Composition and determination of the work content of quota sub-items / BOQ items: main processes + auxiliary content included by default, under "unlisted not separately counted, auxiliary must be included, processes not split"
The work content of a quota sub-item = the listed main construction processes + auxiliary content included by default (machinery movement, material transport, etc.), executing the three rules "unlisted not separately counted, auxiliary must be included, processes not split"; items considered as finished products include the fabrication content when precast on site; the work content boundary corresponds one-to-one with the composition of labor consumption (basic labor / auxiliary labor / over-transport-distance labor / labor differential allowance).
Applicable Codes
- GB/T 50860-2024 构筑物工程工程量计算标准
- GB/T 50857-2024 市政工程工程量计算标准
- GB 50860-2013 构筑物工程工程量计算规范
- TB/T 10821-2024 铁路工程基本定额
- GB/T 50875-2013 工程造价术语标准
- DB11/T 638-2016 房屋修缮工程工程量计算规范
Topic Positioning
The composition and determination rules of the "work content" of quota sub-items (BOQ items): what the quota lists, what is included by default, and what must not be counted separately. Used for judging applicability when applying quotas, listing BOQ items, and auditing duplicate pricing.
Core Conclusions
Work content = all construction processes required to complete the qualified product of the quota measurement unit. The appendices of the various standards / quota sub-items usually list only the main processes; unlisted secondary processes and auxiliary content are included by default — machinery movement, material transport, on-site handling, though unlisted, shall be included (GB/T 50860-2024, GB/T 50857-2024 Clause 4.1.2; TB/T 10821-2024 general notes, Article 7). Three rules: (1) unlisted not separately counted — unlisted content, or content that did not occur, must not be calculated separately; (2) auxiliary must be included — machinery movement, material transport, etc., though unlisted, shall be included; (3) processes not split — the corresponding process, unless specially noted, shall not be split into separately listed BOQ items (GB 50860-2013 Clause 3.0.5). For items considered as finished products (e.g., precast members), on-site precasting includes the fabrication content. Work content corresponds to the composition of labor consumption: main processes -> basic labor; auxiliary work -> auxiliary/over-transport-distance labor; unavoidable interruptions -> labor differential allowance (GB/T 50875-2013 Section 2.3).
Applicable Boundaries
Common to pricing quotas and BOQ items across building, municipal, structures, railway, and other industries, with a consistent caliber; whether a specific sub-item contains a certain process is still governed by that quota sub-item table and its general notes. Where technical conditions differ greatly, adjust per the conversion rules rather than splitting into separately listed items; missing items are handled per the supplementary quota procedure.
Further Reading
GB/T 50860-2024, GB/T 50857-2024 Clause 4.1.2; GB 50860-2013 Clause 3.0.5; TB/T 10821-2024 general notes; GB/T 50875-2013 Section 2.3; DB11/T 638-2016 Clause 4.1.2.
Keywords
- quota line item
- 工作内容
- billed (BOQ) items
- 辅助内容
- 机械移动
- 材料运输
- 工序拆分
- 未列不另计
- labour consumption
Related Cards
- →
Screening double counting in budget documents: five high-frequency duplication scenarios and judgment principles
The general principle for judging double counting: content already included in the work content must not be charged again, separately listed items must not be recomputed, and mutually exclusive items can be taken only once. High-frequency duplication falls into five classes: ① between quota line items (cast-in-place concrete already includes formwork — no separate formwork item; auxiliary content such as machinery relocation and material transport already included); ② between preliminaries and work-sections (vertical transport covers only large machinery, the rest already being in the work-sections; costs of separately listed preliminary items must not be double-counted); ③ within preliminaries (comprehensive vs. individually priced scaffolds — choose one; birdcage (full-area) scaffold and wall-finishing scaffolding are mutually exclusive; height-increase fee keyed to work points above 25 m); ④ other-item fees (provisional sums reduced at settlement by price adjustments; claims carry taxes and duties only); ⑤ fee accrual and taxes and duties (the base to which percentage rates are applied and taxation of free-issue materials (by the employer) must not be duplicated).
- →
Preparing supplementary quota items (supplementary unit-rate build-up schedules): trigger conditions, consumption measurement, base price composition, industry approval, and distinction from supplementary BOQ items
Where the budget quota norms do not cover a work item and no similar sub-item can be applied, prepare a supplementary unit-rate build-up schedule per the compilation principles and methods of the budget quota norms (supplementation is the last resort — prefer adjusted application of existing quotas or similar quota items first; the power industry requires approval by the quota administration; railway supplementary unit-price analyses are copied to the industry standards administration, and passenger station buildings etc. may adopt provincial local quota norms instead). Labour consumption = basic labour + extra-haulage labour + auxiliary labour + labour margin, measured by work-study recording / time measurement; materials = net quantity × (1 + wastage rate), turnover materials by amortized quantity; base price = labour cost + material cost + machinery cost, with management fee, profit, statutory levies and fees, and taxes added for the all-in unit rate. A missing BOQ item is a listing-level matter: supplementary item codes use the standard code + B + three digits (e.g., from 07B001) and are filed with the provincial administration.
