Conversion judgment and methods when a quota item's work content differs from site reality (no conversion for aggregated content; convert by difference type; supplementary valuation for missing items; "换" mark traceability)
Before converting, judge "whether conversion is allowed": content already aggregated in the quota (formwork support content aggregating steel/wood props, external scaffolding aggregating ramps/loading platforms, on-site handling already included) may not be adjusted even if inconsistent with reality; adjustment is allowed only where technical conditions differ significantly from the quota's basis. Convert by difference type: coefficient adjustment; strength grade / mix-proportion conversion (per mix tables or formulas); thickness increment/decrement items; material substitution (bracketed materials priced separately, ready-mixed concrete deducting mixing-equipment consumption). Missing items are not converted — prepare a supplementary unit valuation table per the quota compilation principles (GB/T 51095-2015 Clause 5.3.12); converted quota codes must carry the "换" mark for traceability.
Applicable Codes
- GB/T 51095-2015 建设工程造价咨询规范
- DL/T 5468-2013 输变电工程施工图预算编制导则
- TB/T 10831-2024 铁路工程预算定额 房屋工程
- DB63/T 2013 公路钢筋混凝土装配式结构定额
- DBJ51/T 048-2015 四川省建设工程造价电子数据标准
- GB 50860-2013 构筑物工程工程量计算规范
Topic Positioning
This card answers, in cost preparation and auditing, how to handle "quota item work content inconsistent with site reality": first judge whether conversion is allowed (quite a few "inconsistencies" are aggregated content expressly non-adjustable), then choose the conversion method by difference type, route missing items to supplementary valuation, and finally leave traceability.
Core Conclusions
① First judge convertibility: aggregated content must not be converted — formwork support content already aggregates steel/wood props (no conversion even if a different type is actually used), external scaffolding already aggregates ramps, loading platforms, and guard rails, and the quota already includes on-site handling; adjustment is allowed only where technical conditions differ significantly from the quota's basis (DL/T 5468-2013 Clause 4.1.4). ② Convert by difference type: coefficient adjustment (multiply directly where the quota notes give a coefficient, e.g., scaffolding for concrete walls above 3.6 m indoors taken as single-row × 0.3); strength grade / mix-proportion conversion (concrete and mortar per mix tables; stabilized-soil base per Ci = [Cd + Bd × (H − H0)] × Li/Ld); thickness differences preferably via the quota's own "per ±1 cm" items; material substitution (bracketed materials priced separately; ready-mixed concrete deducts the quota's mixing-equipment consumption). ③ Missing items are not converted: prepare a supplementary unit valuation table per the quota compilation principles and methods (GB/T 51095-2015 Clause 5.3.12); in the power industry, supplementary quotas must be approved by the quota administration before use. ④ Conversion traceability: the converted item code gains the suffix "换" (e.g., AC0001换) with the conversion described (e.g., "labor × 1.2"); for electronic data both quantity and consumption are to be listed (DBJ51/T 048-2015 Clause 6.5.6).
Applicable Boundaries
Applies to budget / estimate quota conversion under the quota-pricing mode (common principles for railway, power, and local quotas). Under the BOQ pricing mode, an item's work content covers all work to complete it — unlisted content must not be priced separately (GB 50860-2013 Clause 3.0.5); work-content mismatches should go through BOQ-deficiency adjustment rather than quota conversion. Specific coefficients and conversion rules follow each quota volume's notes; this card gives only the general judgment framework.
Further Reading
GB/T 51095-2015 Clause 5.3.12 (supplementary unit valuation tables) and Clause 5.3.9 (composition principles for all-in unit rates); DL/T 5468-2013 Clauses 4.1.4 and 4.1.12 (quota adjustment and missing-item handling); TB/T 10831-2024 building works volume notes (aggregated scaffolding/formwork content); DB63/T 2013 Clause 5.6 (concrete/mortar strength, mix-proportion and admixture conversion); DBJ51/T 048-2015 Clause 6.5.6 (the "换" mark rule).
Keywords
Related Cards
- →
Rapid completeness review of a budget document: four-layer quick check — document set integrity, scope consistency, inter-table cross-checks, and content elements
Review budget completeness with a four-layer quick check: ① document set integrity — tick off per the industry depth-of-preparation provisions (cover, signature page, contents, explanatory notes of the estimate, summary budget table, discipline summary tables, unit-work budget tables, other-cost tables and appendices); one missing item means incomplete, with the explanatory notes the most frequently missing; ② scope consistency — the "three-way check" of contract documents, software, and explanatory notes to find omissions and over-inclusions; ③ inter-table cross-checks — upper and lower summary levels equal, cost chains closed, sampled unit rate × quantity = amount, figures in words and numerals consistent; ④ content elements — no empty-price/zero-price items, no unitless list entries, quantity magnitudes reasonable, mandatory health, safety and environmental (HSE) provisions accrued as prescribed, comparison against the approved preliminary estimate, and unit-cost indicator benchmarking. Suspicious parts are then confirmed item by item with the five audit methods.
- →
Reviewing tender bills of quantities: methods and criteria for detecting omissions, errors, and duplications
Check the BOQ against four baselines—tender documents, construction drawings, measurement standards, and the pricing standard: omissions via drawing cross-check + standard appendix tick-off + item description derivation + preliminaries check; errors via codes (twelve digits, no duplicate codes within one project), item descriptions (standard, concise, accurate, complete), units and quantities, and work-content attribution (operations must not be split); duplications via duplicate codes, substantively identical items, split-out operations, and overlaps between work items and preliminaries. Per GB/T 50500-2024 Article 4.1.4: BOQ defects are borne by the employer under unit-rate contracts (adjusted per Section 8.2) and by the contractor under lump-sum contracts (not adjusted per Article 6.1.7).
- →
Judging quantity overstatement in construction-drawing based budgets (pre-tender estimates): five audit methods and cross-check verification
The sole yardstick for judging whether quantities are overstated is whether they are taken off per the item classification and method of measurement of the quota norms (GB/T 51095-2015 Clause 5.3.8). Auditors may choose among five methods — comprehensive audit, standard-based audit, grouped-calculation audit, comparative audit, and key-point sampling (Clause 5.1.5); focus on high-quantity, high-cost, structurally complex items such as foundations, walls, columns, doors and windows, and reinforced concrete beams and slabs (T/ZBD 100.5-2023 Clause 3.2.3), and use cross-checks — typical-floor consistency, wall-to-floor ratio, cut-and-fill balance, formwork-concrete agreement, rebar content ranges, wall opening deductions vs. door/window schedules — to quickly screen suspect items, then confirm each by item-by-item recheck.
- →
Audit of pricing by applying quota line items: identifying over-application, misapplication, and duplicate application via the three-way comparison
Identify problems of pricing by applying quota line items using the "three-way comparison": actual works (drawings / construction method statement) ↔ the work content of the quota line item ↔ the quota chapter notes and calculation rules. For over-application, check specifications, machinery, process, haul/height brackets, and unsupported coefficients; for misapplication, check cross-volume applications, wrong pairings, unsupported borrowings (missing items require supplementary unit-rate build-up schedules), conversions lacking the "换" (converted) mark, and superseded versions; for duplicate application, check work-content coverage (cast-in-place concrete already includes formwork, etc.), line-item splitting, and double-counted preliminaries. Rank items by amount to lock high-value items for focused audit.
Cited By
- ←
Selecting quota items for metal decorative mouldings (stainless steel strips, aluminium alloy grooved strips): two measurement conventions - finished moulding installation by linear metres (centre-line length) versus site-fabricated structural steel framing by weight in tonnes - with item numbers and chapter positions in each system, separation of main-material and installation costs, the boundary against drip grooves, drip noses and plaster mouldings, and adjustment coefficients for curved mouldings
Metal decorative mouldings split into two conventions - 'finished moulding installation' and 'site-fabricated framing/steel members': moulding items whose work content is only setting out, lining, cutting to size, drilling (timber plugs), gluing, installing and fixing are measured by linear metres - bill basis GB/T 50854-2024 table Q.2.1 item code 011502001 'finished decorative mouldings', unit m, computed at the centre-line length of the design dimensions, work content 'installation' only; the railway TB/T 10831-2024 volume 10 items FY-1933 to FY-1948, unit 10 m. Framing items whose work content includes straightening and correcting sections, lofting, cutting, welding and anti-corrosion oil (railway FY-1470 to FY-1472 wall/column aluminium/steel/stainless framing, FY-1528 ceiling structural steel joists) are measured by weight in t. Drip grooves, drip noses and decorative beads formed on site in cement mortar run plastering items (railway FY-1352 plaster mouldings, FY-1969/FY-1970 cement mortar decorative beads; Tianjin table M.2 item 2-140 external elevation decorative-band general plastering) and must not be double priced against finished metal mouldings.
- ←
Weld-joint content rules of pipe installation quotas and handling of excess site welds: quotas do not measure by the number of weld joints and set no per-joint top-up clause (weld joints sit within the comprehensive consumption of labour, welding consumables and welding-machine machine-shifts); the actual weld count is verified as pipe-section butt joints (L/standard length - 1) + butt-welded fittings x2 + fixed and tie-in welds as executed; quantities above the quota determination are not adjustable under clause 3.1.19 - the only routes are a design variation swapping items or a supplementary quota submitted for approval; where fittings are already counted by number, or flanged connections count main materials only, weld joints must not be counted twice
Pipe installation items are not measured by the number of weld joints, and the standard sets no general clause topping up excess welds per joint: industrial piping is measured by pipe length (clause 6.8.18) and fittings by the quantities shown on the design (clause 6.8.25), the influence of weld joints being implicit in the comprehensive consumption of labour, welding consumables and welding-machine machine-shifts; more actual welds than the quota determination is a difference in construction conditions, and under clause 3.1.19 construction consumption shall not be adjusted except as clauses 4.1.1 to 10.7.31 provide otherwise - the only lawful routes are a design variation to swap items or a supplementary unit-price schedule compiled and submitted for approval. The site weld count verified as pipe-section butt joints (L/standard length - 1) plus butt-welded fittings x2 plus fixed and tie-in welds as executed is a practical accounting value and must not serve as a settlement basis; where fittings already run the fitting-installation item by number, or flanged fittings count main materials only, their weld joints must not be counted again.
