Beijing DB11/T 2382-2024 consumption standard: pricing application of the water-tightness test and ball-passing test of drainage pipelines (water-tightness test included in the pipe-laying sub-items, ball-passing test handled by coefficient adjustment on the indoor pipe-installation sub-item - neither itemized separately)

Under Beijing DB11/T 2382-2024 neither test is applied under a separate sub-item: the water-tightness test is already included in the consumptions of "drainage pipeline laying" (7.4.26 - no separate sub-item, no separate BOQ item); the ball-passing test is handled by coefficient adjustment on the indoor drainage pipe installation sub-item (labor x 1.10, other-materials fee ratio +1.00%, other-tools fee ratio +0.05%, 6.10.30, triggered only when required by the design or the code); indoor pipe hydrostatic testing and water flushing are included in the installation consumptions (6.10.25), and the work content of drainage plastic-pipe sub-items additionally includes the water-filling test (e.g. C10-2-104).

Applicable Codes

  • DB11/T 2382-2024 · Standard for Construction Consumption of Construction Works (Beijing) 第7.4.19、7.4.26条(市政工程·管网工程)
  • DB11/T 2382-2024 · Standard for Construction Consumption of Construction Works (Beijing) 第6.10.25、6.10.30条(通用安装工程·给排水、采暖、燃气工程)
  • DB11/T 2382-2024 · Standard for Construction Consumption of Construction Works (Beijing) App. C 子目C10-2-104、C10-2-105、C10-2-107、C10-2-108
  • DB11/T 1835-2021 · Specification for Construction Technology of Water Supply and Drainage Pipeline Works (Beijing) 第9.6.1条
  • DB11/T 1832.13-2022 · Specification for Construction Technology of Building Works (Part 13: Water Supply and Drainage Works) (Beijing) 第5.4.15条

Topic Positioning

This card explains, under the Beijing "Construction Consumption Standard" DB11/T 2382-2024, the pricing treatment of the water-tightness test of municipal (outdoor) drainage pipelines and the ball-passing test of indoor drainage pipelines (as well as water-filling tests, hydrostatic tests, water flushing and disinfection flushing): whether included in the pipe installation sub-items, handled through coefficients, or itemized separately - together with the trigger conditions and the technical-code basis.

Core Conclusions

1. Water-tightness test: no separate sub-item; included in "drainage pipeline laying". 7.4.26 (municipal works, 7.4 pipeline-network works): "Drainage pipeline laying should be itemized by reinforced-concrete pipe, concrete pipe and plastic pipe and by joint type; the construction consumptions should include the work content of the water-tightness test; quantities are calculated by the centre-line length shown on the design drawings, without deducting the lengths occupied by ancillary structures; for pipes laid inside casing pipes the labor consumption should be multiplied by 1.10." Operating rule: apply the corresponding "drainage pipeline laying" sub-item (by pipe material and joint type) - the labor, materials and machinery of the water-tightness test are already included: no separate sub-item and no separate BOQ item (itemizing it separately means duplicate pricing); pipe quantities are calculated by the centre-line length shown on the design, without deducting the lengths of manholes and other ancillary structures. Comparison (same basis for water-supply pipes): 7.4.19 - "Water-supply pipeline laying should be itemized by steel pipe and ductile-iron pipe; the construction consumptions should include the work content of pressure testing, flushing and disinfection; quantities are calculated by the centre-line length shown on the design, without deducting the lengths occupied by ancillary structures, fittings and valves; for pipes laid inside casing pipes the labor consumption should be multiplied by 1.10."