- →
Conversion judgment and methods when a quota item's work content differs from site reality (no conversion for aggregated content; convert by difference type; supplementary valuation for missing items; "换" mark traceability)
Before converting, judge "whether conversion is allowed": content already aggregated in the quota (formwork support content aggregating steel/wood props, external scaffolding aggregating ramps/loading platforms, on-site handling already included) may not be adjusted even if inconsistent with reality; adjustment is allowed only where technical conditions differ significantly from the quota's basis. Convert by difference type: coefficient adjustment; strength grade / mix-proportion conversion (per mix tables or formulas); thickness increment/decrement items; material substitution (bracketed materials priced separately, ready-mixed concrete deducting mixing-equipment consumption). Missing items are not converted — prepare a supplementary unit valuation table per the quota compilation principles (GB/T 51095-2015 Clause 5.3.12); converted quota codes must carry the "换" mark for traceability.
- →
Determining labour consumption in quota norms: composition, time-study methods and data-processing flow
Labour consumption in quota norms = basic labour + auxiliary labour + excess-haul labour (on-site small handling) + labour margin allowance (GB/T 50875-2013 simplifies this to basic labour + other labour; railway TB/T 10821-2024 uses basic + auxiliary + on-site small handling, without a separate margin allowance). It is determined on site by the realistic-work-record analysis method / chronometry, then processed through gross-error rejection -> adjustment coefficients -> random-error treatment -> computation of basic work time per unit product -> addition of other work times, converted at 8 hours per workday, and expressed as composite labour classes I/II/III.
- →
Reviewing tender bills of quantities: methods and criteria for detecting omissions, errors, and duplications
Check the BOQ against four baselines—tender documents, construction drawings, measurement standards, and the pricing standard: omissions via drawing cross-check + standard appendix tick-off + item description derivation + preliminaries check; errors via codes (twelve digits, no duplicate codes within one project), item descriptions (standard, concise, accurate, complete), units and quantities, and work-content attribution (operations must not be split); duplications via duplicate codes, substantively identical items, split-out operations, and overlaps between work items and preliminaries. Per GB/T 50500-2024 Article 4.1.4: BOQ defects are borne by the employer under unit-rate contracts (adjusted per Section 8.2) and by the contractor under lump-sum contracts (not adjusted per Article 6.1.7).
Cited By
- ←
Quota conventions for pipe supports and hangers (general supports, sliding/guiding/anchoring seats) calculated separately by design mass in kg: fabrication and installation items set apart, timber-padded and spring types merged in, outdoor above-ground structural-steel supports switched to the static equipment and process metal structures volume, sources of support spacing values (GB 50242-2002, DB11/T 1832.14-2022), and the double-counting boundary against the bill convention (GB/T 50856-2024 clause 3.0.10, supports already included)
Pipe-laying items exclude supports; supports are calculated separately by design mass in kg: Beijing DB11/T 2382-2024 appendix C sets C10-4-1 'fabrication, general pipe support' and C10-4-2 'installation, general pipe support' (both per 100 kg; the fabrication item carries 105 kg of section steel per 100 kg) - fabrication and installation must be applied as separate items; timber-padded and spring supports run the same items, with anti-corrosion timber pads and spring vibration isolators as main materials added; indoor supports and supports inside outdoor pipe trenches run the piping-volume support items, while above-ground structural-steel supports for outdoor pipes switch to appendix C.3, the static equipment and process metal structures volume (the most frequent mis-application on overhead works); support counts follow the maximum spacings of GB 50242-2002 table 3.3.8 and the anchor-support spacings and free-end lengths of DB11/T 1832.14-2022 tables 2.0.19-1 and 2.0.19-2, then weigh group by group off the standard drawings; under the bill convention (GB/T 50856-2024 clause 3.0.10) the work content already includes support fabrication, installation and painting - no separate bill item without a special design requirement.
- ←
Selecting quota items for metal decorative mouldings (stainless steel strips, aluminium alloy grooved strips): two measurement conventions - finished moulding installation by linear metres (centre-line length) versus site-fabricated structural steel framing by weight in tonnes - with item numbers and chapter positions in each system, separation of main-material and installation costs, the boundary against drip grooves, drip noses and plaster mouldings, and adjustment coefficients for curved mouldings
Metal decorative mouldings split into two conventions - 'finished moulding installation' and 'site-fabricated framing/steel members': moulding items whose work content is only setting out, lining, cutting to size, drilling (timber plugs), gluing, installing and fixing are measured by linear metres - bill basis GB/T 50854-2024 table Q.2.1 item code 011502001 'finished decorative mouldings', unit m, computed at the centre-line length of the design dimensions, work content 'installation' only; the railway TB/T 10831-2024 volume 10 items FY-1933 to FY-1948, unit 10 m. Framing items whose work content includes straightening and correcting sections, lofting, cutting, welding and anti-corrosion oil (railway FY-1470 to FY-1472 wall/column aluminium/steel/stainless framing, FY-1528 ceiling structural steel joists) are measured by weight in t. Drip grooves, drip noses and decorative beads formed on site in cement mortar run plastering items (railway FY-1352 plaster mouldings, FY-1969/FY-1970 cement mortar decorative beads; Tianjin table M.2 item 2-140 external elevation decorative-band general plastering) and must not be double priced against finished metal mouldings.