- ←
Data-taking rules of earthwork and rockwork budget quotas: classifying trenches and pits against general earthwork, classifying dry and wet soil, muck and frozen soil, items already comprehensively included in the quota and not adjustable, determination and successive-multiplication rules for efficiency-reduction conversion coefficients (wet soil, excavation within shoring, excavation between piles, local deepening, deep excavation, vertical soil transport, dynamically compacted ground, etc.), uphill-haul efficiency reduction and allowable over-excavation, and dewatering and shoring to be calculated separately
Earthwork quota data-taking starts with three preliminary steps: (1) classify trench or pit (base width up to 7 m and base length over 3 times the base width, or base length up to 3 times the base width and base area up to 150 m2 - beyond these limits, and not being site levelling, it is general earthwork); (2) split dry and wet soil at the normal groundwater level given in the geological survey data - where dewatering is adopted, the post-dewatering level is the normal water level and dewatering costs are calculated separately; (3) first remove items already comprehensively included and not adjustable (machine excavation already includes manual cleaning of residual layers up to 0.30 m thick on base and slopes, efficiency reduction for loaded uphill hauls at gradients up to 15%, and pipe laying already includes ordinary trench-side shoring). Efficiency reductions then follow the quota coefficients: wet soil by hand labour x1.18; wet soil by machine labour and machines x1.15; hand-dug trenches and pits within shoring x1.43 on labour; soil between piles x1.25 on labour under hand quotas (x1.10 on labour and machines under machine quotas); locally deepened trenches and pits x1.25 on labour and machines; vertical soil transport by hand x1.50; excavation on dynamically compacted ground x1.15; hand excavation beyond 6 m x1.15 per additional metre; where two coefficients coexist they are multiplied successively. Coefficients are taken from the notes of the quota volume actually applied and must not be mixed across volumes.
- ←
Attributing the ironmongery of proprietary doors and windows (hinges, locks, handles, closers, coordinators): the list basis folds it into the door's all-in rate with no separate item, while quota bases split by their door-and-window chapter notes - 'proprietary with ironmongery / hinges only / ordinary in, special out' - with special ironmongery on separate items
Two bases decide 'included or not': the list basis (GB/T 50854-2024 Appendix H) holds hinges, pivots, handles, locks, latches, stops, closers, rollers and tracks, floor springs and the like as inherent to the door - folded into the all-in rate, never listed apart, save 'locks installed alone' at 010801006 per set; where the item description omits ironmongery, clause 4.1.2 ('deemed to include all work necessary') with GB/T 50500-2024 clause 3.3.3 bars both separate listing and claims. The quota basis reads the chapter notes of the volume applied: Beijing 4.9.3 - metal doors carry their matched ironmongery, fire doors exclude locks / closers / hinges / coordinators / concealed latches; Jiangsu and Shaanxi timber-door items carry hinges only, the rest on special-ironmongery items; Shenzhen's proprietary fire doors carry all - the same project may flip conclusions between systems.
- ←
Deciding the relation between bell-and-spigot joints and rubber-ring joint items: joint nature (rigid cement caulked / flexible rubber ring) -> quota basis (joint inside the pipe-laying metre, or a joint item counted per piece) -> whether the ring double-charges, split by pipe material (cast iron / reinforced concrete / plastic) and quota system
Bell-and-spigot is only an end construction, never a pricing basis: cement or asbestos-cement caulked joints (oakum packing included) are rigid; rubber rings, flanged gland plus ring, and clamp plus ring are flexible. Where the joint method is written into the pipe-laying item's name or work content, it is inside the metre-priced laying - never add a 'ring joint' item; only where the quota lists joints as items (railway pipe-jacking joints PY-407~PY-414; municipal collar joints / caulking) do joints count per piece or per ten. Rings as joint auxiliaries already sit in the item's materials (ductile iron laying lists rubber ring at 0, i.e. supplied none extra); pipe main materials outside the base price price separately per the annex table - rings never charge twice.
- ←
Scope of application, included/excluded cost boundaries, material and coefficient adjustment rules, and measurement basis of the pipeline (renewal) repair and fittings renewal repair line items in Volume 2 (water supply and drainage pipelines) of SJG 84-2020, the consumption standard for municipal maintenance works
The cost boundaries of the water supply and drainage maintenance line items in Volume 2 of SJG 84-2020 reduce to four sentences: valve closure and sealing with pumping of pit water, pipe segment length, and the influence of ordinary trench-wall retention and bracing are comprehensively allowed for, with no adjustment for actual differences; trench excavation and retention, obstruction demolition, minor trench excavation, foundations and bedding, formwork and scaffolding, well sealing and unsealing, dewatering and diversion, in-pipe CCTV inspection and removal of old fittings are priced separately under Chapter 7 of the Volume (plastering under Chapter 5, blind plates under Chapter 2); where pipe materials (internal/external diameter, wall thickness, segment length, material) differ from those assumed in the line item, only materials are adjusted and all else stands, coefficients applying only where the text expressly says so (labour cost and machine-shift consumption x 1.18 for concrete pipe laid directly on trench soil foundation; labour cost and machine-shift x 1.5 for full-wrap reinforced concrete encasement; labour cost x 1.1 for the connection working-pit earthwork and bedding; labour cost x 1.5 for connections to prestressed concrete trunk pipes); fittings renewal repair is measured per the quantities shown on the design drawings, counted by number with diameter classes - reducers follow the larger bore side and tees and crosses the trunk pipe diameter - with valves or flanges connected to discs counted separately.
- ←
Selecting quota items for TDF (integral thin-sheet-steel flange) ducts and treating the fabrication part: dedicated items first, borrowing and conversion rules where none exist, the main-material treatment of corner clips and spring clips, and the cost-gap make-up against angle-steel flanges
TDF ducts take the dedicated 'TDF duct fabrication and erection' items first (DB11/T 2382-2024 Table C.7.16, C7-2-87~C7-2-91, per m2, work content already including 'fitting corner clips and spring clips', fabrication and erection in one) - the fabrication part is never borrowed out. Systems without dedicated items run the like flanged-duct items per the volume notes (SJG 111.3-2022 clause 4.1.7 note 8: 'where flange-less connection items are used, no adjustment'), never self-applied experience factors; conversion factors come only from the notes' express text (tapered uniform-supply ducts labour x 2.50, air-curtain ducts labour x 3.00, curved ducts labour and materials x 1.12); true gaps borrow from similar processes with a paper trail or compile supplementary unit-rate build-up schedules for approval. Ducts, valves, diffusers and other main materials list in brackets, never as the base of sundry-material rates.
- ←
BOQ attribution and quota measurement rules for conductor crossings of obstacles on overhead power lines: measured 'per crossing', the 50 m spacing test for same-type obstacles within one span, and the 4.0 coefficient for live-line crossings
Conductor crossings of obstacles are not listed as separate BOQ items - 'crossing type (rivers, gorges, highways, railways, houses, etc.)' is an item description of the conductor stringing item; on the quota side, conductor crossing erection is measured 'per crossing': within one span, several adjacent obstacles of the same type spaced no more than 50 m apart count as one crossing, more than 50 m as two; several types of obstacles within one span are counted by their number. Crossings of power lines and low-voltage (telecommunication) lines are compiled by default on an outage basis; where a live-line crossing is required, the labour and plant consumption is multiplied by the 4.0 coefficient; the river crossing items apply only to rivers (or lakes) with water, and rivers within 20 m are not treated as crossings.
- ←
Judging double counting between masonry scaffolds and finishing scaffolds: exclusivity between the comprehensive and individual scaffold bases, position exclusivity (birdcage scaffold versus wall finish scaffold), the 3.60m height boundary, and one quota line item only where masonry, plastering and coating on the same wall share one scaffold
Non-duplication is judged on four exclusivity lines only: (1) basis exclusivity - wherever gross floor area can be calculated, the comprehensive scaffold applies, and it already covers 'external wall masonry and external wall finishes' and 'internal wall masonry, internal wall and ceiling finishes within 3.6m'; within that scope no interior scaffold or interior wall finish scaffold may be billed again; only works unsuited to the comprehensive scaffold (separately let finishes packages included) go to individual scaffolds. (2) Position exclusivity - 'where the storey height exceeds 3.60m and the ceiling requires plastering, painting, suspended ceilings or the like, a birdcage scaffold may be added and no wall finish scaffold is measured separately'; once a birdcage scaffold is measured for a space, its internal wall finishes attract only a scaffold alteration charge or no further scaffold. (3) Height boundary at 3.60m, but the masonry test is 'from the designed indoor floor level to the soffit (or mid-height of the gable)' while the finishes test is 'the internal wall finish height'; the two must not be mixed; above 3.60m additional quota line items apply to the excess only (masonry to single-row/double-row scaffolds, plastering to the interior wall finish scaffold). (4) Measurement is by scaffold area, not by trade count - interior scaffolds and interior wall finish scaffolds are both measured on the vertical projected area of the wall face; where masonry, plastering and coating on the same wall share one scaffold, only one quota line item is billed and it may not be billed once per trade; under the BOQ basis scaffolds up to 3.6m are not listed as separate preliminary items, their cost already sitting in the all-in unit rates of the divisional and sub-divisional work items (GB/T 50860-2024 clause 4.3.3).