2. Ball-passing test: no separate sub-item; coefficient adjustment on the indoor drainage pipe installation sub-item. 6.10.30 (general installation works, 6.10 water supply and drainage, heating and gas works): "The test content required for indoor pipe installation shall be determined by the design or the code. Where the design requires disinfection and flushing of the pipes, the labor consumption of the corresponding pipe-installation item should be multiplied by 1.05, the other-materials fee ratio may be increased by 0.10% and the other-tools fee ratio by 0.15%; where the design requires a ball-passing test, the labor consumption of the corresponding item should be multiplied by 1.10, the other-materials fee ratio may be increased by 1.00% and the other-tools fee ratio by 0.05%." Operating rule: apply the normal indoor drainage pipe installation sub-item (e.g. drainage plastic pipe (fusion jointing) C10-2-105/DN50, C10-2-107/DN100, C10-2-108/DN125, unit m) and adjust by coefficients at the foot of that sub-item - labor x 1.10, other-materials fee ratio +1.00%, other-tools fee ratio +0.05% - noting "including ball-passing test" in the sub-item remarks. The coefficients are triggered only by a "design or code requirement".

3. Tests already included for indoor works (not charged separately): 6.10.25: "The construction consumptions of indoor pipe installation shall include hydrostatic pressure testing and water flushing." The work content of indoor drainage plastic-pipe sub-items expressly lists "temporary plugging and water-filling test" (e.g. C10-2-104 drainage plastic pipe (solvent-cement jointing) DN200, unit m). Hence indoor hydrostatic testing, water flushing and water-filling (water-tightness-type) tests are likewise not charged separately.

4. Trigger conditions of the tests (technical-code basis):

  • Water-tightness test: DB11/T 1835-2021 "Technical Specification for Construction of Water Supply and Drainage Pipelines", 9.6.1 - "Sewer pipes, combined storm-sewage pipes, inverted siphons and other drainage pipes for which the design imposes a water-tightness requirement shall undergo the water-tightness test."
  • Ball-passing test: DB11/T 1832.13-2022 "Specification for Construction Technology of Building Works, Part 13: Water Supply and Drainage", 5.4.15 - "After the water-flow test passes, a 100% ball-passing test shall be carried out on drainage risers and horizontal mains; the ball diameter is 2/3 of the pipe diameter, and unobstructed passage counts as passing." The Beijing local standard requires 100% ball passing for risers and mains - civil buildings normally must allow for it; do not omit it when compiling.

Applicable Boundaries

  • The basis is Beijing DB11/T 2382-2024; the treatment under other provinces'/cities' standards or other Beijing editions may differ and cannot be transferred directly across regions.
  • Municipal (outdoor) drainage and indoor drainage belong to different chapters: outdoor under 7.4 pipeline-network works "drainage pipeline laying" sub-items (water-tightness test included); indoor under 6.10 water-supply-and-drainage sub-items + coefficients (ball test). Mixing the chapters leads to misapplication.
  • The coefficients for the ball-passing test and disinfection flushing are applied only when "required by the design or the code"; where not required, no adjustment.
  • The water-tightness test must not be itemized as a separate BOQ item or sub-item - risk of duplicate pricing; the coefficient adjustments and the "including ball test" note should be written at the foot of the pipe-installation sub-item so that the basis stands up to audit.
  • This card covers pricing application and does not replace the construction-quality acceptance requirements.

Further Reading

  • DB11/T 2382-2024 "Construction Consumption Standard": municipal works 7.4 pipeline-network works, Clauses 7.4.19 and 7.4.26; general installation works 6.10 water supply and drainage, heating and gas works, Clauses 6.10.25 and 6.10.30; Appendix C sub-items C10-2-104, C10-2-105, C10-2-107, C10-2-108.
  • DB11/T 1835-2021 "Technical Specification for Construction of Water Supply and Drainage Pipelines", 9.6.1 (scope of the water-tightness test; details in Sections 9.1 and 9.2 of DB 11/1071 "Standard for Construction Quality Inspection of Drainage Pipe (Channel) Works").
  • DB11/T 1832.13-2022 "Specification for Construction Technology of Building Works, Part 13: Water Supply and Drainage", 5.4.15 (technical requirements and method of the water-flow and ball-passing tests).