Compiling railway heavy temporary works and transition works costs: definition, compilation depth, and calculation methods (TB 10801-2024 Section 3.8, TB 10811-2024 Section 2.8)
Heavy temporary works comprise 10 categories (railway diversion lines, truck haul roads, girder-transport roads, temporary water supply, temporary power lines >= 6 kV, centralized power generation/substations, temporary communication base stations, temporary yards/stations, tunnel wastewater treatment stations, ferry crossings/wharves, etc.); minor temporary works and land-related costs are not included. Project scales are determined by the project execution plan (construction methodology and site organization); pricing is by applying quota items through the single-item estimate (budget) procedure; the preliminaries percentage rate = same-type formal works x 0.45; borrowed materials carry construction loss, equipment and materials are charged by annual usage percentage rates; diversion line/haul road maintenance costs are listed per the quota norms in TB 10811 Tables 2.8.3 and 2.8.4, booked into Chapter 10 of the composite estimate (chapter 1030).
Applicable Codes
- TB 10801-2024 铁路基本建设工程设计概(预)算编制办法
- TB 10811-2024 铁路基本建设工程设计概(预)算费用定额
- TB 10504-2018 铁路建设项目预可行性研究、可行性研究和设计文件编制办法
Topic Positioning
This card covers the definition, compilation depth, and calculation methods of heavy temporary works and transition works costs in railway capital construction, per 'Measures for compiling design estimates (budgets) of railway capital construction projects' TB 10801-2024 Section 3.8 and Table 2.3.2, and 'Norms for on-costs and expenses for design estimates (budgets) of railway capital construction projects' TB 10811-2024 Section 2.8.
Core Conclusions
- Ten categories of heavy temporary works: railway diversion lines (incl. temporary bridges, tunnels, culverts), truck transport haul roads, girder transport roads, temporary water supply facilities, temporary power lines (>= 6 kV), centralized power generation/substations, temporary communication base stations, temporary yards/stations, tunnel wastewater treatment stations, ferry crossings/pontoon bridges/suspension bridges/overpasses/underpasses; transition works means temporary diversion lines/bridges and transitional station yards adopted to maintain operation when rebuilding existing lines or adding second lines.
- Boundaries: minor temporary works (in-site road lead-ins, gantry-crane runways < 10 t or < 100 m, power lines < 6 kV, etc.) are included in preliminaries; land-related costs (land lease, crops, demolition, reclamation, etc.) are listed under Chapter 1 temporary land use fees — none are listed separately.
- Compilation depth: preliminary design uses estimate (budget estimate) quota norms or budget quota norms, construction-drawing stage uses budget quota norms, both premised on items, scales, and quantities determined by the reviewed project execution plan (construction methodology and site organization).
- Calculation: applying quota items through the single-item estimate (budget) procedure (TB 10811 Clause 2.8.1); preliminaries percentage rate = same-type formal works x 0.45 (except heavy temporary works separately tendered as decided early); borrowing formal-works materials charges construction loss, and using construction-enterprise equipment and materials charges annual usage percentage rates (rails and turnouts/reinforced concrete sleepers/poles/steel crossarms 10%, cast and steel pipes and universal fittings 16%, communication/signaling/power wire materials 30%, transition equipment 25%, optical cables and catenary concrete poles 100% amortized); diversion-line maintenance 23 work-days/(month x km) supplemented by cumulative ballast method; haul-road maintenance earth roads 10, granular trunk lines 16/lead-ins 10 work-days/(month x km).
- Chapter attribution: Chapter 10 of the composite estimate, heavy temporary works and transition works (chapter 1030); sub-items may be added or removed; chapters without costs are retained.
Applicable Boundaries
Applies to railway capital construction project design estimates (budgets); percentage rates and quota norm values are per TB 10811-2024, with compilation-period parameters locked; matters involving operating lines, such as train-interference scope, must be investigated per operating-enterprise rules; this card excludes other cost chapters such as special construction additional fees.
Further Reading
See TB 10801-2024 Section 3.8, Table 2.3.2, Appendix A composite estimate chapter table; TB 10811-2024 Section 2.8 (Table 2.8.2 construction equipment and materials annual usage percentage rates, Table 2.8.3 railway diversion-line maintenance cost quota norms, Table 2.8.4 haul-road maintenance cost quota norms); used with 'Measures for compiling pre-feasibility, feasibility, and design documents of railway construction projects' TB 10504-2018, dedicated chapter on major heavy temporary works.
Keywords
- heavy temporary works
- 大临
- 过渡工程
- 铁路便线
- 养护费
- 施工器材年使用费率
- 概预算编制