- ←
Pricing boundaries of anti-vibration pedestals, equipment hangers and equipment foundations for ventilation and air-conditioning equipment: installation-side metal structure and pedestal line items, civil-side concrete foundations, and vibration isolation elements as principal materials - a three-part split and the test against double counting
Anti-vibration arrangements are priced in three parts: (1) steel pedestals, supports and hangers integral with the equipment go to the installation side (railway rule: 'fan vibration-damping pedestals may be priced under the equipment support line items, with dampers priced separately', FY-2675/FY-2676 per 100kg; Beijing DB11/T 2382-2024 has standalone vibration isolation pedestal line items C1-6-105 to C1-6-109 measured per unit by equipment weight, and the equipment support items may not be applied as well); (2) concrete equipment foundations and plinths belong to civil works and are listed separately in m3 (reinforcement and formwork priced separately), the installation side keeping only the steel base sections, shim plates and grouting; (3) vibration isolators, isolation pads and spring dampers are principal materials priced separately per piece or per group - wherever the line item work content already includes them (supports and packing supplied with the equipment, fan installation including isolator installation), they must not be counted again.
- ←
Choosing the format of the all-in unit rate analysis sheet, its mandatory preparation requirements, and its roles across tendering, settlement and audit (GB/T 50500-2024 Appendix E, tables E.2.2-1 and E.2.2-2)
GB/T 50500-2024 Appendix E provides that detailed all-in unit rate analysis shall follow table E.2.2-1 and simplified analysis table E.2.2-2, the choice being fixed by the tender requirements and the contract; the rates in the analysis sheet and the prices of lump-priced items must be 'completely consistent' with the corresponding figures in the BOQ (clause 3.1.7); at tender the sheet, together with tables E.3.2, E.3.3 (which must list initial set-up, mid-term operation and final dismantling costs) and E.3.4, must be submitted in full, consistent with the priced BOQ (clauses 6.2.12 and 6.2.13). The all-in unit rate carries risk costs within the agreed scope and bands and excludes VAT (clauses 2.0.9 and 3.2.2), so the risk allowance sits inside the rate build-up rather than as a stand-alone charge. At settlement, clause 3.1.6 requires item-by-item checking that rates match the priced BOQ in the contract, with no adjustment except for variations and agreed matters; dayworks and additional works may draw on 'the detailed price make-up in the all-in unit rate analysis sheet of similar BOQ items' (clause 8.6.3; cost expert assessment guideline clause 4.8.4); audit examines whether new rate build-ups follow the quota pricing rules agreed in the contract, whether every line-item price is fixed, and whether common material prices are reasonable.
- ←
Comparative review of the all-in unit rate of one BOQ item under two construction methods: the three-identity sameness test, quantity-price separated line-by-line comparison sheets, attribution on unit output (machine-shift consumption), build-up compliance anchors, method-price consistency checks, and detection of unbalanced rates
First run the three-identity test (BOQ code + item description + unit of measurement) to confirm it is the same BOQ item; if not, price under the GB/T 50500-2024 clause 8.9.1 variation valuation rules. Then attribute the rate gap line by line, quantity separated from price, to consumption and price gaps in labour, materials and plant and to overhead and profit rate gaps; plant cost must be reduced to unit output (machine-shift rate x machine-shift consumption per unit of quantity), not compared on machine-shift rates alone, and machine models and shifts must also close against the plant allocation in the method. Compliance anchors: the analysis sheet fully consistent with the priced BOQ rate (clause 3.1.7), not below cost and not above the tender price ceiling (clause 6.1.3), deviation from the evaluation benchmark price (DB37/T 5161-2020 clause 5.3.4). The standards set no uniform deviation-percentage threshold; judging 'unreasonably low or high' and any magnitude threshold must be agreed in the tender documents and evaluation rules.
- ←
Re-derivation of the all-in unit rate when a changed construction method makes the quota machine-shift consumption inapplicable: the three-path quota conversion test, the hierarchy of bases for recalculating plant consumption, the requirements for recasting the all-in unit rate analysis sheet, and the procedure for confirmation by the employer
Changes of construction method and plant usage are factors expressly listed in GB/T 50500-2024 Clause 8.9.1 as changes of item description or construction condition that can trigger adjustment of the all-in unit rate, but conversion must step down level by level: a conversion line item within the same chapter (DL/T 5468-2013 Clause 4.1.4 item 1: 'where the technical conditions prescribed by the quota (index) differ materially from the actual conditions of the works, the applicable quota (index) may be adjusted and applied according to the technical conditions of the works and the provisions of the quota') -> an express quota coefficient -> borrowing a similar process -> building up a rate from supplementary consumption (GB/T 51095-2015 Clause 5.3.12; TB 10801-2024 Clause 2.4.3); with no express coefficient, none may be invented. The hierarchy for recalculating machine-shift consumption is: contractor's in-house norms (GB/T 50875-2013 Clause 2.3.3) -> construction quotas (Clause 2.3.5) -> budgets or final accounts of similar works, or site measurement records certified by both parties (DL/T 5468-2013 Clause 4.1.4 item 2). After conversion, the all-in unit rate analysis sheet must be recast (GB/T 51095-2015 Clause 5.3.9; GB/T 50500-2024 Clause 6.2.12 and Annex E Table E.2.2-1) and submitted to the employer under the 'submission, checking, review, re-examination and confirmation' procedure (Clauses 8.1.2 and 8.1.3; for additional works, the project execution plan or implementation scheme and the priced offer must also be submitted before execution, Clause 8.10.2). The original quota line item must never be applied in departure from the approved construction scheme.
- ←
The pricing boundary between cable laying costs and cable termination fabrication and installation costs: two measurement lines (m and count), the split of work content, and four no-double-counting tests (Jing Jian Fa [2021] No. 201, general installation, volume 4, chapter 8, cables)
Cable laying is measured in 'm' and power and control cable terminations in 'count' - two parallel measurement lines; the coexistence of the two costs on one cable is not by itself duplication. Duplication arises only in three situations: the laying item's rate (work content includes only 'temporary sealing', with no stripping, no crimping of lugs, no termination installation) already contains the termination process; the termination count does not match cables x ends + joints; the 1.5 m maintenance allowance at terminations and the 2.0 m reserve at each end of joint boxes are added a second time outside the laying length. The tests: different units; mutually exclusive work content; reserves counted once only; quantities and factors not stacked (10kV single-core terminations / joints x 0.4; five-core laying x 1.15 applies to laying consumption only).
- ←
Treating unit-works pile foundation (bored pile) quantities below the quota table's listed amounts: labour and plant of the corresponding items x 1.25, with no separate small-works addition
Building and decoration consumption quotas handle 'unit-works pile quantities below the table thresholds' by quota-consumption conversion - labour and plant of the corresponding items x 1.25 (materials excluded) - not by creating a 'small-works addition' fee item; the two are different layers, and the same quantities may never take both the factor and the addition. The bored-pile measurement base differs by volume (quantities per the measurement rules / concrete from the cap interface to the toe excluding bore protection / placed concrete volume) - check the threshold table of the volume in use.
- ←
Formwork and scaffolds of retaining walls: formwork by concrete contact area, the consumption of the wall-formwork item, and scaffolds of walls and slopes over 1.2m vertical height by vertical projected area
Formwork computes by the contact area with concrete in m2 (DB11/T 2382-2024 Appendix D Table D.1.31, item D1-7-6 'formwork, retaining wall body', unit m2, work content covering fabrication of formwork and supports, erection, release agent, removal, repair and stacking; per m2 - all-in labour I 0.2080 workdays, steel formwork connectors 0.2380 kg, steel props 0.5580 m, timber 0.0026 m3, release agent 0.0500 kg, nylon caps 4.8208, 4t truck 0.0042 machine-shifts, 8t crane 0.0177 machine-shifts). Cast formwork rules: single holes up to 0.3m2 not deducted and hole side faces not added; over 0.3m2 deducted with the side faces merged in. Scaffolds per SJG 181.2-2024 clause 8.2.4: retaining walls and slopes (over 45 degrees) with vertical height over 1.2m take scaffolds by vertical projected area, one or two faces per the approved execution plan.
- ←
Fixing the number of amortisation cycles for turnover steel in excavation retention works - steel struts, steel wales, inserted H sections - and the pricing deduction basis where 'the quota amortises but the site hires'
The steel member material consumption of struts and inserted / extracted H sections is fixed from the design drawings first; absent a design requirement it may be measured on 4 amortisation cycles (DB11/T 2382-2024 clauses 4.3.15, 4.3.6). In Appendix item A-2-52 the strut quantity 270.0000 kg/t is the amortised amount, and the removal item A-2-53 carries no turnover material; where the site hires instead, per the Jiangsu 2026 basis the corresponding amortised quantity is deducted from the item and the hire priced separately - amortisation quantity and hire fee are never taken together.
- ←
Splitting equipment from piping in insulation works and selecting items: equipment versus pipe insulation by insulated object, and the volume of the insulation layer and area of the cladding of box-type equipment (bolted panel tanks)
Insulation items divide by 'insulated object', not by bore or material: GB/T 50856-2024 Appendix M Table M.8.1 (code 031208) lists equipment insulation, other piping insulation, ventilation duct insulation, and valve and flange insulation. Equipment insulation must describe the equipment form (vertical / horizontal / spherical) and pipe insulation the pipe outside diameter - the description items and consumptions differ and the two classes are not interchangeable. Rectangular bolted box equipment such as stainless panel tanks is itemised as equipment insulation under equipment items; the insulation layer is by volume m3 (outer surface area x thickness; cylinders by pi x (D+1.03d) x 1.03d x L), cladding and vapour barriers by the outer area of the insulation m2, lap and seam wastage already inside the item materials. The GB 50264-2013 clause 5.7.3 commentary line 'pipes over 720mm count as equipment for insulation and cladding' is a banding reference only.