- ←
Weld-joint content rules of pipe installation quotas and handling of excess site welds: quotas do not measure by the number of weld joints and set no per-joint top-up clause (weld joints sit within the comprehensive consumption of labour, welding consumables and welding-machine machine-shifts); the actual weld count is verified as pipe-section butt joints (L/standard length - 1) + butt-welded fittings x2 + fixed and tie-in welds as executed; quantities above the quota determination are not adjustable under clause 3.1.19 - the only routes are a design variation swapping items or a supplementary quota submitted for approval; where fittings are already counted by number, or flanged connections count main materials only, weld joints must not be counted twice
Pipe installation items are not measured by the number of weld joints, and the standard sets no general clause topping up excess welds per joint: industrial piping is measured by pipe length (clause 6.8.18) and fittings by the quantities shown on the design (clause 6.8.25), the influence of weld joints being implicit in the comprehensive consumption of labour, welding consumables and welding-machine machine-shifts; more actual welds than the quota determination is a difference in construction conditions, and under clause 3.1.19 construction consumption shall not be adjusted except as clauses 4.1.1 to 10.7.31 provide otherwise - the only lawful routes are a design variation to swap items or a supplementary unit-price schedule compiled and submitted for approval. The site weld count verified as pipe-section butt joints (L/standard length - 1) plus butt-welded fittings x2 plus fixed and tie-in welds as executed is a practical accounting value and must not serve as a settlement basis; where fittings already run the fitting-installation item by number, or flanged fittings count main materials only, their weld joints must not be counted again.
- ←
Quantity take-off and double-counting prevention for field joint coating and damage repair of factory-prefabricated anti-corrosion pipes: whole-pipe anti-corrosion quota line items must not be re-applied; joint coating counted by weld count (per joint/spot) with per-joint nominal length converted to area; damage repair graded by damage size; dual-track pricing of BOQ m2 versus quota joints
The factory-applied anti-corrosion coating cost is already inside the material price of finished coated pipes, so only field joint coating and damage repair may be counted on site; painting, anti-corrosion coating or coal-tar epoxy quota line items must not be applied again over the whole pipe length or surface (GB/T 50856-2024 clause 3.0.8 opens an exception only for painting the design expressly requires to be completed on site and for repainting in reconstruction or extension projects; DB11/T 2382-2024 clauses 7.4.52 and 7.4.53 confine field anti-corrosion to the joints - heat-shrink sleeves and three-layer polyethylene heat-shrink tape are measured by weld count, and coating-type joint methods take the same-scope line item with labour x 1.10). Joint coating count = number of girth welds (standard-length sections - 1, plus fittings, valves and tie-in joints); developed area per joint = pi x pipe OD x nominal length per joint (400 mm for OD no more than 426 mm, 600 mm for OD above 426 mm); the BOQ item is measured in m2 of design-shown surface area per GB/T 50856-2024 table M.9.1 (code 031209) while the quota counts per joint/spot, so units must be converted before pricing; damage repair is treated per spot, graded by damage depth and puncture size (GB/T 50538-2020 clause 8.5.1).
- ←
Units of measurement for installing fans, fan coil units and air handling units (all measured per unit, computed from the quantities shown on the design drawings), comparison of tiering parameters (model, equipment weight, air volume, installation method) across the standard systems, and the cost boundary between installation of the equipment itself and base grouting, supports and height-related inefficiency
Installation line items for the three equipment classes are all measured per unit from the design drawings, so the unit itself is not in dispute - the disputes are all about the tiering parameters. The fan tiering basis varies with the standard system: the civil-building ventilation and air-conditioning volume tiers by fan type/model + installation method (DB11/T 2382-2024 clause 6.1.37 states that 'fan installation for general industrial and civil building works shall follow the corresponding ventilation and air-conditioning items'); industrial fans go to the machinery installation volume and tier by equipment weight (clauses 6.1.33 and 6.1.39; direct-drive includes body + motor + base, non-direct-drive excludes the motor); the railway building works volume tiers by air volume (TB/T 10831-2024 FY-2635 to FY-2646) and the railway motive power and rolling stock volume by equipment weight (TB/T 10833-2024 JY-1174 to JY-1177); fan coil units tier by installation method (clause 6.7.11), with induction units and multi-split indoor units absorbed into the fan coil items (clause 6.7.7); combined air handling units tier by cooling capacity or air volume (clause 6.7.10), with fresh-air units absorbed into the combined AHU items (clause 6.7.8). Base concreting goes to the building and finishing works volume and secondary grouting to machinery installation (clause 6.7.1); supports and packing supplied with the equipment are included in its installation, site-fabricated supports by weight and fan hangers by model (clauses 6.7.5 and 6.7.24).
