-2024 铁路基本建设工程设计概(预)算编制办法 第3.6节、第3.11.11条
  • TB 10811 铁路基本建设工程设计概(预)算费用定额
  • 湖北省建筑安装工程费用定额(2024)
  • 陕西省建设工程费用规则(2025)
  • 中华人民共和国噪声污染防治法 第八十八条
  • 中华人民共和国环境噪声污染防治法 第三十条

Topic positioning

The three preliminary heads most often confused in works pricing - mandatory HSE provisions (renamed 'statutory safety provisions' in GB/T 50500-2024; 'statutory work safety levy' in railway terminology), temporary works and site establishment costs, and the additional cost of night work - what each contains, on what premise and base each is charged, and the clause-level basis and item listing rules for the non-competitive status of mandatory HSE provisions. Applicable to preliminaries listing under BOQ or quota pricing, tender document preparation and bid review.

Core conclusions

1. Hierarchy: temporary works cost is not an independent preliminary item parallel to mandatory HSE provisions

Article 4 of Jian Ban [2005] No. 89, Provisions on the Administration and Use of Costs of Safety Protection and Site Order Measures in Building Works: the costs of safety protection and site order measures in building works comprise the site order cost, environmental protection cost, temporary facilities cost and safe construction cost contained in the measure costs of the Composition of Costs of Building and Installation Works (Jian Biao [2003] No. 206); 'of which the safe construction cost comprises the costs of edge protection, opening protection, crossing work and work at height, the provision costs of works involving significant hazards and other costs, determined by local construction administration authorities in light of local conditions'.

Local cost norms are to the same effect: item 1 of preliminaries, 'mandatory HSE provisions', subdivides into (1) environmental protection cost, (2) site order cost, (3) safe construction cost and (4) temporary works cost; item 2 is the additional cost of night work (item 3 re-handling cost, item 4 winter and rainy season additional cost). So under building / municipal BOQ pricing, temporary works cost is a sub-head of mandatory HSE provisions; the three heads are 'parallel' only at the level of cost composition description, and in listing items the temporary works cost must not be pulled out of mandatory HSE provisions as a separate line and double charged.

Terminology basis: GB/T 50875-2013 clause 2.2.52, 'mandatory HSE provisions: preliminary costs incurred by the contractor during construction of the project to ensure safe and orderly construction and to protect the environment on and off site'.

The railway position differs: TB 10801-2024 clause 3.6.2 provides that railway construction measure costs comprise the winter and rainy season additional cost, the night work additional cost, the minor temporary works cost, the tools, instruments and meters usage cost, the survey setting-out re-check / works handover / site clearance cost, the site order and construction environmental protection cost, and the protection of completed works and equipment cost; while the 'statutory work safety levy' is listed under clause 3.11.11, 'other costs' - so in railways the (minor) temporary works cost and the statutory work safety levy sit in different cost chapters; the terminological correspondence is 'mandatory HSE provisions - railway statutory work safety levy'.

2. The four components of mandatory HSE provisions (named)

  1. Environmental protection cost: costs needed on the construction site to meet the requirements of the environmental authorities, i.e. to reach the environmental and hygiene standards set by the national environmental authority and to improve production conditions and the working environment.
  2. Site order cost: costs needed for orderly site conditions during construction.
  3. Safe construction cost: costs needed to purchase and update construction safety protection appliances and facilities and to improve work safety conditions, per the current national construction safety standards and relevant provisions.
  4. Temporary works cost: costs of the temporary buildings, structures and other temporary facilities for living and production that the contractor must erect to construct the works, including erection, maintenance, removal, clearance or amortisation.

Under some local cost norms, mandatory HSE provisions also contain a fifth head, 'work safety liability insurance': commercial insurance under which the insurer compensates personal injury and related economic loss from work safety accidents occurring to the insured works and provides accident prevention services for the insured works.

Specific content within lump-sum preliminaries (local norm listing): safety warning signs, the five boards and one chart (site notice boards and site layout chart), company marking, site appearance (excluding ground hardening), material stacking, refuse clearance (to the designated on-site point), site fire prevention, etc.; edge protection of floors, roofs and balconies, protection of access openings, protection of reserved openings, protection of hoistway entrances, etc.