- ←
Quantity rules for triaxial cement deep-mixing piles: measuring by 'panel', no double counting of the three-circle overlaps inside a panel, and the three paradigms for inter-panel laps (one-hole re-stacking / full-section re-stacking), with a d850@600 panel-section worked example
Triaxial cement mixing pile quantities count by 'panel' (the three shafts of one driving pass): panel = panel cross-section x pile length (plus over-cast); the mutual overlaps of the three circles inside a panel never count twice (Shaanxi deducts the overlap volume, Jiangsu bars double-counting overlap area, Shenzhen takes the per-panel unit section, Fujian counts 3 circles for the opening panel and 2 thereafter), group-pile overlaps not deducted; inter-panel laps follow the quota rules - full-section re-stacking labour and plant x 1.50 (railway, Shaanxi), the re-mixed lap holes charged as empty boring (Shenzhen), or the re-stacked quantity not deducted with cement based on the design reinforced-soil volume (Jiangsu); pile counts are whole panels, not single shafts x 3. For d850@600: one panel net of internal overlaps 1.4949 m2; a panel after a one-hole lap adds 1.1349 m2.
- ←
Applicability relationship between comprehensive scaffolding and individual scaffolding and their quantity calculation rules (railway buildings quota TB/T 10831-2024)
Comprehensive scaffolding and individually priced scaffolds must not be double-counted on the same project: only items unsuitable for comprehensive scaffolding are executed under the corresponding individually priced scaffold items. Comprehensive scaffolding is calculated by gross floor area (GFA); exterior scaffolding by exterior wall face length × height (no deduction for door/window openings); birdcage (full-area) scaffold by clear indoor area split into a basic layer and additional layers; isolated columns and cast-in-place beams apply the double-row exterior scaffolding item × factor 0.30.
- ←
Pricing and member-wise itemisation of stone balustrades (granite balustrades): the basis test, the post / panel / sill items and their measurement rules
Stone balustrades route by works basis first: landscape / scenic and antique-style balustrades (posts + panels + continuous sill as grouped stonework) take Beijing 2024 antique volume B.2 stonework (B-2-15 to B-2-19) or landscape volume E.3.3-10 / 11; modern stone panels of stairs, corridors and outdoor platforms take building volume A.15.3-7. Member-wise measurement: sill stones by length m (landscape) or volume m3 (antique); posts by size per piece; Xunzhang and Luohan panels by drawn height x base length in m2; drum-end stones by base length x mean height in m2. BOQ itemisation per GB/T 50855-2024 Table B.2.1 (code 020202) or GB/T 50854-2024 Table Q.3.1 (code 011503).
- ←
Area-to-weight conversion of epoxy mortar (anti-corrosion mortar surfacing) quantities: the density-bridged formulas, density value paths and back-calculation of quota wastage factors
In the quotas, epoxy mortar material quantities are volumetric (m3) while items are areal (m2); area and weight must convert through volume with density as the bridge: G (kg) = S (m2) x h (mm) / 1000 x density (kg/m3) x (1 + k), and reversely S = material volume (m3) / quota consumption (m3/m2). Density first per GB/T 50589-2010 Article 3.1.2 paragraph 3: 2.2-2.4 g/cm3 (2200-2400 kg/m3); or by summing the mix proportions or order-of-magnitude cross-checks. Quota volume / theoretical net volume back-calculates the composite wastage factor (e.g. 0.0052 / 0.005 = 1.04).
- ←
Pricing when design sizes exceed the top band of budget quota items (quota gap / over-range): over-range is a gap, not a conversion; proportional extrapolation is banned; four steps - express note, top band, borrowing similar-workmanship quotas, supplementary build-up for approval
Design sizes above the quota's top band are a quota gap, not a quota conversion: no linear extrapolation by diameter, section area or capacity, and no self-invented unfounded coefficients (review reads up-rating). Order: 1 check the volume / chapter notes for express over-range provisions and follow them (e.g. stated adjustment coefficients); 2 absent them, the top band is the ceiling - apply it and record the design difference honestly in the notes, no equivalent-quantity conversion or self-set coefficients; 3 borrow similar-workmanship quotas (cross-volume / discipline / region allowed), listing the borrowing basis, charging following the borrowed volume's rules; 4 compile a supplementary unit-rate build-up per quota compilation principles and submit for approval (GB/T 51095-2015 Article 5.3.12; DL/T 5468-2013 Article 4.1.4). Sizes below the bottom band likewise bar interpolation.
- ←
Where waterproofing primers (cold primer oil / primer coat / substrate treatment agent) sit in membrane waterproofing quotas: included in the membrane items or to be itemised separately
The test is not the operation's name but whether the executed membrane item's work content states brushing the primer and its consumption table lists the primer material: stated and listed means included - no separate itemisation, which would double count. The railway TB/T 10831-2024 Volume 10 roofing membranes FY-983 to FY-1000 and basement / kitchen / bathroom membranes FY-941 to FY-957 all list brushing primer in the work content - included, not recharged; TB/T 10834-2024 Volume 13 station works notes state that membrane seams, edge terminations and screed joint sealing are already in the quota while the cement mortar screed itself is not (screed chargeable, its sealing included). Beijing DB11/T 2382-2024 membrane items include brushing primer and set no separate cold-primer item; a few systems do set one (Jiangsu 2026 items 9-132 / 9-133 cold primer oil, first and each additional coat; Shenzhen SJG 181.5-2024 dedicated primer under other waterproofing), used only where the quota excludes it or the design requires separate application.
- ←
Adjusting haul-distance changes in quota transport items: items are compiled as a base-haul band plus increment bands; cost is not proportional to distance, so scaling by distance ratio is forbidden
Quota transport items come in a banded ladder of a base haul band plus an increment band; each band's cost carries distance-independent fixed consumptions - loading and unloading, waiting, empty returns - so cost is not proportional to distance: a shortened haul must not be scaled by ratio (1 km cut to 200 m is not x 0.2); where a first band up to 200 m exists, apply that band directly; where the first band is 1 km or more, 200 m still falls within it and the base item applies without reduction; only beyond the first band does base item + increment item x number of increments stack, the count rounding at the half (a remainder under half an increment unit is dropped, at half or more it counts as one); adjusted items must carry a conversion mark on the item number.
- ←
Quota pricing route for micro-disturbance cement mixing piles (IMS piles): workmanship classification, quota-gap determination and cement-content conversion
Micro-disturbance cement mixing piles (IMS piles) are a workmanship variant of deep cement mixing piles (T/ZS 0141-2020 Article 2.1.1); pricing lands in the deep cement mixing pile items of the ground-treatment chapter, not a new pile type; because the rig and workmanship parameters differ from conventional triaxial practice (high-pressure air-assisted cutting shall not be used; dedicated combined augers), triaxial items cannot be casually applied, nor pin-type items misattributed - where no matching item exists, treat as a quota gap (first adapt the nearest similar workmanship, else compile a supplementary unit-rate build-up schedule on quota principles for approval); where the cement content differs from the quota basis, stack the per-additional-1%-cement or plus-minus-5-kg/m adjustment items instead of editing consumptions directly.
- ←
Construction of screed division joints and the charging boundary of their sealing: the cement mortar screed itself is not in the waterproofing quota and is chargeable, but membrane seams, edge terminations and screed joint sealing are already included and must not be recharged
The dividing line runs between the screed itself and the sealing of the screed: per the volume notes of TB/T 10834-2024 Volume 13 Station and Yard Works, the waterproofing quota does not include the cement mortar screed, which may be charged separately under the relevant quotas; but the seams and edge terminations of the waterproof membrane and the sealing of the screed are already included and must not be charged again. So under the railway station waterproofing items, sealing the screed division joints with waterproof mastic is not listed separately; only in systems carrying sealing as an independent item by metre (e.g. DB11/T 2382-2024 Table A.9.6-2 sealing, A-9-268 roof concrete division joint sealing, A-9-269 movement joint sealing) is it listed by metre under those items. Construction-wise the division joints are mandatory: screed division joints at spacing preferably not over 6 m both ways, width preferably 5-20 mm, with division joints also between the screed and parapets and the walls of roof-mounted tank rooms, stair enclosures and vent cowls, the joints filled with sealing mastic (DB11/T 1832.9-2022 Article 3.4.8).
- ←
Choosing the pricing route and item attribution for electrical handholes / manholes under quotas (power cable chambers, street-lighting pull pits, telecom manholes / handholes, precast vs cast-in-place)
Pricing a cable working chamber first chooses between two routes: (1) whole-chamber comprehensive items (unit per chamber, work content covering the base, masonry or casting, rendered and waterproofed walls, covers and frames, even pit excavation and backfill outside - no further sub-items covered by them); (2) split combined items (blinding / masonry base / formwork / rendering / cover fabrication and installation / cover and seat listed separately, units m3 / m2 / set). Power (electric cable) chambers go to the power / cable line chapters (e.g. TB/T 10829-2024 Volume 8 DY-341 to DY-349 cable manhole fabrication); street-lighting pull pits and telecom manholes / handholes go to the telecommunications / ducting chapters (e.g. TB/T 10826-2024 Volume 5 TY-60 to TY-69 masonry manholes / handholes). Whether precast concrete chambers can be applied depends on the item's workmanship: DB11/T 2382-2024 Table F.1.5-2.3 standard concrete cable chambers is a cast-in-place work content and cannot be applied as precast; precast members and shafts are measured by volume / length per Articles 7.4.15 / 7.4.16, and where no precast chamber item exists it is a gap requiring a supplementary quota and approval.
- ←
Quota conversion coefficients and item adjustment rules for masonry and vertical-surface insulation works (wall over-height, curved masonry, double fair-faced boundary walls, rubble slope protection over-height, curved wall / column-surface insulation labour and material coefficients)
TB/T 10831-2024 Volume 10 Buildings, volume notes: where masonry wall height exceeds 3.60 m, the quota labour on the excess quantity is multiplied by 1.3; brick, block and stone masonry are compiled for straight masonry - for curved masonry the corresponding quota labour is multiplied by 1.10 and the bricks, blocks, stone masonry and mortar (adhesive) by 1.03; double fair-faced boundary walls apply the single-face fair-faced wall items with quota labour x 1.15; rubble stone slope protection over 4 m high takes quota labour x 1.15; in vertical-surface thermal insulation, curved-wall surfaces take labour x 1.10 and column-surface insulation labour x 1.19 and materials x 1.04; insulation material mix proportions, nature and thickness may be converted where they differ from the design.