- ←
Constituent requirements of BOQ item descriptions and the three common defects (vague description / missing measurable parameters / disconnect from the work process), with corrected drafting (GB/T 50500-2024 clauses 2.0.5, 2.0.27, 4.1.7, 4.2.2, 4.2.4; GB/T 50854-2024 clause 4.1.2)
An item description, by definition (GB/T 50500-2024 clause 2.0.5), is 'a textual description stating the nature and requirements of the BOQ item itself ...'; a description written wrongly falls under clause 2.0.27, BOQ errors (including 'mismatched item description'), and enters the price-adjustment channel rather than mere textual polish. The hard yardstick of accurate description is GB/T 50854-2024 clause 4.1.2 - 'item descriptions must be given accurately and comprehensively ... sufficient to satisfy the need to determine the all-in unit rate' - and they must be 'prepared on the basis of the design documents and in combination with the completion and handover requirements' (GB/T 50500-2024 clause 4.2.2); any parameter whose variation would change labour, material and plant consumption or the basis of percentage charges must be stated, while decorative words that do not change the price are useless if stated.
- ←
GB/T 50856-2024 "no deduction of valve and fitting lengths" for piping is measurement-only: industrial piping (Appendix H) lists fittings/flanges/valves separately; water supply/drainage/heating/gas (Appendix K) merges fittings into piping
In GB/T 50856-2024 (replacing GB 50856-2013, effective 2025-09-01), "piping quantities do not deduct lengths occupied by valves, fittings, or square compensators" is only a length-measurement rule and is separate from whether fittings get their own BOQ items. Industrial piping (Appendix H, code 0308): piping measured in m along the design centerline, while fittings, valves, and flanges are independent BOQ items (counted by "piece/sheet") — elbows, tees, and flanges must be listed and priced separately. Water supply/drainage, heating, gas (Appendix K, code 0310): piping in m without deducting lengths of valves, pressure reducers, traps, water meters, expansion joints and other fittings or various chambers; square compensator length merges into piping, and its fabrication and installation are included in the all-in unit rate for piping; pressure testing, purging and flushing are piping work content; elbows, tees and other fittings merge into piping items without separate listing.
- ←
Fixing the quota home of communication cables in low-current systems: separating control cables / multicore flexible cords / twisted-pair cables / telecom optic-electric cables by the product standard behind the type code, with laying items banded by 'method + section + cores', conversion factors, and the treatment of screened and armoured constructions
Fix the product identity first, then the item - never the system it serves or the signal it carries: KVV / KVVP / KVV22 / KVVR (GB/T 9330.2 plastic-insulated control cables) run the electrical 'control-cable laying' items, banded by method + single-core section + core count; RVV / RVVP (JB/T 8734.3 flexible cords) run the 'multicore flexible cord' wiring items (drawn into conduit / laid in trunking, trays and on brackets), screened cords on the same items with labour x 1.20, sheathed cords over eight cores in conduit reverting to control-cable items; twisted-pair and large-pair-count cables are structured cabling, on the intelligent-building 'twisted-pair / multipair' items; local telephone cables belong to the information-communication volume's 'optic (electric) cable laying'. Under DB11/T 2382-2024 clause 6.4.54, screening, armouring and flexible construction never open separate laying items (only cable terminations split armoured / unarmoured); compiled on three-core (three-core-with-earth) copper, five-core x 1.15, single-core x 0.67, aluminium or alloy x 0.67.
- ←
Attributing the ironmongery of proprietary doors and windows (hinges, locks, handles, closers, coordinators): the list basis folds it into the door's all-in rate with no separate item, while quota bases split by their door-and-window chapter notes - 'proprietary with ironmongery / hinges only / ordinary in, special out' - with special ironmongery on separate items
Two bases decide 'included or not': the list basis (GB/T 50854-2024 Appendix H) holds hinges, pivots, handles, locks, latches, stops, closers, rollers and tracks, floor springs and the like as inherent to the door - folded into the all-in rate, never listed apart, save 'locks installed alone' at 010801006 per set; where the item description omits ironmongery, clause 4.1.2 ('deemed to include all work necessary') with GB/T 50500-2024 clause 3.3.3 bars both separate listing and claims. The quota basis reads the chapter notes of the volume applied: Beijing 4.9.3 - metal doors carry their matched ironmongery, fire doors exclude locks / closers / hinges / coordinators / concealed latches; Jiangsu and Shaanxi timber-door items carry hinges only, the rest on special-ironmongery items; Shenzhen's proprietary fire doors carry all - the same project may flip conclusions between systems.
- ←
Deciding the relation between bell-and-spigot joints and rubber-ring joint items: joint nature (rigid cement caulked / flexible rubber ring) -> quota basis (joint inside the pipe-laying metre, or a joint item counted per piece) -> whether the ring double-charges, split by pipe material (cast iron / reinforced concrete / plastic) and quota system
Bell-and-spigot is only an end construction, never a pricing basis: cement or asbestos-cement caulked joints (oakum packing included) are rigid; rubber rings, flanged gland plus ring, and clamp plus ring are flexible. Where the joint method is written into the pipe-laying item's name or work content, it is inside the metre-priced laying - never add a 'ring joint' item; only where the quota lists joints as items (railway pipe-jacking joints PY-407~PY-414; municipal collar joints / caulking) do joints count per piece or per ten. Rings as joint auxiliaries already sit in the item's materials (ductile iron laying lists rubber ring at 0, i.e. supplied none extra); pipe main materials outside the base price price separately per the annex table - rings never charge twice.
