Determining amortization cycles and per-cycle amortization cost of consumable formwork materials (railway basic quota basis)

Look up the number of reuses (amortization cycles) in the quota take-off tables (timber 4-20 cycles, steel 50, combined steel formwork 50, precast formwork 75-100, etc.); per-use amortized quantity = first-use quantity ÷ number of reuses (for materials subject to wastage, add first-use quantity × wastage rate; metal members and piping follow the annual use rate); per-use amortized cost = per-use amortized quantity × material unit price. For budget preparation, use the quota contents directly; for cost estimation, recompute using the actual number of reuses.

Applicable Codes

  • TB/T 10821-2024 铁路工程基本定额 Ch. 9

Topic Positioning

This card covers how the number of reuses (amortization cycles) and the per-use amortized cost of turnover materials (formwork, shoring, scaffolding, metal members, etc.) are determined, per Chapter 9 of the railway basic (fundamental) quota manual TB/T 10821-2024; consumption standards in other industries follow the same approach.

Core Conclusions

  1. The number of reuses comes from the quota take-off tables, not from self-set values. Timber: formwork for small cast-in-place members 5, formwork shoring 8, scaffolding 12, bamboo plywood 5, formwork for small precast members 20, sleeper stacks and skid tracks for girder dragging 16, auxiliary dunnage 4. Metal materials: nails 1 (one-off), metal fittings 5-25 (by cast-in-place/precast location), tie rods, bolts and lift hooks 8-25, wire rope 40, steel (rebar, plate, section, pipe, couplers) 50. Steel formwork: combined steel formwork 50 (shoring 85, accessories 25), profiled steel formwork for bridge piers 30, precast T-girders/box girders 75, cast-in-place box/continuous girders 20, large-block formwork for pile caps and spread footings 60, precast pipes 100.
  2. The amortized-quantity formulas fall into three classes: (1) materials without wastage (steel formwork, timber, other track materials): per-use amortized quantity = first-use quantity ÷ number of reuses; (2) materials subject to site handling and operational wastage (combined steel formwork accessories and shoring, plastic formwork, metal materials): per-use amortized quantity = first-use quantity ÷ number of reuses + first-use quantity × wastage rate; (3) metal members and piping, rails and turnouts: amortized quantity = total weight used × one-time erection/dismantling wastage rate + total weight used × annual use rate × years of use (any part of a quarter counts as a full quarter).
  3. Per-use amortized cost = per-use amortized quantity × material unit price (quota base-period price or compilation-period market price).

Applicable Boundaries

Applies to quota-based budget preparation: the quota contents already include amortization at normal reuse cycles—generally no separate calculation is needed; for construction cost estimation, if actual reuse cycles are below the quota values (tight schedule, early retirement), recompute per the actual scheme. Rented turnover materials (rented by day/month/area) are not covered by the amortization formulas. The number-of-reuses figures correspond only to their own quota system; cross-system use requires looking up the respective quota.

Further Reading

See Chapter 9, "Amortization of Auxiliary Structural Materials and Semi-finished Products", of the railway basic (fundamental) quota manual TB/T 10821-2024: Section 1, steel formwork amortization and quantities (including the number of reuses and design steel quantities for combined/profiled/large-block steel formwork in bridge and culvert works), Section 3, timber amortization and quantities, Section 4, metal materials amortization; for detailed amortization coefficients, refer to the quota appendices.