- ←
Routing cast-in-situ and precast terrazzo floors under the quota: monolithic finishes (cast, ground and waxed on site - railway FY-1209 to 1213, Beijing A-11-24 to A-11-27) versus tile (precast slab) finishes laid on a bed with the main material swapped - banding and adjustment rules
Terrazzo routing ignores the word "terrazzo" and reads the construction form: site-mixed casting with grinding and waxing is a MONOLITHIC finish taking the terrazzo monolithic items (TB/T 10831-2024 Volume 10 FY-1209 to FY-1213: 15 mm with divider strips / 15 mm with strips, colour-split / mirror 20 mm with strips / mirror 20 mm with strips, colour-split / per 1 mm up or down, all per 10 m2); factory-precast slabs laid on a bed are a TILE finish - GB 50209-2010 clause 6.4.1 "precast slab finishes of cement concrete, terrazzo and artificial stone slabs shall be laid on a bed" - taking tile items with the main material swapped to precast terrazzo slabs (mainstream quotas set no precast terrazzo floor item). Banding follows divider material and grade: ordinary terrazzo takes glass strips, artistic (coloured) takes brass strips; coloured / artistic and mirror stand as separate items, never coefficient-converted.
- ←
Pricing the core filling of hollow blocks (core-column concrete): never merged into the block-wall items - apply the cast-in-place concrete column "core column" item, quantities on hole section area times design-shown height
Block-wall items cover only "mixing mortar, cutting, laying and the like" - core filling is outside; apply the "core column" item among the cast-in-place concrete columns (Beijing DB11/T 2382-2024 A-5-13; 2021 edition 5-13), unit m3; quantities on the hole cross-section area times the design-shown height by volume. Plain and reinforced core columns take the same item; the bars, ties and inserts within them execute under the concrete and reinforced concrete rules. Regions differ (Shaanxi, e.g., already counts the core mortar of vertically laid blocks at opening jambs inside the walling mortar) - apply per the local quota notes.
- ←
When bill and quota measurement units mismatch (m2 bill against m3 quota): no unit conversion - bill and quota quantities run on separate tracks, bridged by the all-in rate P = sum of item prices over Q
Bill units are locked - never rewrite a bill to m3 because the quota runs m3: GB/T 50500-2024 clauses 3.1.4 and 4.1.7 require units per the national and sector measurement standards, and GB 50861-2013 clause 4.2.6 (mandatory) "bill units shall follow the units in the appendix". The right handling is neither unit conversion nor a conversion factor on the quota rate, but: bill quantities on bill rules (keeping the appendix m2 unit), quota quantities converted on quota rules (m3), independent; then bridged per DBJ/T 15-145-2018 clause 6.1.4 - the all-in rate of a bill item equals the sum of the quota item prices under it divided by the bill item quantity.
- ←
Pricing归属 of foundation probing (rod probing/tamping) in Beijing: already综合 in the manual-excavation item work contents, not itemized separately
Beijing DB11/T 2382-2024, 4.2.2: "manual excavation consumption is determined by soil class and shall include rod probing and bottom tamping" — foundation probing has no separate item; it is priced with the manual digging/pit items by soil class; with machine digging, hand trimming of the base (300mm where design is silent) uses the manual items, probing included (4.2.2(3), 4.2.15(2)). On the BOQ side, GB/T 50854-2024 makes base probing a "base treatment method" characteristic description, not a standalone code. Genuine separate listing (e.g., subcontract caliber) is a missing item — compile a supplementary unit-price estimate and guard against double pricing with the manual digging items.
- ←
Beijing DB11/T 2382-2024 consumption standard: quota-application method for water-tank (assembled / integral) installation - capacity banding, measurement per unit, and the treatment of accessories and peripheral works
Water-tank installation quantities shall be classified by total tank capacity and calculated by the numbers shown on the design (Clause 6.10.88), measured per "unit"; site panel assembly applies Table C.10.72-2 assembled-tank installation (work content includes panel assembly and water testing), and factory-finished whole tanks delivered to site apply Table C.10.72-1 integral-tank installation (including fitting-up of parts and the full-water test). Accessories supplied complete with the tank are included in the sub-item work content and not itemized separately; the tank body is priced as an unpriced main material/equipment; steel-section supports are executed under equipment-support fabrication and installation per Clause 6.10.41 (classified by support-group weight, calculated by the design mass in kg); control cabinets (panels) follow the electrical volume, and vibration-isolation devices follow the machinery volume.
- ←
Beijing DB11/T 2382-2024 consumption standard: pricing application of the water-tightness test and ball-passing test of drainage pipelines (water-tightness test included in the pipe-laying sub-items, ball-passing test handled by coefficient adjustment on the indoor pipe-installation sub-item - neither itemized separately)
Under Beijing DB11/T 2382-2024 neither test is applied under a separate sub-item: the water-tightness test is already included in the consumptions of "drainage pipeline laying" (7.4.26 - no separate sub-item, no separate BOQ item); the ball-passing test is handled by coefficient adjustment on the indoor drainage pipe installation sub-item (labor x 1.10, other-materials fee ratio +1.00%, other-tools fee ratio +0.05%, 6.10.30, triggered only when required by the design or the code); indoor pipe hydrostatic testing and water flushing are included in the installation consumptions (6.10.25), and the work content of drainage plastic-pipe sub-items additionally includes the water-filling test (e.g. C10-2-104).
- ←
Parapet inner-face plastering: interior or exterior wall items? Attribution method, regional norm precedents, and pricing points
At BOQ level (GB/T 50854-2024) there is no interior/exterior split — attribution is a norm-application question governed by the local current norm notes. The mainstream caliber treats it as exterior (merged into exterior plaster); some regions explicitly use interior items with factors — e.g., Shaanxi 2024: parapets without drip-nose bricks take interior items x 1.10, with drip-nose x 1.30; the outer face merges into exterior. Interior vs exterior items differ sharply (railway general plaster labor differs about 63%), so attribution drives cost.
- ←
Pricing pavement removal: selection criteria between milling and demolition sub-items, with corresponding Beijing DB11/T 2382-2024 Appendix D municipal sub-items and consumptions
Pavement removal is not a binary choice but split by construction essence: asphalt course shaving (maintenance/overlay, milling machine, milled material loaded and recycled) applies milling sub-items; wholesale pavement excavation (structure abolition, pipeline trenching) applies demolition sub-items; full-depth cement-concrete removal can only apply demolition (the milling group has only a "texturing within 1 cm" tier); pre-overlay surface texturing applies milling - texturing. Criteria: material, depth, and the approved method-statement process — all three indispensable. Beijing 2024: milling group D1-6-14-19 (100 m2), demolition group D1-6-1-6, 8-9, 10-11, 26-29 (pneumatic-pick type per 10 m2, mechanical per 100 m2); milling work content already includes loading (do not double-count loading), demolition only "piling old material" without loading/haul — count separately; demolition of pavement/base courses is computed by area.
- ←
Septic tank pricing by applying quota line items (Beijing DB11/T 2382-2024 structures works): line-item selection along the three construction routes of cast-in-place concrete / masonry / GRP factory-made tanks, work content already included, and measurement adjustment rules
Under the Beijing DB11/T 2382-2024 system a septic tank belongs to the structures works and is priced by a composite line item per tank ("zuo"): cast-in-place concrete tanks use Table F.1.5-2.4 (F-1-57 to F-1-79, selecting size number / effective volume / with or without groundwater / H+h earth cover), masonry tanks use Table F.2.3-2.1 (F-2-10 to F-2-23), and GRP factory-made tanks use F.3.2 (from F-3-107, further selecting trafficable / non-trafficable); the items already include earthworks, rebar, waterproofing and covers (factory-made tanks also include the riser and vent pipe) and must not be double counted; formwork is billed separately under the preliminary (measures) items; where the riser height differs from the standard atlas, adjust by the number of risers using the "riser, for each 0.10 m increase or decrease" items; integral precast concrete tanks delivered and installed on site are work items not covered by the quota manuals and are handled through supplementary quota items.
- ←
Beijing 2024 consumption standard (DB11/T 2382-2024) waterproof mortar: sub-item selection cross-referenced by position and method - roof A-9-83/84/85/89, walls A-9-166/167, floors A-9-209
Under Appendix A.9 of the Beijing 2024 "Construction Consumption Standard" (DB11/T 2382-2024), waterproof mortar has independent sub-items set by "position + method" and they must not be applied across positions: within the roof rigid-waterproofing table, A-9-84 (with waterproofing agent), A-9-83 (SF polymer), A-9-85 (cementitious capillary crystalline), A-9-89 (waterproof concrete); walls A-9-166 (dry-mixed rendering mortar DP M10 + waterproofing agent), A-9-167 (SF polymer); floors A-9-209 (with waterproofing agent). All are measured in m2; the corresponding 2021-edition numbers are 9-84/9-83/9-85/9-89, 9-166/9-167 and 9-209 (the 2024 edition adds the "A-" prefix in one-to-one correspondence).
- ←
Pricing steel ladders and the built-in ladders (steps) of inspection chambers: quantities by mass at design-shown dimensions, quota item attribution, and the "already inside the chamber item, not charged again" test
Steel ladders are measured by mass (t) at design-shown dimensions, without deducting holes and without adding welding rods, rivets or bolts (DB11/T 2382-2024 clause 4.7.17 item 1; municipal networks clause 7.4.17); steel ladders execute as "stepped steel ladders", embedded or welded-to-insert rolled-angle treads may execute as sundry steel members (clause 4.7.10). The steps / ladders inside inspection chambers are mostly already in the standard-chamber items' work content (e.g. D4-6-178 "chamber step and cover installation"; railway LY-441 "rung installation") and may not be listed again; where a separate item is truly needed, count in kg by design-shown weight (SJG 111.2-2022 clause 3.2.4); finished steps count by design-shown number (DB11/T 2382-2024 clause 9.3.5 item 6). Standard-chamber ladders are compiled in plastic-steel - differing designs convert the ladder material only, all else unchanged (SJG 181.4-2024 clause 3.1.3).
