Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Railway estimate/budget haul-road cost classification: the dividing standard between heavy temporary works and minor temporary works (preliminaries) (TB 10801-2024 Clause 3.6.2 vs. Clause 3.8.3)

Whether a railway temporary haul road is charged to heavy temporary works or to minor temporary works is decided by "use and location", not by width or other technical parameters: truck haul roads (trunk trucking roads, longitudinal haul roads along the line, and access spurs to major earthwork sites, bridges, tunnels, station buildings, borrow/spoil grounds, self-built sand-gravel (ballast) yards, inter-block traction substations, and temporary yards) and beam-haul roads (built specifically for transporting and erecting large precast concrete beams) are heavy temporary works — sized per the project execution plan (construction methodology and site organization), priced by applying quota items, and listed in Chapter 10 of the composite estimate; "on-site haul roads other than the longitudinal on-site haul road listed under heavy temporary works (including temporary bridges and culverts)" and access spurs to culverts and other works, and to construction camps, material depots, and garages are already included in the preliminaries (minor temporary works cost), charged as a lump percentage rate = (base-period labour cost + base-period plant and small tools cost) x preliminaries percentage rate, and not separately billed.

Applicable Codes

  • TB 10801-2024 · Measures for Compilation of Design Estimates and Budgets of Railway Capital Construction Projects 第3.6.2条、第3.6.3条、第3.8.3条、第3.8.4条、第3.8.7条、App. A
  • TB 10811-2024 · Fee schedule for design estimates and budgets of capital railway works

Topic Positioning

This card answers the cost classification of "temporary haul roads" in railway capital-construction design estimates (budgets): which roads enter the heavy temporary works fee (listed item by item per the project execution plan (construction methodology and site organization) and priced by applying quota items) and which are already included in the minor temporary works cost within the preliminaries (lump percentage rate, not separately billed). The dividing standard is use and location, not technical parameters such as width or length. Basis: Clauses 3.6.2 and 3.8.3 and Appendix A of TB 10801-2024 "Measures for Compiling Design Estimates (Budgets) of Railway Capital Construction Works".

Core Conclusions

I. Roads charged to heavy temporary works (TB 10801-2024 Clause 3.8.3):

  1. Truck haul roads (including temporary bridges, tunnels, and culverts): trunk trucking roads, longitudinal haul roads along the line, and access spurs to the construction points served by truck haulage — major earthwork sites, bridges, tunnels, station buildings, borrow/spoil (rock) grounds, self-built sand-gravel (ballast) yards, inter-block traction substations, and temporary yards.
  2. Beam-haul roads: haul roads built specifically for transporting and erecting large precast concrete beams. Appendix A composite-estimate chapter table, Chapter 10 "Heavy Temporary Works and Transition Works", item (2) Truck haul roads splits into: newly built trunk roads, newly built access spurs, rebuilt (widened) roads (notes all stating "including temporary bridges, culverts, tunnels, and road maintenance costs") and compensation for using existing local roads. Heavy temporary works are sized per the project execution plan (construction methodology and site organization) and priced by applying quota items through the item-estimate procedure (heavy temporary works costs computed per the norms for on-costs and expenses TB 10811, Clause 3.8.7), listed in Chapter 10 of the composite estimate; temporary line/road maintenance per the corresponding TB 10811 quota norms.

II. Roads already included in the preliminaries (minor temporary works) (Clause 3.6.2 item 3, "minor temporary works cost"):

  • "On-site haul roads other than the longitudinal on-site haul road listed under heavy temporary works (including temporary bridges and culverts)";
  • haul-road access spurs to culverts and other works and to construction camps, material depots, garages, etc. (including temporary bridges and culverts);
  • water-supply lines failing the heavy temporary works standard and similar small ancillary facilities. Minor temporary works are not separately billed; the cost is packaged into the preliminaries: preliminaries = (base-period labour cost + base-period plant and small tools cost) x preliminaries percentage rate (Clause 3.6.3), the percentage rate per TB 10811 by work category and region number. Heavy temporary works themselves contain no minor temporary works costs, and their preliminaries percentage rate is the percentage rate of the same formal-work category x 0.45.

III. Confusion trap: technical parameters of haul roads (single-/dual-lane subgrade width, pavement width requirements) are construction standards deciding how the road is built — they are not a criterion for cost classification; do not judge heavy vs. minor temporary works by width.

Applicable Boundaries

  • Applies to railway capital-construction estimate/budget compilation (TB 10801-2024 scope) and to judging haul-road item classification in estimate review.
  • Actual compilation follows the project execution plan (construction methodology and site organization): the design document's "Opinions on Setting Heavy Temporary Works" (road locations, standards, quantities) states which roads enter the heavy temporary works scheme — check the project execution plan first when classifying.
  • Other heavy temporary works items (temporary railway lines, temporary water facilities, temporary power lines >= 6 kV, temporary yards) and other preliminaries contents (winter/rainy season working, night work, tools and implements, etc.) are covered on other cards.
  • Municipal, highway, and other industries have different temporary-road rules (per their own BOQ/quota bases) — do not apply this card.
  • Width and similar construction parameters do not decide cost classification; do not mix them.

Further Reading

  • TB 10801-2024: Clause 3.6.2 (preliminaries composition; haul-road list under the minor temporary works cost), Clause 3.6.3 (preliminaries formula), Clause 3.8.3 (heavy temporary works scope, including truck haul roads and beam-haul roads), Clause 3.8.4 (heavy temporary works cost contents), Clause 3.8.7 (heavy temporary works and transition costs computed per TB 10811), and Appendix A Chapter 10 "Heavy Temporary Works and Transition Works".
  • TB 10811-2024 "Norms for On-Costs and Expenses for Design Estimates (Budgets) of Railway Capital Construction Works": preliminaries percentage rate tables (by work category and region number), heavy temporary works road maintenance quota norms, and the 0.45 factor for heavy temporary works preliminaries percentage rates (commentary).
  • Classification sequence: (1) check whether the project execution plan (construction methodology and site organization) lists the road under heavy temporary works; (2) check the Clause 3.8.3 list (trunk/longitudinal roads, spurs to major sites, beam-haul roads -> heavy temporary works); (3) remaining on-site haul roads and spurs to camps, depots, and garages -> minor temporary works.

Keywords

Cited By