- ←
Steel cover plates for trenches (channel troughs): quota-system attribution of steel grating covers versus chequer-plate covers, line item selection, measurement-unit conventions, whether the main material is priced separately, separate billing against the trench body, and the distinction from manhole-cover items at inspection chambers
For steel cover plates, first identify the applicable system, then pick the line item: steel covers laid continuously along a trench follow the metal-structures basis - self-fabricated covers (steel included) are measured in t for fabrication plus erection, while proprietary grating covers are measured in m2 for erection only with the main material priced separately; cast iron or composite covers at inspection chamber openings are counted per piece or per set, and the two systems must not be cross-applied. The structures BOQ bills trench base slabs, walls and cover slabs separately (the cover is a stand-alone item); masonry trench line items carry only blockwork plus joint pointing, so the cover must be billed separately, whereas the all-in trench item measured by m already includes 'trench cover fabrication and erection' in its work content and must not be re-billed. Section-steel edge frames and angle stiffening frames of covers are merged into the cover quantity in t by theoretical mass, and grating apertures with a single-opening area of no more than 0.30 m2 are not deducted.
- ←
Definition, BOQ item (011601002) and cost composition of vertical transport: the pricing vehicle for machine-shifts of large vertical handling plant and their attending labour; a preliminaries item priced as a lump sum per item and held fixed; and its boundary against the plant costs of work items (concrete pumping, extra height for concrete placing)
Vertical transport cost is the price of BOQ item 011601002 'vertical transport' in the preliminaries bill, covering only the machine-shifts of large vertical handling plant during construction (tower cranes, builder's hoists / external hoists, material hoists and the like) plus the plant-mounted and attending labour; vertical transport done with other lifting plant or manual aids is already included in the work content of the relevant work items and must not be charged again (GB/T 50854-2024 Appendix R.2.3; GB/T 50860-2024 Appendix C.2.3). The item work content covers mobilisation and demobilisation with erection and dismantling of the plant, fabrication and installation of anchorage devices and bases, laying and removal of tracks for travelling plant, and plant operation and use; pricing follows GB/T 50500-2024 clause 3.2.1, 'the preliminaries bill is preferably priced on a lump-sum basis', priced per item, with the composition entered per Appendix E schedule E.3.2 'composition detail analysis sheet for preliminaries items', held fixed under clause 3.3.7 and not re-measured or adjusted under clause 7.3.1 (save for variations, provisional-sum works not fully foreseen, employer causes and other statutory events).
- ←
BOQ classification under GB/T 50856-2024 of power cable earthing, handover tests and insulation checking: termination earthing included in the termination installation itself, cables (wires) used as earth conductors billed under cable installation / conduits and wiring, stand-alone lightning protection and earthing installations under 030410, tests under 030416 (electrical adjustment and testing), with the billing scope of cable installation 030409 and the boundaries drawn by the D.17 problem notes
Earthing of the metal sheath, armour or screen at cable terminations (power cable terminations, cable joints, control cable terminations) is work content of the termination installation itself ('termination earthing') - no separate BOQ item and no separate earthing item; where cables or wires serve as earth conductors, bill under the relevant item codes of Appendix D.9 cable installation and Appendix D.12 conduits and wiring; stand-alone earth electrodes, earth bars, down conductors, grading rings, air-termination tapes (meshes), air-termination rods, equipotential bonding terminal boxes, earthing bonding jumpers and the like are billed separately under 030410 (table D.10.1). Power cable tests (including insulation resistance measurement and withstand voltage tests) and earthing installation commissioning go to table D.16.1 electrical adjustment and testing (code 030416); 'insulation checking' has no stand-alone code in the BOQ, and its test items and voltage application follow GB 50150-2016 clauses 17.0.1 and 17.0.2. Within cable installation (030409), cable trays / raceways, protective conduits for cables entering buildings, and cable branch boxes are billed instead under the relevant codes of Appendix D.12 and Appendix D.5.
- ←
Deciding when firestop collars are required on plastic drainage pipes (GB 50015-2019 clause 4.4.10 and the fire-code family), measurement per piece and BOQ / quota item application (including the dedicated items of Beijing DB11/T 2382-2024 with the collar as main material priced by pipe size), and the pricing boundaries against floor-penetration sleeves and firestop sealing materials
Firestop collars on plastic drainage pipes measure per piece ('ge'), banded by main-pipe / nominal diameter, counted as shown on the design: DB11/T 2382-2024 clause 6.10.44 - collar installation counts by main-pipe diameter as shown - with dedicated items under Table C.10.25-6 (DN50 -> C10-4-82, DN100 -> C10-4-84, unit 'piece', work content marking, drilling, setting, bolting, collar installation), the 'firestop collar' main material listed separately at 1.0000 piece per piece. GB/T 50856-2024 Appendix K Table K.2.1 (pipe accessories, 031002) and the local list guide Table N.1 (other and ancillary works, 031301) set no dedicated collar item - add a supplementary item (last three digits 801~999) or fold into the plastic drainage pipe's all-in unit rate. The setting test is not a blanket 'DN110': GB 50015-2019 clause 4.4.10 requires collars on both sides of fire walls (no diameter threshold); in high-rise buildings, exposed soil stacks of dn110 and over crossing floors take a collar below the slab (all three preconditions); pipes crossing shaft walls take collars outside the shaft wall; GB/T 51410-2020 clause 5.2.4 adds that pipes over 50mm nominal take a collar or firestop wrap below vertical penetrations or on both sides of horizontal ones.