- ←
Handling specifications beyond a quota item's largest step (over the top band): no proportional extrapolation - a four-step ladder of volume-note wording first, analogous items next, supplementary quota last
A specification over the top band is a "quota gap", not a "quota conversion" - conversion stands only where the quota text expressly allows it; beyond the largest step no band exists, and extrapolation by capacity ratio or diameter ratio, or "unsupported coefficients", is strictly barred (that is over- and mis-application). The correct order: (1) check the volume / chapter notes for express wording (execute under another volume or discipline; multiply the stated coefficient beyond stated conditions; execute under same-class items for other types / bands); (2) take the band within - never extrapolate; (3) borrow analogous construction-process quotas (across volumes or sectors / regions, listing the basis and taking on-costs per the borrowed volume); (4) with nothing analogous, compile a supplementary unit-rate build-up schedule and obtain approval / file it (power requires approval of the quota authority; railway files with the sector standard authority and may substitute provincial local quotas).
- ←
Quota application for tile-and-stone grout sealing on floors: the tiling items' work content ends at joint wiping and pointing, excluding grout sealing - it needs its own item; the grout item is chosen in three steps: dedicated item first, then a tile-finish table item carrying sealant consumption, else a supplementary quota or market rate build-up
The work content of tiling items ends at "joint wiping / pointing" (cement slurry or jointing compound fill) and excludes grout sealing; two-component sealants and epoxy coloured sand are separate workings needing separate items or description in the bill item descriptions. Choose the grout item in three steps: (1) where the region has a dedicated "grout sealing" item, apply it (e.g. Hunan 2024 (2025 edition in the source data) A11-200 tile grout sealing, m2); (2) else where the tile-finish table holds an item with sealant consumption, apply that (e.g. Beijing DB11/T 2382-2024 A-11-67: all-in labour Grade I 0.0240 workday/m2, two-component sealant 400 ml 0.1040 set/m2, other materials 1.5%, plant 2%, unit m2); (3) else compile a supplementary quota or build up from market labour and materials, confirmed by the employer / quota authority. Red lines: tiling items already contain wiping / pointing - never add a pointing item on top; never over-apply movement-joint caulking or curtain-wall silicone items.
- ←
Deciding quota pricing of combustible gas alarms across systems: the split between the industrial-instrument "safety monitoring device" (per set) and the fire "point-type detector" (per unit), the code basis and the unit difference
Pricing a combustible gas alarm is not "either-or, take the dearer" but a match on three gauges: (1) system attribution (which controller receives the alarm signal); (2) device make-up (a lone sensor head, or head plus alarm controller as a set); (3) the quota item's unit and work content. Signals into DCS / PLC used for process interlocks price under the automatic-control instrument "safety monitoring device - combustible gas alarm" per "set" (integral installation of head plus alarm, system test); signals into the fire alarm panel used only for warning and fire interlocks price as "point-type detector - combustible gas" per "unit" (head plus base, in-situ commissioning). The hardest basis is GB 50116-2013 clause 8.1.2: "the combustible gas detection and alarm system shall stand alone, and combustible gas detectors shall not connect into the detector loops of the fire alarm panel; where the gas alarm signal must enter the automatic fire alarm system, it shall be brought in through the combustible gas alarm controller." Writing one basis down (or up) into the other is mis-application / unsupported cross-system borrowing, refutable on the code.
- ←
Deciding the quota items for pre-laid bond waterproof sheets: taking foundation sheet waterproofing under Beijing DB11/T 2382-2024 as the example, separating the "pre-laying method" items from the "torch-on method" items by construction process, with item work content, consumption and the companion measurement rules
Pre-laid bond (polymer self-adhesive film sheets) takes the "pre-laying method" items: Beijing DB11/T 2382-2024 foundation sheet waterproofing A-9-243 (HDPE self-adhesive film sheet, pre-laying, raft single layer, all-in labour Grade II 0.0630 workday/m2, HDPE film waterproof sheet 1.2 mm 1.3760 m2/m2) and A-9-244 (flat slab single layer, labour 0.0600 workday/m2, sheet 1.2510 m2/m2); the torch-on items must not be used. Basis: DB11/T 2382-2024 clause 4.10.8 "sheet waterproofing shall be itemised and determined by construction process"; the commentary to GB/T 51310-2018 clause 16.3.2 states plainly "cold-applied self-adhesive sheets must not be laid by the torch-on method".
- ←
Quota application and material attribution for stone-plastic composite (SPC) elevator door linings: classify by material into plastic decorative materials, take the finished door-and-window lining item with the main material swapped, or take the plastic decorative moulding and plastic decorative board finish items per the site detail
Stone-plastic composite (SPC - SPC boards, SPC mouldings) is a man-made composite finish material extruded from PVC resin and stone powder, belonging to the "plastic decorative materials" class - neither stone nor ceramic tile. It must not take the stone door-and-window lining items (e.g. Beijing DB11/T 2382-2024 Annex A table A.8.8, A-8-66 "door and window linings, stone", whose main material is locked to "finished stone 20 mm") nor the tile-finish items; the iron rule is "classify by the actual material, not by the stone-like pattern or the word 'stone' in the name". Current quotas carry no standalone "stone-plastic" item (absent in Beijing 2024, railway TB/T 10831-2024 Volume 10 and Hunan 2025) - a new-material gap: apply the item with "same process, similar material" and swap the main material (marking the conversion "converted"); where nothing is analogous, compile a supplementary unit-rate build-up schedule for approval. Finished SPC door linings take the "door and window linings" finished-set installation item (e.g. Beijing A-8-64, 0.0770 workday/m2 + finished timber door lining 1.000 m2/m2), swapping the finished timber lining for the finished SPC lining; moulding assembly takes the decorative moulding items (railway FY-1949 to FY-1957 plastic decorative mouldings); board adhesion takes the plastic decorative board finish items (Beijing A-12-176). Quantities by developed area at design-shown dimensions (Beijing 4.9.12; railway Volume 10 volume notes IX.7).
- ←
Measurement of metal-surface rust removal (and painting, anti-corrosion): routed by object - plant and piping by area m2, metal structures by theoretical mass t/kg - with the companion rule of matching the unit of the quota item applied
Rust-removal quantities route by the OBJECT treated, not an either-or: plant and piping rust removal is computed by area (m2) on the design-shown surface, metal-structure rust removal by the theoretical mass of the structure (DB11/T 2382-2024 clauses 6.12.8, 6.12.9), and the outcome must match the unit of the quota item applied. Within metal structures a further split applies: general steelwork (hangers, supports, brackets, ladders, railings, platforms) and pipe-rack steelwork measure in kg; steelwork of sections over 300 mm and H sections over 300 mm measure by developed area in m2 (GB/T 50856-2024 Annex M table M.1.1 note 8); pipe surface S = pi x D x L, with fittings, valves, flanges, manholes and nozzle irregularities comprehended and not added. The municipal basis agrees (DB11/T 2382-2024 clause 7.4.51: pipe rust removal and painting on pipe surface area; steelwork rust removal and metal-structure painting on theoretical mass).
- ←
Deciding how the pumping charge for ready-mixed concrete is applied: reading whether the published price information includes pumping, and the three mutually exclusive quota paths (a separate pumping item / convert materials by delivery method and apply the conveying item / included in the item, not charged again)
There is no national unified rule for pumping charges; two lines decide. (1) The publication notes of the current published price information - where issued as "ready-mixed concrete (pump type)" or marked as including pumping, it is included and never charged again; where issued by strength grade with a remark "pumping charge: truck pump +X, trailer (boom) pump +X yuan per m3", it is excluded and must be added. (2) The compilation basis of the quota item applied - "a separate concrete pumping item" (e.g. TB/T 10831-2024 Volume 10, FY-531 pump wagon 79.57 yuan per 10 m3, FY-532 stationary pump 107.25 yuan per 10 m3); "items exclude conveying - convert materials by delivery method and apply the conveying items of the chapter" (SJG 181.2-2024 Volume 2, clause 2.1.4); "items already include conveying, no further computation" (SJG 181.3-2024, SJG 181.4-2024 general rules). The three are mutually exclusive - one only; double charging is a high-frequency audit disallowance. Where no pumping item exists, charge by pumping plant machine-shifts (JTG/T 3833-2018 pump wagon 1781.5-2194.98 yuan per machine-shift, conveying pump 257.77-1241.61 yuan per machine-shift).
- ←
Whether conversion is allowed when the actual construction process differs from the quota norms: general principle, permitted situations, prohibited red lines, and the step-down path for missing items
General principle: quota norms are compiled on the basis of a rational project execution plan (construction methodology and site organization) and normal conditions; except where the quota norms expressly allow conversion, no change to the quota norms is permitted because the project execution plan, operating method, or material consumption differs from the quota norms (DB63/T 2013-2022 Clause 5.5). Permitted conversions require express written rules (strength grades per mix-ratio tables; dry-to-wet mortar at 1.75 t + 0.3 m3 water = approx. 1.0 m3 wet mix plus deduction of the tank mixer shift; fair-faced wall labour cost coefficients 1.15/1.30; admixtures counted separately; ready-mixed concrete deducts the mixing equipment); different mix ratios, cement types, or machinery types/specifications are never convertible. Where conversion is impossible, step down: adjusted application -> quota of similar processes -> compiling a supplementary quota item submitted for approval.
