Railway estimate/budget preliminaries and on-costs (indirect costs): composition, calculation base, and percentage rates (TB 10801-2024 Clauses 3.6/3.9; TB 10811-2024 Table 2.9.1)

Preliminaries (7 items: winter (cold-weather) and rainy-season construction increase; night-work increase; minor temporary works cost; tools, utensils, instruments and meters cost; setting-out re-survey, work handover, and site clearing; mandatory health, safety and environmental (HSE) provisions and construction environmental protection; protection of completed works and equipment) = (base-period labour cost + base-period plant and small tools cost) x preliminaries percentage rate; on-costs (indirect costs) = overheads (company and site; 12 items) + profit, on the same base (base-period labour cost + base-period plant and small tools cost) x on-costs percentage rate (TB 10811-2024 Table 2.9.1; 16 work categories, 8.9%-58.6%).

Applicable Codes

  • TB 10801-2024 · Measures for Compilation of Design Estimates and Budgets of Railway Capital Construction Projects 第2.6、3.6、3.9条
  • TB 10811-2024 · Fee schedule for design estimates and budgets of capital railway works 第2.9节Table 2.9.1

Topic Positioning

This card covers the detailed composition, calculation bases/formulas, and percentage rate values of "preliminaries" and "on-costs (indirect costs)" in railway capital-construction design estimates (budgets), per Clauses 2.6, 3.6, and 3.9 of TB 10801-2024 "Measures for Compiling Design Estimates (Budgets) of Railway Capital Construction Works" and Section 2.9 of TB 10811-2024 "Norms for On-Costs and Expenses for Design Estimates (Budgets) of Railway Capital Construction Works".

Core Conclusions

  1. Position in the fee system (TB 10801-2024 Tables 2.6.1/2.6.2): cost of works (construction and installation) = direct costs + on-costs; direct costs = direct work costs + preliminaries + special construction increase; on-costs = overheads (company and site) + profit. In the item-estimate calculation program: item 12 preliminaries = [(1)+(3)] x preliminaries percentage rate ((1) = base-period labour cost; (3) = base-period plant and small tools cost); item 15 on-costs = [(1)+(3)] x on-costs percentage rate; item 16 item-estimate value = direct costs + on-costs. The two share the same base and differ only in percentage rate.
  2. Preliminaries (Clauses 3.6.1-3.6.2): expenses of a technical, welfare, and environmental-protection nature incurred before and during construction for completing the railway works. Seven items: (1) winter (cold-weather) and rainy-season construction increase — added costs of cold-proofing, insulation, rain-proofing, damp-proofing, and protection measures per the codes during winter and rainy seasons, and of reduced labour and machinery efficiency without changed technical processes; (2) night-work increase — reduced efficiency, night-shift allowances, and added lighting installations (installation/removal, amortization, maintenance, fuel, and power) for work that must proceed continuously at night or inside tunnels (ballast and track laying, wire and cable laying, catenary erection); (3) minor temporary works cost — costs of building minor temporary works and using temporary construction sites for construction and construction transport (including temporary operation control), covering temporary living and residential buildings; cultural-educational and public buildings; office and production buildings and ancillaries; in-site transport spur roads (including temporary bridges and culverts); light rails; gantry-crane travel tracks of tonnage under 10 t or length under 100 m; power lines from trunk lines to the site or camp; local communication lines; water-supply lines below heavy temporary standards; temporary water installations (water towers, pools, wells under 50 m deep); temporary drainage, sedimentation, and oil-separation pools; drilling slurry and sedimentation pools; temporary servicing installations; temporary signals, communications, and power; temporary station-yard structures; catenary pre-assembly yards; pole storage yards; scattered precast-component storage yards; rebar (steel-structure) processing yards; and erecting-machine and similar large-machinery assembly/dismantling sites and ancillaries; the cost includes the earthwork, ground improvement, hard surfacing, and masonry of these temporary works, their erection, relocation, dismantling, maintenance, amortization, and restoration, and land-related costs (land rental, crop compensation, relocation compensation, reclamation) — excluding land-related costs of the production areas of heavy temporary stations; (4) tools, utensils, instruments and meters cost; (5) setting-out re-survey, work handover, and site clearing; (6) mandatory health, safety and environmental (HSE) provisions and construction environmental protection — noise, dust, and vibration-interference control, and domestic-waste removal and disposal; (7) protection of completed works and equipment — costs of protecting completed works and equipment before taking-over (completion acceptance).
  3. On-costs (Clauses 3.9.1-3.9.2): expenses incurred by the contractor in organizing construction production and business management = overheads (company and site) + profit. Overheads (company and site) has 12 items: management personnel wages (basic wages, allowances and subsidies, auxiliary wages, staff welfare, labour protection, five insurances and one housing fund, union funds, staff education funds); office expenses; travel and transport; fixed-asset use; tools and utensils use; inspection and testing (excluding research tests on new structures and materials, tests on materials with conformity certificates and destructive tests required by the employer, employer-commissioned external tests, and tests beyond the acceptance standards required by design); property insurance; taxes and duties (property tax, vehicle and vessel tax, land-use tax, stamp duty, environmental protection tax, urban maintenance and construction tax, education surcharge, local education surcharge); contractor mobilization/demobilization and site transfer (excluding that of special machinery such as shield machines and TBMs); labour insurance; finance charges; others (technology transfer, technology development, business entertainment, greening, advertising, notarization, legal counsel, audit, consulting, intangible-asset amortization, bidding, contractor's in-house norms measurement, enterprise/project information-management system construction and use, works-acceptance cooperation, integrated testing and commissioning cooperation, etc.).
  4. Calculation and percentage rates: preliminaries = (base-period labour cost + base-period plant and small tools cost) x preliminaries percentage rate, per TB 10811-2024 (Clauses 3.6.3-3.6.4); on-costs = (base-period labour cost + base-period plant and small tools cost) x on-costs percentage rate (Clause 3.9.3). On-costs percentage rates (TB 10811-2024 Table 2.9.1, 16 categories): manually executed earthworks 14.3%; mechanically executed earthworks 20.6%; the "incremental haul" portion of the truck-hauling earthwork quota norms 9.3%; substructures of super-major and major bridges 17.7%; precast concrete beams 33.4%; cast-in-place concrete beams 25.8%; hauling and erecting simply supported concrete box beams 8.9%; open-cut and shed tunnels with self-quarried sand and gravel 21.1% (including TBM-driven tunnels, excluding shield-driven tunnels); subgrade appurtenant works (excluding appurtenant earthworks) 25.9%; frame bridges, highway and medium/small bridge substructures (including appurtenances), culverts, ferry terminals, and other building works, and building/installation works of information, power, water supply and drainage, locomotive, rolling stock, EMU, track-maintenance, and station-yard works 25.4%; track laying, turnout laying, erection of other concrete beams, steel beams, steel pipe arches, steel structures, station buildings, etc. 58.6%; ballast laying 38.7%; ballastless track bed and track-related works 31.4%; signaling, disaster monitoring, power, and other structures building/installation works 36.2%; electric traction power-supply works 47.0%; shield-driven tunnels 19.5%. Note: heavy temporary works are charged at the listed percentage rate of the same formal-work category x 0.8; transition works at the listed percentage rate of the same formal-work category.