- ←
Scope of application, included/excluded cost boundaries, material and coefficient adjustment rules, and measurement basis of the pipeline (renewal) repair and fittings renewal repair line items in Volume 2 (water supply and drainage pipelines) of SJG 84-2020, the consumption standard for municipal maintenance works
The cost boundaries of the water supply and drainage maintenance line items in Volume 2 of SJG 84-2020 reduce to four sentences: valve closure and sealing with pumping of pit water, pipe segment length, and the influence of ordinary trench-wall retention and bracing are comprehensively allowed for, with no adjustment for actual differences; trench excavation and retention, obstruction demolition, minor trench excavation, foundations and bedding, formwork and scaffolding, well sealing and unsealing, dewatering and diversion, in-pipe CCTV inspection and removal of old fittings are priced separately under Chapter 7 of the Volume (plastering under Chapter 5, blind plates under Chapter 2); where pipe materials (internal/external diameter, wall thickness, segment length, material) differ from those assumed in the line item, only materials are adjusted and all else stands, coefficients applying only where the text expressly says so (labour cost and machine-shift consumption x 1.18 for concrete pipe laid directly on trench soil foundation; labour cost and machine-shift x 1.5 for full-wrap reinforced concrete encasement; labour cost x 1.1 for the connection working-pit earthwork and bedding; labour cost x 1.5 for connections to prestressed concrete trunk pipes); fittings renewal repair is measured per the quantities shown on the design drawings, counted by number with diameter classes - reducers follow the larger bore side and tees and crosses the trunk pipe diameter - with valves or flanges connected to discs counted separately.
- ←
BOQ itemisation and quota application for preheat, post-heat and weld-joint heat treatment of industrial pipework: 030813008 and 030813009 measured per joint and banded by material and diameter x wall, electric-pad / induction / oxyacetylene items distinguished, hardness testing attribution, and the cost boundary against weld NDT
GB/T 50856-2024 Table H.13.1 (code 030813) lists preheat and post-heat as 030813008 and joint heat treatment as 030813009, both per 'joint', quantities per the code or design; NDT (030813001~030813007) lists separately. Pricing bands items by material and diameter x wall into quota items; electric pad, induction and oxyacetylene items differ and never interchange (GB 50236-2011 clause 7.4.11, 'post-heat and PWHT should use electric heating', grounds the electric items as the routine basis). Preheat followed directly by treatment still takes both items, the preheat labour x 0.87 (DB11/T 2382-2024 Table C.8.89-5 note). Hardness testing rides inside the treatment item only where the work content says so - the local PWHT item C3-7-54 includes 'hardness testing'; the preheat / post-heat and electric-pad joint items do not, and combine separately when the design requires.
- ←
Selecting quota items for TDF (integral thin-sheet-steel flange) ducts and treating the fabrication part: dedicated items first, borrowing and conversion rules where none exist, the main-material treatment of corner clips and spring clips, and the cost-gap make-up against angle-steel flanges
TDF ducts take the dedicated 'TDF duct fabrication and erection' items first (DB11/T 2382-2024 Table C.7.16, C7-2-87~C7-2-91, per m2, work content already including 'fitting corner clips and spring clips', fabrication and erection in one) - the fabrication part is never borrowed out. Systems without dedicated items run the like flanged-duct items per the volume notes (SJG 111.3-2022 clause 4.1.7 note 8: 'where flange-less connection items are used, no adjustment'), never self-applied experience factors; conversion factors come only from the notes' express text (tapered uniform-supply ducts labour x 2.50, air-curtain ducts labour x 3.00, curved ducts labour and materials x 1.12); true gaps borrow from similar processes with a paper trail or compile supplementary unit-rate build-up schedules for approval. Ducts, valves, diffusers and other main materials list in brackets, never as the base of sundry-material rates.
- ←
BOQ attribution and quota measurement rules for conductor crossings of obstacles on overhead power lines: measured 'per crossing', the 50 m spacing test for same-type obstacles within one span, and the 4.0 coefficient for live-line crossings
Conductor crossings of obstacles are not listed as separate BOQ items - 'crossing type (rivers, gorges, highways, railways, houses, etc.)' is an item description of the conductor stringing item; on the quota side, conductor crossing erection is measured 'per crossing': within one span, several adjacent obstacles of the same type spaced no more than 50 m apart count as one crossing, more than 50 m as two; several types of obstacles within one span are counted by their number. Crossings of power lines and low-voltage (telecommunication) lines are compiled by default on an outage basis; where a live-line crossing is required, the labour and plant consumption is multiplied by the 4.0 coefficient; the river crossing items apply only to rivers (or lakes) with water, and rivers within 20 m are not treated as crossings.