- ←
Quantity calculation for lightning-protection grounding devices and determination of the number of "groups": grounding electrodes counted by "piece", commissioning of independent grounding devices (up to 6 electrodes) counted by "group", grounding-grid testing counted by "system"
Fabrication and installation of grounding electrodes is counted by "piece" (2.5 m per electrode where the design does not specify); "group" appears only in electrical adjustment and testing: commissioning of an independent grounding device is counted by "group" (applicable ceiling of up to 6 grounding electrodes), and grounding-grid testing by "system". One independent grounding device = 1 group; the number of groups follows the number of "locations", not "total electrodes / 6"; where there are more than 6 electrodes or a grid has formed, count by "system" instead, and electrodes within the grid may not be counted again for testing.
- ←
BOQ and quota item selection for compact package unit substations (prefabricated substations): the mainstream principle of billing the complete unit per set; splitting into transformer plus HV/LV panels only for non-package supply, missing quota bands or contract-required splits; with commissioning and handover-test interfaces and a Beijing / Shenzhen / railway / national-standard comparison
For package unit substations (compact / prefabricated substations) the principle is to bill the complete unit: apply one installation item per set by capacity band, the work content already covering positioning, wiring and checking, earthing and individual commissioning, with no split into transformer plus HV/LV panels; only non-package supply, missing quota bands or contract-required splits justify splitting, split and unsplit being mutually exclusive with strictly no double counting of included content. Beijing DB11/T 2382-2024 clause 6.4.19 (one container body counts as one unit), Shenzhen SJG 181.7-2024 (measured per set) and GB/T 50856-2024 (switchgear installation 030402 covers prefabricated substations; clause 3.0.11 - equipment installation includes commissioning of the equipment itself) are consistent; railway TB/T 10829-2024 splits installation (DY-1074 to DY-1084) and commissioning (DY-1407 to DY-1410) into two items per unit, likewise without splitting the body.
- ←
Distinguishing and applying tile (block) finishes vs stone finishes: separate BOQ items and three quota criteria (material -> size -> workmanship)
"Block finish" carries two senses — a collective chapter name (all slab finishes including stone) and a material-specific sense (non-stone tiles); which sub-item applies is decided by the face material, not the table name: those consuming natural-stone facing panels/marble apply stone sub-items; those consuming floor tiles, glazed tiles and other ceramics apply block sub-items; in GB/T 50854-2024, stone floors / rubble-stone floors / tile floors (code 011102) and stone wall-columns / rubble / tile wall-columns (code 011203) are separate BOQ items priced under their own quotas; the railway caliber expressly runs vitrified tiles under ceramic-tile sub-items and stone within 100x100 under accent sub-items.
- ←
Railway tunnel waterproof board/geotextile/insulation quantity rules: lap and slack allowances enter the quantities; the quota carries operating waste only (TB/T 10824-2024 tunnel volume)
Waterproof board, geotextile, and insulation quantities are computed per the design laid area plus the lap and slack requirements (TB/T 10824-2024 Volume 3, waterproofing and drainage quantity rules, item 1), on the developed area along the lining inner profile, not the horizontal projection; the quota allows for operating waste only and excludes lap and slack increases (note 2 of the same section) — so lap and slack increments must enter the quantities and be booked; "the quota already includes it" is no excuse to omit them. Mining-method items SY-155/156 (waterproof board), SY-157/158 (geotextile), SY-159 (insulation, unit 100 m2); materials not matching the quota may be swapped; waterstops, blind drains, and permeable hoses per design length.
- ←
Grounds for reducing over-graded quota items in decoration works: plaster grade determination (GB 50210-2018 4.1.1/4.2.5), repricing for errors and omissions in the BOQ (GB/T 50500-2024 8.2.1/8.9.1), and construction cost expert assessment (judicial appraisal) basis (T/ZBD 100.4-2023 4.4.4)
Core grounds for reducing over-graded quota items in decoration works: quota line items must match actual work, judged by the 'three-way comparison' (actual work vs quota line item work content vs chapter notes/calculation rules). Grade determination rests directly on GB 50210-2018 4.1.1 — 'general plastering works are divided into ordinary plastering and high-grade plastering; where the design has no requirement, acceptance is as ordinary plastering' — applying a high-grade quota line item where the design states no grade constitutes over-grading; the surface-quality provisions in 4.2.5 provide counter-evidence on whether actual work meets high-grade standards. Under BOQ-based pricing, per GB/T 50500-2024 8.2.1, item description (work item specification) mismatches are characterised as errors and omissions in the BOQ and re-measured, with all-in unit rates adjusted at the 15% boundary per 8.9.1; the construction cost expert assessment (judicial appraisal) basis is in T/ZBD 100.4-2023 4.4.4. Reductions take the form of price-difference reductions and corresponding downward adjustments to the fees charged on the work-item base.
- ←
Pricing-attribution rules for equipment foundations, secondary grouting, and vibration-isolation devices: BOQ caliber vs quota caliber
Equipment concrete foundations belong to civil works and are priced separately; the installation work content already includes base channel steel (GB/T 50856-2024 Clause 3.0.10), listed separately per kg under Appendix N only with special design. Secondary grouting is already included in the equipment installation work content at the BOQ level (Clause 3.0.9) and not listed separately, but some quota items exclude grouting, requiring a grouting item applied and merged into the all-in unit rate. Vibration-isolation devices are listed with equipment installation — installation included, main materials counted separately.
- ←
Handling path for missing quota items: similar-process application -> compilation from similar-project data -> compilation from technical conditions -> approval/filing (including power and railway industry differences)
Missing quota items are handled in step-down order: (1) preferentially refer to quotas of similar construction processes (power first refers to similar power quotas, then cross-industry/local ones with matching fee standards); (2) with no similar sub-item but similar-project budget/settlement data available, compile the supplementary quota therefrom; (3) with no data, compile per the project's specific technical conditions; (4) submit the supplementary quota to the quota administration agency for approval before use; in railway, file a copy with the industry standard administration agency. Railway passenger station buildings, canopies, and overpasses may borrow the provincial local quota at the project location with matching fee standards. Unapproved supplementary quotas do not stand in settlement and audit.
- ←
Composition and determination of the work content of quota sub-items / BOQ items: main processes + auxiliary content included by default, under "unlisted not separately counted, auxiliary must be included, processes not split"
The work content of a quota sub-item = the listed main construction processes + auxiliary content included by default (machinery movement, material transport, etc.), executing the three rules "unlisted not separately counted, auxiliary must be included, processes not split"; items considered as finished products include the fabrication content when precast on site; the work content boundary corresponds one-to-one with the composition of labor consumption (basic labor / auxiliary labor / over-transport-distance labor / labor differential allowance).
- ←
Applying quota items to civil-defence duct airtight sleeves (airtight wall-penetrating spools with sealing flange rings) under the Beijing 2024 consumption quota standard: select Type I / III by the wall-penetration form, band by diameter within d300 / d600 / d1000, measured per "piece"; fabrication and installation of the sealing rib and the spool body are included in the item and not charged separately
Civil-defence duct airtight sleeves take the dedicated "pipes through airtight walls" tables: where a plain steel-plate duct is cast directly into the reinforced concrete wall, take Type I (C7-11-68/69/70, within d300/d600/d1000); where the duct is not cast in and a spool with a sealing flange ring is embedded, take Type III (C7-11-72/73/74), measured per "piece" (one per penetration); the sealing rib (sealing flange ring) and the spool body, both fabrication and installation, are already included in the item consumption (plate 2.6 mm to 3.2 mm is the spool body, 4.1 mm to 7 mm is the flange ring) - no separate sealing-rib / steel-piece item, and no duplicate charging of the main material.
- ←
Applying quotas to highway signs and pavement markings: composition of sub-items 5-1-4 signs and 5-1-5 pavement markings, quantity rules, and finished-price points (JTG/T 3832-2018 Part 5)
For highway signs apply 5-1-4 signs (steel-plate signs split by single-post/double-post/single-cantilever/double-cantilever/gantry, each further split into post and panel sub-items, priced at finished-product rates excluding reflective sheeting); for markings apply 5-1-5 pavement markings (ordinary, hot-melt, rumble, two-component markings, colored surfacing, reflective road studs, rubber speed humps, etc.). Metal sign posts and panels are each computed by total mass; pavement markings by net marked area.
- ←
Pricing curtain-wall embedded parts and post-installed anchors: separate-listing judgment, pricing composition, and anchor compliance constraints
The BOQ work content stating "including embedded parts" ≠ already priced; whether to list separately depends on whether the quota consumption includes embedded parts; most curtain-wall items do not, so embedded parts must be listed separately (per t with embedded-iron installation items; channel-type embedded parts of unitized curtain walls per count, T-type transfer bolts per set). Post-installed anchors = anchor plates per t + anchors per set + installation labor + pull-out test fees counted separately. Anchors must be chemical/undercut anchors (expansion bolts prohibited), diameter >=10 mm, >=2 per embedded part; where welding is needed, choose mechanical undercut or inverted-cone chemical anchors.
- ←
Checklist of permitted quota-conversion situations and prohibited red lines: when conversion is allowed and how to convert
Quota conversion takes "express permission in the quota provisions" as the sole premise (DB63/T 2013-2022 §5.5): only prescribed situations may be converted — strength grades per mix-ratio tables; stabilized-soil base mix ratios per Ci=[Cd+Bd×(H−H0)]×Li/Ld; compaction thickness over the limit with layered machinery shifts ×2.0; dry/wet mortar interchange (1.75 t dry mix + 0.3 m3 water ≈ 1 m3 wet mix); labor coefficients for structural differences such as fair-faced walls/arcs/extra height; supply modes such as ready-mixed concrete/centralized mixing; admixtures counted separately; missing items compiled as supplementary quotas submitted for approval. Actual mix ratios (unless the notes allow), cement types, and machinery types/specifications are never convertible; after conversion, mark the item number with "converted" for traceability.