Applicable Boundaries

Applies to railway capital-construction estimate/budget compilation (the TB 10801-2024 + TB 10811-2024 system); not applicable to highway (JTG 3830), building, or municipal pricing systems. Both fees use base-period labour cost + base-period plant and small tools cost as base (excluding materials and price differences); note that the special construction increase uses compilation-period labour and plant as its base — a different basis. The 2024 edition no longer lists statutory levies and fees separately — workers' five insurances and one housing fund, union funds, and staff education funds are folded into comprehensive labour costs and overheads (company and site) (the management-wages item); mind this when comparing with older editions. The preliminaries percentage rate is further selected by 16 work categories x the preliminaries regional division (TB 10811 Appendix B region numbers); this card does not list preliminaries percentage rate values. The 0.8 heavy temporary factor for on-costs and the 0.45 heavy temporary factor for preliminaries are coefficients of two different items — do not mix. Percentage rates change with quota norms revisions; verify the current effective edition in use.

Further Reading

See TB 10801-2024 "Measures for Compiling Design Estimates (Budgets) of Railway Capital Construction Works": Section 2.6 (fee composition and Table 2.6.2 item-estimate calculation program), Section 3.6 (preliminaries), Section 3.9 (on-costs), Section 3.7 (special construction increase — companion card); TB 10811-2024 "Norms for On-Costs and Expenses for Design Estimates (Budgets) of Railway Capital Construction Works": Section 2.9 (Table 2.9.1 on-costs percentage rates), Section 2.6 (preliminaries percentage rate Table 2.6.1), and Appendix B (preliminaries regional division). Related extensions: heavy temporary works and transition works (TB 10801 Section 3.8) to fix the minor/heavy temporary works boundary; winter (cold-weather) works criteria and winter increase estimation (the winter (cold-weather) and rainy-season increase being the first preliminaries item).