3. Enumeration of temporary works cost components

Living / production temporary facilities: canteen, kitchen, toilets, clinic, temporary cultural and welfare rooms, temporary store, processing yard, mixing platform, temporary simple water tower, water tank, etc.

Erection, maintenance, removal or amortisation costs of temporary facilities: temporary water supply piping, temporary power lines, minor temporary facilities, etc.

Site-type items: within the prescribed range of the construction site (where unspecified, within 50m outside the outer axis lines of the building), the laying, maintenance and removal of temporary simple roads; the building, maintenance and removal of temporary drainage ditches and drainage facilities; the costs of erecting, maintaining, removing or amortising other temporary facilities.

Railway position (minor temporary works cost): includes the site earthworks, ground treatment, hardened surface and masonry costs of minor temporary facilities, and the costs of erection, relocation, dismantling, maintenance, amortisation and removal and restoration; land-related costs arising from building minor temporary facilities and using temporary construction sites - land rent, crop compensation, relocation compensation and reinstatement - but excluding the land-related costs of the production areas of temporary stations and yards within heavy temporary works.

4. Composition of the additional cost of night work

GB/T 50875-2013 clause 2.2.53: 'additional cost of night work: preliminary costs arising from night work, namely night shift allowances, reduced efficiency of night work, amortisation of night work lighting equipment and lighting electricity.' Local norms phrase it as night shift allowance, night work reduced efficiency, and amortisation of night lighting equipment and lighting electricity; it also includes the costs of installing, dismantling, maintaining and using lighting installations, and the reduced efficiency of labour and plant, where construction occurs in parts without natural light such as underground buildings, sealed dark rooms or artificial rock caves.

Railway position (TB 10801-2024 clause 3.6.2 paragraph 2): the relevant additional costs arising where works must proceed continuously at night or where ballast and track are laid, wires and cables laid or overhead contact lines erected in tunnels - reduced efficiency, night shift allowances, and additional lighting installations (including their erection and removal, amortisation, maintenance, and fuel and electricity).

5. The binding determination that mandatory HSE provisions are non-competitive (clause numbers)

GB/T 50500-2024 clause 3.2.5, original text: 'Statutory safety provisions in the bill of preliminaries shall be priced per the relevant provisions of the state and of provincial and industry authorities. Statutory safety provisions in the bill of preliminaries are non-competitive items; their pricing shall comply with the relevant provisions of the state and of provincial and industry authorities.'

The term is defined in GB/T 50500-2024 clause 2.0.4: 'statutory safety provisions: costs of the measures adopted by the contractor, in performing and completing the works in accordance with the work safety requirements of the state, the industry and local authorities, to secure the safety of construction production.' 'Statutory safety provisions' include the work safety requirements set by the employer in the tender documents and agreed in the contract.

GB 50722-2011 clause 5.2.9, original text: 'Mandatory HSE provisions and work injury insurance for migrant workers in the bill of preliminaries must not be treated as competitive costs. The Provisions on the Administration and Use of Costs of Safety Protection and Site Order Measures in Building Works (Jian Ban [2005] No. 89) bring mandatory HSE provisions within the scope of national mandatory standards, and their cost standards are not open to competition. This clause provides that mandatory HSE provisions in the bill of preliminaries shall be priced per the cost standards set by national or provincial or industry construction authorities; the tenderer may not require tenderers to discount this cost, and tenderers may not subject this cost to market competition. Safe construction costs in the preliminaries bill include the site order cost, environmental protection cost, temporary facilities cost and safe construction cost of the measure costs under the Composition of Costs of Building and Installation Works (Jian Biao [2003] No. 206).' The clause also cites the State Council Opinions on Resolving Migrant Worker Issues (Guo Fa [2006] No. 5) and the Regulations on Work-Related Injury Insurance (State Council Decree [2003] No. 375), making clear that the cost of work injury insurance for migrant workers must not enter market competition at tender.