- ←
Quota line item classification for factory-finished spiral welded steel pipe (large diameters DN800/DN1000): apply the low-pressure carbon steel plate-rolled pipe (spiral rolled pipe) installation item with the pipe as an unpriced principal material; do not apply the finished carbon steel pipe installation item, and do not add any pipe rolling fabrication item
Under Chapter 6.8 of DB11/T 2382-2024: low-pressure spiral rolled pipe installation shall follow the corresponding carbon steel plate-rolled pipe items (6.8.16), and the pipe is an unpriced principal material (shown in brackets under 6.8.13). When factory-finished spiral welded pipe arrives on site for direct installation, only the installation item applies; no pipe rolling fabrication item may be added (the chapter contains only 'pipe fittings fabrication' items 6.8.80-6.8.82, with no pipe-body fabrication item). Large diameters DN800/DN1000 exceed the size bands of the finished carbon steel pipe installation items; borrow the nearest band of the plate-rolled / spiral rolled pipe installation items at the same pressure class and connection type. Upgrading to higher-priced items and splitting fabrication from installation for double counting are both prohibited.
- ←
Quota application for the erection cost of vertical storage tanks (metal oil tanks) built by the reverse jack-up method with hydraulic lifting: line-item selection by construction form and capacity class, measurement by shell metal weight in t, lifting gear and temporary stiffening to preliminaries, and NDT and the water filling test charged separately
The reverse jack-up method has no standalone line item in the erection consumption quota: the item is selected by 'tank type x shell construction form (lap-jointed / butt-jointed) x capacity class' and measured by shell metal weight in t (no deduction for the area of openings in the shell, and including bottom plates, shell plates, roof plates, curb angle, stiffening rings, wind girders, and shim and reinforcement plates); where only one tank is built on one site, labour and plant consumption is multiplied by 1.25 (materials not). Neither the plant schedule nor the work content of the items contains a lifting step, so the hydraulic lifting devices and the temporary stiffening of the reverse method are charged as preliminaries; the work content stops at 'leak testing' - shell weld NDT, the water filling test and foundation settlement monitoring are outside the items and must be listed separately.
- ←
Determining missing items not listed in the BOQ appendices and setting supplementary items: the three-element comparison search path, the discipline-code + B coding rule (from 01B001), the five required accompanying elements, the tender-document explanation / filing requirements, and the boundary of error when fitting near-match items
Under GB/T 50854-2024 Clause 4.1.4, for items not covered in Appendices A~R the compiler may add supplementary items, coded with this standard's code 01 plus B and three Arabic numerals, numbered sequentially from 01B001, and must attach the item name, item description, unit of measurement, quantity take-off rule and work content (for preliminaries that cannot be measured: name, work content and scope of inclusion). The determination is a three-element comparison (item description + work content + unit of measurement with calculation rule): so long as any element can be carried by an existing appendix item, the existing item must be applied forward and the difference expressed in the item description, and no supplementary code may be created; work content lists only principal operations, auxiliary content such as plant movement and material transport is deemed included, and operations may not be split out and listed separately unless specifically stated. The 2024 editions (GB/T series) say 'may add' and no longer require filing; instead GB/T 50500-2024 Clause 3.1.3 requires the supplementary basis to be explained in the tender and contract documents; the 2013 compulsory national standards required 'shall add + file with the provincial or industry construction cost administration institution', and local standards may still retain the filing requirement.
- ←
Classification basis and table numbers for soil and rock on site (soft rock / hard rock / boulders), the threshold position on measuring boulders as rock, and the price adjustment boundary where the actual class differs from the BOQ item description
BOQ item descriptions are entered per Table A.4.3-1 of GB/T 50854-2024 (soil classes 1-4, judged by soil name plus excavation method) and Table A.4.3-2 (extremely soft rock through extremely hard rock); where classes cannot be fixed precisely, describe from the geotechnical investigation report. The quota-system classes 'loose rock / sub-hard rock / ordinary hard rock / extra-hard rock' (Protodyakonov I-XVI) are not listed in the BOQ classification tables and must not be entered as item descriptions. Boulders: the building works position has only a qualitative boundary - clearance of natural obstructions 'removable together with the earthworks' is already inside the earthwork items, while boulders needing separate breaking or crushing are listed separately as rock or handled as missing items or variations; the water sector position expressly measures boulders larger than 0.7 m3 as rock excavation. Where the class differs from the BOQ description, under a unit-rate contract the all-in unit rate is re-determined on the item description actually constructed (GB 50500-2013 clause 9.4.2), with a 15% quantity deviation as the boundary for rate adjustment (clause 9.6.2).
- ←
Earth and rock haulage pricing: haul distance measured as the nearest distance from the excavation centroid to the fill or spoil centroid, on-site transport already included in excavation line items, off-site transport listed separately as disposal of surplus material and banded as basic haul plus increments, the loading charge taken only once, and hoisting soil from deep excavations charged separately as vertical transport
Earth and rock haul distance is measured as the shortest and nearest distance between the centroid of the excavated (or demolished) material and the centroid of the fill area or the spoil (stockpile) area, the centroid positions being fixed by the approved project execution plan; it means the shortest distance along a traversable haul route, not the straight line between two points. The work content of excavation BOQ items includes only on-site transport; off-site haul must be listed separately as 'disposal of surplus material' (covering loading and haul from the site to the disposal point), and the quota bands it as 'basic haul + increments' (manual cartage with a 20m basic band plus 10m/20m increments; mechanical cartage with a basic band within 1km plus 1km per increment; loader loading and carting of loose soil applying only within 20m). Loading and haul may be split into processes, but the loading charge may be taken only once, in either the excavation or the haul item (excavation 'without loading' line items are converted from the loading line item by coefficient 0.80). Hoisting soil from deep excavations beyond the set depth (commonly 2m) is charged separately as vertical transport at 7m of horizontal haul per metre of depth, but dedicated line items such as large strutted excavations and excavation within bracing already include vertical hoisting and take no further charge.
