Railway 2024 quota pricing rules for bored-pile steel casings: one-time amortization on water, 8 uses on land, quantities per design weight (TB/T 10823-2024, Volume 2 bridge and culvert works)
TB/T 10823-2024 "Railway works budget quota, Volume 2: bridge and culvert works": over-water steel casings are "amortized once; no separate removal or refurbishment cost; no salvage credit deducted"; land casings (ordinary soils) have the amortization already in the quota (TB/T 10821-2024 sets land steel-casing uses = 8), so no extra material cost; where special ground conditions mean the casing stays in place, analyze separately on the one-time-amortization principle. Land casings >=2 m diameter may be swapped. Quantities per design weight (including stiffeners and connections, excluding holding frames), unit t. Items: QY-222/223 land placing and extraction (depth <=2 m/<=4 m); QY-224~226 driving (pile dia <=2/<=3.0/<=3.5 m); QY-227 placing plus holding-frame make/erect/remove; QY-228 guide casing erect/remove.
Applicable Codes
- TB/T 10823-2024 铁路工程预算定额 Vol. 2 桥涵工程(册说明第四~六条、第十一条;QY-222~228)
- TB/T 10821-2024 铁路工程基本定额 Ch. 9第四节 金属材料摊销
Topic Positioning
The pricing rules for bored-pile steel casings in the railway 2024 quota system (TB/T 10823-2024 "Railway works budget quota, Volume 2: bridge and culvert works" + TB/T 10821-2024 "Railway works basic quotas"): how over-water versus land casings are booked, how quantities are computed, and which quota items apply. For determining casing costs in railway estimates and budgets.
Core Conclusions
Two calibers, over-water versus land (volume notes 4-6, key sentences kept): (1) Over-water steel casings are "amortized once; no separate removal or refurbishment cost, and no deduction of salvage value of recovered material" — the full casing weight is booked; recovered salvage is not credited back. (2) Land casings (ordinary soils) are amortized: Chapter 9 Section 4 "metal materials amortization" of TB/T 10821-2024 sets land steel-casing uses = 8; and volume note 6 states "the casing and double-wall-cofferdam guide-casing quotas already include the casing amortization" — the land placing-and-extraction items carry 1/8 of the material cost; casing material is not booked again. (3) Where special ground conditions or the design/construction mean the land casing is not extracted, "analyze the cost separately on the one-time-amortization principle for steel casings". (4) "Land steel casings of diameter >=2 m may be swapped" (note 4); additionally, for large-diameter (>=2.5 m) bored piles constructed on land, delete the water-borne vessel quantities and swap the quota's <=20 t derrick-mast crane quantities for 50 t crawler-crane quantities.
Quantity rule (volume note 11 item 4, as written): "Steel casing and steel guide-casing quantities are per design weight, including stiffeners and connections, excluding holding frames." Unit t; casing length (diameter, wall thickness, embedment) is fixed by the design and converted to weight — the quota sets no casing length. Guide casings (inside double-wall cofferdams) are likewise per design weight.
Items (Chapter 1 substructure, Section 4 (10) steel casings, unit t):
- QY-222 casing placing and extraction, embedment <=2 m (land)
- QY-223 casing placing and extraction, embedment <=4 m (land)
- QY-224 casing driving, pile dia <=2 m
- QY-225 casing driving, pile dia <=3.0 m
- QY-226 casing driving, pile dia <=3.5 m
- QY-227 casing placing plus holding-frame make/erect/remove
- QY-228 guide casing erect/remove Compiling essentials: over-water casing weight booked in full via the driving items (stepped by pile diameter), no removal/refurbishment cost, no salvage credit; land casings per design weight via the placing-and-extraction items (stepped by embedment), amortization already inside — do not re-book material; holding-frame weight is not casing quantity; casings left in place (e.g., doubling as permanent works) are analyzed separately on one-time amortization.
Applicable Boundaries
- Applies only to the railway 2024 budget quota system (TB/T 10823-2024 bridge and culvert volume + TB/T 10821-2024 basic quotas); other sectors (highway, municipal) or old railway quotas have their own calibers.
- Casing length is a design/construction-organization matter the quota does not fix: over-water total length is computed by the design (water depth + overburden + stability penetration + freeboard); the common 2-4 m land embedment is only the quota step boundary and a customary reference, not a quota rule.
- This card covers only the casing item's pricing rules, not other bored-pile items (empty holes, rock sockets, slurry, rebar cages, pile-head cropping) or construction tolerances (see the cited card).
Further Reading
- TB/T 10823-2024 "Railway works budget quota, Volume 2: bridge and culvert works": volume notes 4-6 (casing amortization and swapping); note 11 item 4 (quantity rules); Chapter 1 Section 4 (10) steel casings, items QY-222~QY-228.
- TB/T 10821-2024 "Railway works basic quotas", Chapter 9 auxiliary structures and semi-finished products amortization, Section 4 metal materials amortization (land steel casing uses = 8).
- See card card_0f309bba for the excavation and pumping calibers of the same volume; see card card_6b929902 for the upstream method of fixing amortization counts.
Keywords
- 钢护筒
- bored piles
- 摊销
- 一次摊销
- railway works budget quota manual (China Railway)
- 桥涵工程
- TB/T 10823-2024
- TB/T 10821-2024