Three hard determinations follow: (1) the tenderer may not require tenderers to discount or concede it (cutting the rate is a violation); (2) tenderers may not bring it into competitive pricing (quoting '0' or an arbitrary reduction is non-compliant); (3) the cost shall be calculated at the prescribed percentage rate or cost standard, with the floor set by article 6 of Jian Ban [2005] No. 89 - a tenderer's price for safety protection and site order measures must not be lower than 90% of the total cost calculated at the rate determined by the construction cost agency at the expected location of the works, and the tender documents shall list the schedule of safety protection and site order measure items separately in light of actual conditions, with tenderers pricing them separately. Temporary works cost is fixed by law together with mandatory HSE provisions and must not be conceded separately; the additional cost of night work is outside this head - it is self-priced per the project execution plan and is competitive.

6. Charging methods and calculation bases

Measurable preliminaries under the national measurement standards: preliminaries = sum of (preliminaries quantity x all-in unit rate).

Preliminaries not readily measurable (lump-sum, by percentage rate):

  • Mandatory HSE provisions = calculation base x mandatory HSE provisions rate (%). The base shall be the quota base price (norm-based elemental works cost plus the measurable preliminaries within the quota), the norm-based labour cost, or (the norm-based labour cost plus the norm-based plant cost); the rate is determined comprehensively by the construction cost agency per the characteristics of each discipline.
  • Additional cost of night work = calculation base x additional night work cost rate (%); re-handling cost and the winter and rainy season additional cost are of the same type (calculation base x the corresponding rate).
  • Railway: construction measure costs = (base-period labour cost + base-period plant and small tools cost) x construction measure cost rate, the rate per TB 10811, Rate Norms for Design Estimates and Budgets of Railway Capital Construction Works (TB 10801-2024 clauses 3.6.3 and 3.6.4).
  • Railway statutory work safety levy: funds withdrawn by the contractor at the prescribed rate, charged in costs (expenses) and dedicated to improving the work safety conditions of the contractor or the project; the scope of use is limited to the ten categories listed in table 3.11.11 of TB 10801-2024 (improvement, renovation and maintenance of safety protection facilities and equipment; emergency rescue equipment; detection, assessment and monitoring of major hazard sources; safety inspection, assessment, evaluation, consultation and standardisation; safety protection articles for site workers; work safety publicity, training and education and hazard reporting rewards; promotion of new technologies, standards, processes and equipment; testing, inspection and calibration of safety facilities and special equipment; work safety liability insurance; other expenditure directly related to work safety); items in the table must not be double-listed elsewhere in the design estimate or budget; calculation follows TB 10811.

7. Trigger conditions for night work and the boundary of 'night'

Noise Pollution Prevention and Control Law of the People's Republic of China, article 88, item (2): 'night means the period from 10 p.m. to 6 a.m. the next morning; people's governments of cities divided into districts and above may separately prescribe the start and end of night in their own areas, the night period being eight hours.'

The former Environmental Noise Pollution Prevention and Control Law of the People's Republic of China, article 30: 'within areas of concentrated noise-sensitive buildings in urban areas, construction work producing environmental noise pollution at night is prohibited, except for rush repair and rescue work and operations that must proceed continuously by reason of production technology or special need. Where continuous operation is necessary for special need, certification by the people's government at or above the county level or its relevant authority must be obtained. Night work under the preceding paragraph must be announced to nearby residents.'

Charging trigger: the additional cost of night work is not 'charged automatically once 22:00 passes'; night work must actually occur together with either technologically required continuous construction or an approved night work plan or certificate - the railway position confines it more precisely to 'works that must proceed continuously at night or where ballast and track are laid, wires and cables laid or overhead contact lines erected in tunnels'. Hence, in claims or listing, support should rest on the approved project execution plan, the night work plan, government or authority certificates and site records; normal day-shift work must not be charged.

