Fixing the number of amortisation cycles for turnover steel in excavation retention works - steel struts, steel wales, inserted H sections - and the pricing deduction basis where 'the quota amortises but the site hires'
The steel member material consumption of struts and inserted / extracted H sections is fixed from the design drawings first; absent a design requirement it may be measured on 4 amortisation cycles (DB11/T 2382-2024 clauses 4.3.15, 4.3.6). In Appendix item A-2-52 the strut quantity 270.0000 kg/t is the amortised amount, and the removal item A-2-53 carries no turnover material; where the site hires instead, per the Jiangsu 2026 basis the corresponding amortised quantity is deducted from the item and the hire priced separately - amortisation quantity and hire fee are never taken together.
Applicable Codes
- DB11/T 2382-2024 · Standard for Construction Consumption of Construction Works (Beijing) 4.3.4、4.3.6、4.3.10、4.3.15条
- DB11/T 2382-2024 App. A Table A.2.2-4(A-2-51、A-2-52、A-2-53)
- 江苏省建筑与装饰工程消耗量(2026版)相应章节说明第2、3、8条
Positioning
How the turnover-material amortisation cycles of excavation retention steel members (struts, wales, inserted H sections, lockpipe joints) are fixed in the quota, and the pricing treatment when 'the quota is compiled on amortisation but the site actually hires' - for tender rate build-up, cost estimates and hire-versus-buy comparison.
Core conclusions
1. The amortisation rules of Beijing DB11/T 2382-2024 (fallback values absent a design requirement)
- 4.3.15: 'The steel member material consumption in strut works consumption is determined per the design drawings; absent a requirement, it may be measured on 4 amortisation cycles.'
- 4.3.6 item 2 (deep cement mixing walls): 'For inserted H sections, the H steel consumption is determined per the design drawings; absent a requirement, 4 amortisation cycles.'
- 4.3.10 item 4 (diaphragm walls): 'The joint consumption of lockpipe joint lifting and extraction is measured per the drawings; absent a requirement, preferably on the amortised circular lockpipe flexible joint.'
- 4.3.4 (filled-pile composite ground): 'The over-consumption coefficient is measured per the drawings; absent a requirement, preferably 1.15.' (Same 'fallback when the drawings are silent' logic; a material-consumption matter checked alongside, though not amortisation.)
Common rule: the design drawings first; only when silent does the quota's fallback value apply. With a designed cycle count, adjust to it - never force 4.
2. How the amortised quantity lands in the appendix items
- A-2-52 'strut installation' (t): struts 270.0000 kg/t is the turnover-amortised quantity, plus wales 2.5500 kg/t, sundry materials 7.8900 and 5.2500 kg/t, sundry 11.6200 m/t, hex bolts with nuts 0.0300, all-in labour category II 2.2120 workdays/t, 40t crawler crane 0.2139 machine-shifts/t, 10m3/min electric compressor 0.0400 machine-shifts/t.
- A-2-53 (strut removal, t): only all-in labour category II 1.1100 workdays/t and 40t crawler crane 0.0970 machine-shifts/t - no turnover material: removal carries no further amortisation (charged once at installation), avoiding duplication.
- A-2-51 (steel wale / H wale fabrication and installation, t): I-beams 823.2000 kg/t, medium plate 7.7851 kg/t, sundry 221.6000 kg/t, labour 1.9600 workdays/t, 25t crane 0.0337 machine-shifts/t, 32kV.A AC arc welder 1.1130 machine-shifts/t.
3. 'Quota amortises, site hires' (per the Jiangsu 2026 consumption basis)
- Chapter note 8: inserted H sections, wale erection and removal, sheet piling, and steel pipe struts are compiled on turnover amortisation; on hire, deduct the corresponding amortised quantity from the item and price the hire separately.
- That is, a hire scheme never takes 'both the amortised quantity and the hire fee' - one or the other; the hire fee stands alone by actual duration and rate. This mutual exclusion is the first check when auditing hire-based offers.
- Chapter note 2: the pit steel-pipe strut fabrication / removal items are compiled for 1 strut level; with more than one level, labour and plant of the strut items (including the first level) are x 1.1.
- Chapter note 3: sheet piling under 50t per unit works - labour and plant x 1.25; on-site sheet transport is inside the items.
- Chapter note 1: earthworks dug and hauled at strut positions and the filling concrete between wales and the pit wall are excluded and charged on actual occurrence (the cost boundary outside amortisation).
4. Division of bases: budgets and tender price ceilings take the quota's amortised quantities as compiled - no adjustment for the site's actual cycle counts (the quota has averaged them); only cost estimates and hire-versus-buy comparisons recompute per actual cycles (per-cycle quantity = one-time use / cycles, plus one-time use x wastage for lost material). Never mix the two.
Applicable boundaries
- The cycle values are from DB11/T 2382-2024 (Beijing) clause 4.3 and Appendix A.2.2-4; the hire deduction, strut-level factor and 50t factor are Jiangsu 2026 chapter notes - regional bases, not directly portable; check the local volume notes for the same provisions.
- The cycle count is a compilation-stage parameter, not a settlement adjustment basis; designed counts govern, the fallback only when silent.
- With hire priced separately, overheads and taxes still accrue per contract or local rules; this card carries no rates or prices.
- Railway, highway and other sector cycle tables differ and are outside scope.
Further reading
- DB11/T 2382-2024 clauses 4.3.4, 4.3.6 item 2, 4.3.10 item 4, 4.3.15; Appendix A Table A.2.2-4 items A-2-51/52/53.
- Jiangsu 2026 consumption, chapter notes 1, 2, 3 and 8 (amortisation versus hire, strut-level factor, small-quantity sheet factor).
- Sector cycle tables (railway basic quota turnover cycles, marine steel casing one-shot amortisation) in the related cards.
Keywords
- 周转材料摊销
- 钢支撑
- 插型钢
- 钢腰梁
- number of reuses (amortization cycles)
- 租赁计价
- DB11/T 2382-2024
- 四次摊销