Area-to-weight conversion of epoxy mortar (anti-corrosion mortar surfacing) quantities: the density-bridged formulas, density value paths and back-calculation of quota wastage factors

In the quotas, epoxy mortar material quantities are volumetric (m3) while items are areal (m2); area and weight must convert through volume with density as the bridge: G (kg) = S (m2) x h (mm) / 1000 x density (kg/m3) x (1 + k), and reversely S = material volume (m3) / quota consumption (m3/m2). Density first per GB/T 50589-2010 Article 3.1.2 paragraph 3: 2.2-2.4 g/cm3 (2200-2400 kg/m3); or by summing the mix proportions or order-of-magnitude cross-checks. Quota volume / theoretical net volume back-calculates the composite wastage factor (e.g. 0.0052 / 0.005 = 1.04).

Applicable Codes

  • DB11/T 2382-2024 建设工程施工消耗量标准
  • GB/T 50589-2010 环氧树脂自流平地面工程技术规范 第3.1.2条
  • DB63/T 2013-2022 公路养护工程预算定额 App. C Table C.42
  • GB/T 50854-2024 房屋建筑与装饰工程工程量计算标准 App. K Table K.2.1
  • CJJ/T 53-93 民用房屋修缮工程施工规程 附录C 表C-1
  • 陕西新编消耗量定额 10-133/10-134

Scope of the question

Converting epoxy mortar (anti-corrosion mortar surfacing) quantities between construction area (m2) and material weight (kg). Quota materials are volumetric, items areal; area and weight must pass through volume once, bridged by density (bulk density) - quotas never jump from m2 straight to kg.

Core conclusions

1. Starting basis: in the consumption tables the epoxy mortar line is in m3 and the item in m2 (banded by thickness), so quota material quantity (m3) = area x design thickness x composite wastage factor.

2. Core formulas

  • Forward: G (kg) = S (m2) x h (mm) / 1000 x density (kg/m3) x (1 + k)
  • Reverse: S (m2) = G / density / (h / 1000) / (1 + k), or S = material volume (m3) / quota consumption (m3/m2)

3. Choosing the path by the material data at hand

  • (1) quota consumption (m3 per unit area): G = S x q x density
  • (2) unit-area dosage (maker / standard drawing gives kg/m2 or kg per m2-mm): G = S x g x (thickness / reference thickness)
  • (3) mix (by mass): sum the proportions into a density (kg/m3), then path (1)

4. Three traceable density sources

  • Code value (preferred): GB/T 50589-2010 Technical Code for Epoxy Self-levelling Flooring, Article 3.1.2 paragraph 3: the density of epoxy mortar should be 2.2-2.4 g/cm3, i.e. 2200-2400 kg/m3.
  • By mix summation: DB63/T 2013-2022 Appendix C Table C.42 note 2 - epoxy mortar mass mix epoxy binder : cement : medium (coarse) sand = 10 : 15 : 20, adjustable as executed; the Jiangsu 2026 material library's epoxy mortar 1:0.07:2.4 holds per m3 quartz sand 1336 kg, E42 epoxy 337 kg, ethylenediamine 167 kg, acetone 67 kg etc. - summing gives the bulk density.
  • Order-of-magnitude cross-check: Beijing highway supplementary quota 3-1-5 lining surface corrosion treatment (1 m2), epoxy mortar repair 2 cm with epoxy 2.145 kg + grade-32.5 cement 0.012 t + medium (coarse) sand 0.020 m3, the three summing to about 43 kg/m2 - back-calculating to about 2.15 t/m3, matching the national range's lower bound.

5. Quota consumptions carry wastage and can be back-calculated: quota volume / theoretical net volume = composite wastage factor. Beijing DB11/T 2382-2024 A-10-110 epoxy mortar 5 mm: 0.0052 m3/m2 / 0.005 = 1.04 (4% wastage); A-10-112 epoxy mortar 20 mm: 0.0216 / 0.020 = 1.08 (8%); Shaanxi 10-133 5 mm: 0.510 m3/100 m2 = 0.0051 m3/m2 (factor 1.02); 10-134 per 1 mm: 0.100 m3/100 m2 (net).

6. Data-check warning (important): Beijing A-10-112 is named epoxy mortar 20 mm but its material line reads unsaturated polyester mortar (code 800700120000) 0.0216 m3 - name and material mismatch; verify before applying, lest an epoxy price ride on polyester consumptions.

7. Density-value warning: CJJ/T 53-93 Appendix C Table C-1 note 3 gives epoxy mortar density 1271 kg/m3 (with epoxy binder 1062 and epoxy putty 1121) - that is the pressure-grouting crack-repair mix, not the anti-corrosion self-levelling surfacing mix, and should not be applied directly to surfacing conversion.

Applicability limits

  • The formulas suit mass-measured (kg / t) mortar and slurry surfacings built by area x thickness (epoxy, unsaturated polyester and like anti-corrosion surfacings); similar volume-weight conversions apply too.
  • Density must take the actual project mix or the relevant code: the same name varies widely (surfacing about 2.2-2.4 t/m3; the old grouting basis 1271 kg/m3).
  • Quota consumptions already include construction and operation wastage - use them as they stand for procurement conversion, no double wastage; net design volumes serve only theoretical checks.
  • Consumptions are quantity standards - adjustable only where the quota expressly allows (adjusting quantity is not adjusting price).

Further reading

  • Beijing DB11/T 2382-2024 Appendix A Table A.10.2-2 anti-corrosion mortar surfacing, A-10-110 and A-10-112 (unit m2).
  • Shaanxi new consumption quota anti-corrosion works 10-133, 10-134.
  • GB/T 50589-2010 Article 3.1.2; DB63/T 2013-2022 Appendix C Table C.42 note 2; Beijing highway tunnel maintenance quota 3-1-5; Jiangsu 2026 material library; GB/T 50854-2024 Appendix K Table K.2.1 anti-corrosion surfacing (code 011002).