8. Quick reference for item attribution

Cost Charging premise Composition Charging method and base Competitive status
Mandatory HSE provisions (statutory safety provisions / railway statutory work safety levy) Charged once the works occur, per the provisions of the state and of provincial and industry authorities Environmental protection + site order + safe construction + temporary works (some localities add work safety liability insurance) Calculation base x rate; base = quota base price (norm-based elemental works cost + measurable preliminaries) / norm-based labour cost / (norm-based labour cost + norm-based plant cost); railway per TB 10811 Non-competitive
Temporary works cost Living and production temporary facilities the contractor must erect to construct See the enumeration in section 3 above; includes erection and removal, maintenance, dismantling, clearance or amortisation Contained within the mandatory HSE provisions rate, not listed separately Fixed by law together with mandatory HSE provisions, no separate concession; in railways an independent construction measure item (minor temporary works cost)
Additional cost of night work Night work actually occurring under technologically required continuous construction or an approved night work plan (statutory night 22:00 to 6:00 next day) Night shift allowance + night reduced efficiency + lighting equipment amortisation + lighting electricity Calculation base x rate; charged only on the labour and plant cost base corresponding to the night work; railway = (base-period labour cost + base-period plant and small tools cost) x rate Competitive, self-priced per the project execution plan

Applicable boundaries

  • Terminology changes with the pricing basis: GB/T 50500-2024 uses 'statutory safety provisions' (clause 2.0.4); local 2024/2025 cost norms still largely follow 'mandatory HSE provisions plus the four components'; railways use 'statutory work safety levy'. In compilation, terminology and rates must align with the pricing basis in force and must not be mixed across bases.
  • 'Temporary works cost not listed separately' applies only where local or industry practice makes it a sub-head of mandatory HSE provisions; railways list 'minor temporary works cost' as an independent construction measure item, excluding heavy temporary works and transitional works (accounted in other chapters).
  • The 22:00 to 6:00 night boundary is the statutory period under the noise law; cities divided into districts and above may prescribe otherwise; in pricing, the contract or norm agreement and the approved night work plan ultimately govern, and the statutory night period must not be equated directly with the charging period.
  • The 90% pricing floor comes from Jian Ban [2005] No. 89 on the pricing of safety protection and site order measures; implementation follows current local provisions; whether a zero quote can later be topped up is a contract settlement question to be judged under the relevant clauses of the pricing standard.
  • The winter and rainy season additional cost, the re-handling cost and the survey, setting-out and re-check cost are also preliminaries, but their trigger conditions and exceptions have their own provisions (e.g. warm-shed construction, secondary handling of finished components) and are outside this card's three heads.

Further reading

  • GB/T 50500-2024, Standard for Valuation with Bill of Quantities of Construction Works: clause 2.0.4 (term: statutory safety provisions), clause 3.2.5 (statutory safety provisions are non-competitive)
  • GB 50722-2011, Code for Management of Urban Rail Transit Construction Projects, clause 5.2.9 (contract management: mandatory HSE provisions and migrant worker injury insurance must not be competitive costs)
  • GB/T 50875-2013, Standard for Construction Cost Terminology: clause 2.2.52 (mandatory HSE provisions), clause 2.2.53 (additional cost of night work)
  • Jian Ban [2005] No. 89, Provisions on the Administration and Use of Costs of Safety Protection and Site Order Measures in Building Works, articles 4, 5 and 6; Jian Biao [2003] No. 206, Composition of Costs of Building and Installation Works
  • TB 10801-2024, Compilation Rules for Design Estimates and Budgets of Railway Capital Construction Works: section 3.6 construction measure costs (3.6.1 to 3.6.4), clause 3.11.11 statutory work safety levy and table 3.11.11 scope of use; with TB 10811, Rate Norms for Design Estimates and Budgets of Railway Capital Construction Works
  • Local cost norms: Hubei Building and Installation Works Cost Norm (2024), preliminaries content and the 'calculation base x rate' formula; Shaanxi Works Cost Rules (2025), detail of the temporary works cost and night work additional cost composition
  • Noise Pollution Prevention and Control Law of the People's Republic of China, article 88; former Environmental Noise Pollution Prevention and Control Law, article 30

Keywords