Railway estimate compilation scope and unit division: the total/comprehensive/single-item three-level system (TB 10801-2024 Sections 2.2, 2.3)
Per TB 10801-2024 Sections 2.2-2.3: total estimates divide scope by 7 principles (cross-province/asset ownership, phased construction, multiple design institutes, hubs, marshalling yards/logistics centers/EMU depots, station buildings using provincial local quotas, other special cases); comprehensive estimates share the scope of the corresponding total estimate, compiled by Appendix A chapters with empty chapters keeping numbers and names; single-item estimates are the basis of comprehensive/total estimates, their units divided by the total scope plus the chapter table by work class — 6 classes requiring separate single-item estimates: bridges with max foundation water depth >= 10 m, or 100 m+ spans, or orthotropic-plate steel girders, or max pier height >= 50 m; tunnels 4000 m+ or with auxiliary galleries, multi-track, or Class I risk; large buildings; beam yards and other heavy temporary works; etc.
Applicable Codes
- TB 10801-2024 · Measures for Compilation of Design Estimates and Budgets of Railway Capital Construction Projects
Topic Positioning
Reading TB 10801-2024 Section 2.2 "Compilation scope and units" and Section 2.3 "Compilation depth and requirements": the scope division principles and unit rules of total, comprehensive, and single-item estimates, including the concrete thresholds of the 6 classes "requiring separate single-item estimates" in 2.2.5 (bridge depth/span/pier height, tunnel length, large buildings, heavy temporary works). For scoping railway preliminary-design estimates and construction-drawing based budgets (pre-tender estimates).
Core Conclusions
1. Three-level system and document positioning (2.2.1-2.2.3)
- The total estimate reflects the investment scale and composition within its scope; total budget units match total estimate units (2.2.1).
- The comprehensive estimate concretely reflects the works cost total and composition within one total estimate scope; its scope matches the corresponding total estimate (2.2.2).
- The single-item estimate is the basis of comprehensive and total estimates, the main document detailing each work class and major/special sites (2.2.3).
2. Seven scope principles for total estimates (2.2.1)
- Works crossing provinces or with assets under different owners compile separately by jurisdiction (or asset ownership); where truly impossible, propose investment-division principles and ratios;
- Phased projects compile by phase scope;
- Where two or more design institutes share a project, each compiles its part, the lead institute assembling the total;
- Hub works bounded by the hub; approach works, connecting and relief lines may compile separately as needed;
- Marshalling yards, logistics centers, EMU depots, and integrated property development compile separate total estimates;
- Passenger station buildings, complexes, canopies, and footbridges using provincial local quotas compile separate total estimates;
- Other special cases may divide scope per project needs.
3. Single-item estimate contents (2.2.4)
- Construction-installation single-item estimates: labour cost, material cost, plant and small tools cost, out-of-price freight and handling charges, price differentials, fill material cost, preliminaries, special construction increases, and on-costs (indirect costs);
- Equipment single-item estimates: equipment cost and equipment freight and handling charges.
4. Single-item estimate units (2.2.5) Units divide per the total estimate scope, combined with the comprehensive chapter table, by work class, complying with 6 provisions (the following require separate single-item estimates):
- Bridges with max foundation water depth >= 10 m, with 100 m+ spans, with orthotropic-plate steel girders or other special structures, or max pier height >= 50 m (the OCR shows a garbled character; it should be "orthotropic-plate steel girder");
- Single/double-track tunnels 4000 m+ or with auxiliary galleries, multi-track tunnels, and Class I risk tunnels;
- Dispatch buildings, repair sheds, preparation sheds, inspection sheds, underfloor wheel-lathe sheds, county-level-or-above passenger station buildings (incl. complexes), and other large buildings;
- Beam (storage) yards, track-laying bases, sleeper precasting yards, track-slab precasting yards, and other heavy temporary works;
- New-technology works with large investment and complexity;
- Sites whose investment is borne by investors other than the project company.
5. Assembly rules and depth (Section 2.3)
- Comprehensive estimates assemble single-item estimates per Appendix A order; details may be adjusted; chapters without costs keep their numbers and names; multiple comprehensive estimates assemble a summary table (2.3.3).
- Total estimates assemble comprehensive estimates by chapter; chapters without costs keep numbers and names when outputting; multiple totals assemble a summary (2.3.4).
- Depth matches design stage and detail standards (2.3.1). Table 2.3.2: subgrade earthworks (earth and rock) and ancillary works use budget quota norms at both stages based on quantities; buildings, communication/signalling/disaster monitoring/power/electric traction power supply, water supply and drainage/depot/rolling stock/EMU/track maintenance/station/other buildings and equipment use preliminary estimate or budget quota norms at preliminary design (from quantities or design standards, scale, structural type, equipment capacity) and budget quota norms at construction-drawing design; heavy temporary works, transition works, and temporary land reclamation are compiled per detailed work items and the project execution plan (construction methodology and site organization) — preliminary estimate or budget quota norms at preliminary design, budget quota norms at construction-drawing design.
Applicable Boundaries
- Applies to railway capital construction (new, reconstruction, etc.) estimate scope and unit definition per TB 10801-2024; budget units match estimate units (2.2.1).
- This card answers only "by what scope and unit"; cost methods (pricing by applying quota line items, adjustment for price differentials, percentage rates) are in companion cards.
- The 2.2.5 six classes are hard thresholds but not exhaustive — 2.2.1 item 7 and 2.2.5 item 5 are catch-alls.
- The bridge/culvert, tunnel, and track rows of Table 2.3.2 are missing from the current text; this card does not speculate; chapter detail adjustments follow Appendix A.
- Station buildings using provincial local quota norms are compiled separately from works under the railway quota manuals — keep the bases distinct.
Further Reading
- TB 10801-2024 Sections 2.2 (2.2.1-2.2.5) and 2.3 (2.3.1-2.3.4, Table 2.3.2), Appendix A chapter table.
- Companion cost documents: TB 10811-2024 (preliminaries and on-costs percentage rates); TB 10813/10814-2024 discipline quota norms.
- Heavy temporary works single-item estimates and cost attribution — see the referenced card.