- ←
Triage rules when quota materials differ from actually used materials: variety/species per express quota rules or via design change; same material — adjustment for price differentials only
First triage the type of "different material": for a variety/species change, non-load-bearing materials follow express quota conversion rules for consumption conversion (mix-proportion tables, stabilized-soil mix formulas, dry/wet mortar equivalent interchange, admixture/ready-mixed concrete adjustments), while load-bearing structural materials (rebar/sections/timber) must go through design change and equal-strength/equal-section substitution procedures — not quota conversion; changing only the price of the same material is purely an adjustment for price differentials (consumption fixed; price difference = quota consumption x (compilation-period price - base-period price)). Red lines: cement variety, actual construction mix proportion, and machinery type/species differences are never converted; site losses are already included and not counted again.
- ←
Decision path for selecting quota line items: item description matching -> direct application -> adjusted application -> similar construction process -> supplementary quota item submitted for approval
Applying a quota line item starts with matching "item description (work item specification) + work content": where fully consistent, apply directly (labour/material/machinery consumption taken from the line item, prices taken as market prices at the compilation date, on-costs per the matching norms for on-costs and expenses); where technical conditions differ greatly, apply with adjustment per the quota provisions; for missing items, preferentially refer to quota norms for similar construction processes (cross-industry/local allowed); where no reference exists, compile a supplementary quota item per the project's technical conditions and submit it to the quota administration agency for approval. Red lines: applying a higher-grade quota item and splitting processes for double counting are prohibited.
- ←
Railway building-works quota TB/T 10831-2024 earthworks: trench-pit vs general earthworks division, manual/mechanical boundary (depth >6 m mechanical), and the <=0.30 m manual bottom-cleaning included in mechanical excavation
Building pit excavation first tests "trench-pit" or "general earth-rock" per volume note 2: trench-pit means trenches with bottom width (design bedding or foundation width) <=7 m and length >3 x width, or pits with length <=3 x width and bottom area <=150 m2; beyond these, unless site grading, it is general earth-rock. Depth <=6 m: manual (FY-1~FY-12) or mechanical (FY-31~FY-42) per the actual method; depth >6 m "shall be treated as mechanical excavation". Mechanical earthwork already comprehends manual cleaning and trimming of the <=0.30 m left at base and slopes — "must not be adjusted in use"; no separate manual bottom-cleaning item.
- ←
TB/T 10825-2024 track quota: CWR track laying and rail-material transport compiled at "rail length <=500 m" — laying longer rail strings (unit sections) applies directly, no conversion, no extra booking
Under the railway 2024 quotas (TB/T 10825-2024 Volume 4 track works), long-rail laying for CWR (GY-9~11, GY-24~30) and rail-material transport (GY-31~36) are all compiled at "rail length <=500 m"; units are track-km laid / 1 km of rail material, consumptions amortized per kilometre — "<=500 m" is a compilation basis, not a ceiling. Laying long rails beyond 500 m on site (design unit sections preferably 1000-2000 m, TB 10015-2012 Clause 4.5.1) applies directly, with no conversion factor and no "excess booked separately" clause; rail-string joints use the on-site rail welding quota separately; closure sawing and rail drilling per Chapter 6. Wherever the volume requires adjustment it lists a factor (grade >20 permille x1.5, tunnel >1 km x1.25, both x1.75, etc.); no factor means apply directly.
- ←
Rules when quota plant differs from the plant actually used on site: machine-shift consumption locked, adjustment for price differentials, and three legitimate paths
Where the type or specification of plant differs from that actually used in construction, the machine-shift consumption (quantity) is locked and no conversion is permitted — higher or lower actual plant efficiency is no ground for adjusting the quantity; the only permissible routes are three: (1) plant adjustments expressly laid down in the quota norms (e.g. layered compaction machine-shifts x 2.0, dry-mixed to wet-mixed mortar deducting mixer machine-shifts, switching to ready-mixed concrete deducting batching-plant machine-shifts); (2) where technical conditions differ materially, adapting and applying a similar quota; (3) where the machine-shift cost quota does not cover the item, compiling a supplementary machine-shift cost quota. Price differences are dealt with through adjustment for price differentials, with the quantity untouched: plant usage cost differential = quota machine-shift consumption x (machine-shift rate per machine-shift at the compilation date - machine-shift rate per machine-shift at the base date).
- ←
Route choice for pricing metal railings under quota standards: distinguishing factory-finished railings installed on site (decoration-works finished-railing items, by m2/m) from site fabrication and installation (steel-member items, by t) - covering Beijing DB11/T 2382-2024, the GB/T 50854-2024 bill-of-quantities position, and the railway TB/T 10831-2024 comparison
Metal railings first split into two routes by how the material arrives: where finished products are procured and only installed on site, apply the decoration-works finished-railing items (Beijing DB11/T 2382-2024 Annex A.15.3-1.1 metal stair railing (panel) table, A-15-52 to A-15-61, by m2/m, work content only "installation, fixing etc.", the main material being the finished railing); where material is cut, assembled and welded on site, apply the steel-member items (A.6.6 other steel members, A-6-35 steel guardrail, by t, main material "steel-pipe guardrail" 1.000 t/t entered as a semi-finished product). Bill-of-quantities position (GB/T 50854-2024): steel-member items are compiled on a semi-finished basis excluding fabrication - site fabrication is listed under the "fabrication of steel members" item code; metal products are compiled as finished products installed on site, excluding fabrication. Railway position (TB/T 10831-2024): steel-railing fabrication (FY-1975 to 1977, by angle steel / steel pipe / round and square steel) and installation (FY-1978) are separate, both by t; finished stainless-steel railings by 10 m (FY-1979 to 1981).
- ←
Market-inquiry pricing when no applicable quota exists: the two-step method (multi-source inquiry → labor/material/machinery pricing) and traceability/audit requirements
A missing quota does not mean missing pricing rules: the all-in unit rate structure (labor/materials/machinery + management fee + profit + statutory fees + taxes) stays unchanged, with labor/material/machinery prices obtained instead from multi-channel market inquiries (online platforms / telephone / site visits / similar-project benchmarks), and consumption referenced from similar quotas with correction, manufacturer technical parameters, or field measurement. Inquiries must be multi-source and benchmarked, consistent with design parameters, and must not directly pick published prices; records are countersigned and a ledger kept; fees still accrue per the fee standards. The priority of price bases is contract agreement > price confirmed by both parties > published price > market inquiry — inquiry-based pricing is the last resort and requires employer / auditor acceptance with traceability (inquiry-verification report, preparation notes, all-in unit rate analysis sheets).
- ←
Ceiling transition layers and reinforcement measures (reverse supports, over-length hangers) must be priced separately: trigger conditions and item attribution
Steel transition layers, reverse supports, and over-length hangers beyond the quota standard length are all outside the regular work content of the ceiling BOQ/quota items and must be priced separately: the transition layer is listed separately under metal-structure works (Appendix F) by theoretical mass in t; reverse supports per steel-structure bracing/reinforcement items; regular hangers are already included in the ceiling items and not priced again.
- ←
Scenario split for applying quota line items to PE-ERT pipes under Beijing DB11/T 2382-2024: assignment between floor radiant heating pipes (C10-7-41 to 43) and plastic water supply pipes (C10-2 / C10-1 series), with a comparison against PP-R and PE-X
Under Beijing DB11/T 2382-2024, PE-ERT pipes are priced by use scenario. Floor radiant heating pipes take C10-7-41 to 43 (pipe OD within 16/20/25 mm, unit m, under the heating-appliances items); the stated work content already covers "pipes of polyethylene and similar materials", so the items apply directly without material conversion. For plastic water supply pipes (fusion jointed), indoor takes C10-2-77 to 87, buried / in-wall takes C10-2-89 to 92, and outdoor takes C10-1-43 to 52. The floor-heating and water-supply line item families must never be cross-applied (the table note states expressly that buried laying "is not applicable to floor heating"); PP-R and PE-ERT share the same tables and items (main material converted per the design type), while PE-X cannot be fusion jointed and must not directly take the fusion-connection items.
- ←
Whether curing is priced separately when applying quotas to cement-concrete pavement: Beijing DB11/T 2382-2024, Shenzhen SJG 181.1-2024, and the highway quota all include curing
Cement-concrete pavement is priced by the surface-course sub-item; curing is already in the quota work content — no separate computation, no separate curing BOQ item. Beijing DB11/T 2382-2024 sub-item D2-2-20 "cement concrete surface course, 18 cm thick" work content verbatim includes "placing, vibrating, troweling, texturing, curing, etc."; Shenzhen SJG 181.1-2024 states expressly "cement-concrete pavement placing comprehensively considers pavement curing, not computed separately"; the highway system's sub-item 2-3-8 work content also includes "texturing and curing". Three calibers, one verdict.
- ←
Red-line checklist of situations where norm resource consumption must not be adjusted: no adjustment except where conversion is expressly permitted; adjusting quantity is not adjusting price
Quota norms are compiled on the basis of a rational project execution plan and normal construction conditions; except where conversion is expressly permitted, the consumption must not be changed merely because the actual project differs from the quota provisions. Red lines: differing project execution plan (construction methodology and site organization), operating methods, actual mix proportions, cement types, or machinery types/specifications must not be adjusted; content already comprehensively covered — such as on-site material loss and small machinery/tool costs (already in overheads (company and site)) — must not be double-counted; concrete/mortar quantities already listed per the standards must not be recalculated. Unit prices may be adjusted per compilation-period prices, but consumption is a quantity standard that does not vary with price fluctuations — adjusting price is not adjusting quantity.
- ←
Box substation commissioning norm work-content boundaries and AC withstand-test charging under railway TB/T 10829-2024 Vol. 8 (power works)
Box-substation commissioning items (DY-1407~DY-1410, per capacity "per unit") cover only high/low-voltage insulation tests and functional and grounding-continuity tests — AC withstand testing is not included; AC withstand is a handover test per GB 50150 performed by a qualified testing body: budgets must not assume it inside the commissioning norm or re-charge it under other commissioning items.