- ←
Pricing boundaries of anti-vibration pedestals, equipment hangers and equipment foundations for ventilation and air-conditioning equipment: installation-side metal structure and pedestal line items, civil-side concrete foundations, and vibration isolation elements as principal materials - a three-part split and the test against double counting
Anti-vibration arrangements are priced in three parts: (1) steel pedestals, supports and hangers integral with the equipment go to the installation side (railway rule: 'fan vibration-damping pedestals may be priced under the equipment support line items, with dampers priced separately', FY-2675/FY-2676 per 100kg; Beijing DB11/T 2382-2024 has standalone vibration isolation pedestal line items C1-6-105 to C1-6-109 measured per unit by equipment weight, and the equipment support items may not be applied as well); (2) concrete equipment foundations and plinths belong to civil works and are listed separately in m3 (reinforcement and formwork priced separately), the installation side keeping only the steel base sections, shim plates and grouting; (3) vibration isolators, isolation pads and spring dampers are principal materials priced separately per piece or per group - wherever the line item work content already includes them (supports and packing supplied with the equipment, fan installation including isolator installation), they must not be counted again.
- ←
Content boundary between duct fabrication and installation line items and supports and hangers (hanging/supporting brackets), and preventing double counting: the BOQ layer 'items include supports and hangers' versus the quota layer 'volume preamble plus line-item work content', three parallel yardsticks (included / priced separately / composite duct as a complete set), the weight linkage to 100 kg support line items when priced separately, and no separate charge for stiffening
The test runs on two layers. At the BOQ layer, GB/T 50856-2024 Table G.2.1 note 6 (ventilation duct items include fabrication and installation of supports and hangers; where listed separately, itemise under Appendix N) and Clause 3.0.10. At the quota layer, the volume preamble plus the work-content column of the governing line item must be checked: railway TB/T 10831-2024 volume preamble 'the thin steel sheet and GRP ventilation duct fabrication and installation quotas include flanges, stiffening frames and hanging/supporting brackets, but exclude floor-standing frames spanning ducts (price floor-standing frames under the equipment support quota)'; Shenzhen SJG 111.3-2022 4.1.7-3 same yardstick; Beijing DB11/T 2382-2024 line item C7-2-87 work content includes making and installing hanging/supporting brackets - all fall under 'included', and supports and hangers must not be priced separately. Two further yardsticks exist: 'excluded, price support line items separately per design quantity (in kg / 100 kg)' and 'composite duct supports supplied with the complete product, installation only'. The same support or hanger may be charged once only; duct stiffening (beading / stiffening ribs / stiffening frames) is inside the fabrication line item and must not be charged again; floor-standing frames spanning ducts are the sole exception to the 'included' yardstick.
- ←
Where pipe support and hanger costs sit for water supply and drainage (heating, gas) piping, and the boundary for billing them separately: three sets of tests - the BOQ measurement criterion, the Beijing consumption standard criterion, and the diameter gates of the national unified quota and the railway quota
Support and hanger costs cannot be answered wholesale as 'included' or 'not included'; they split by criterion. Under the BOQ measurement criterion, GB/T 50856-2024 clause 3.0.10, the work content of pipe installation items already covers fabrication and erection of supports, hangers and base structural steel plus painting, so no separate item is generally listed (yet rate build-up must still load the support line items into the all-in unit rate); Beijing DB11/T 2382-2024 clauses 6.10.29 and 6.10.35 require supports, pipe clips and hooks to be billed separately under 6.10.39-6.10.42, with no diameter gate; Jing Jian Fa [2021] No. 201 (Beijing), Volume 10, chapter 2 notes item 11 states 'pipe installation does not include pipe support erection', and the 2012 edition of the same note added '(plastic pipes excepted)', which the 2021 edition deleted. The Volume 8 family formula 'DN32 and below include clips and hooks, above that billed separately' of the national unified installation quota and the railway TB/T 10831-2024 'steel pipe below DN25 includes clips and hooks' are both volume-notes-level local or sector criteria, not a national rule. Supports are measured by design-shown mass in kg (quota unit 100kg); proprietary clips and proprietary seismic supports are counted by design-shown number, and seismic supports must be listed separately under the proprietary-support item code.
- ←
Pricing boundary of fire sprinkler system commissioning: equipment installation already includes commissioning of the equipment itself and single-machine trial runs (the negative conclusion, not separately payable), while system interlock commissioning is separately itemised under code 030909 with its point-counting rules, and water extinguishing commissioning and fire alarm commissioning are itemised separately
GB/T 50856-2024 Clause 3.0.11: 'the equipment installation work content of this standard includes commissioning of the equipment itself and single-machine trial runs' - single-machine trial runs and commissioning of the unit may never be charged outside the equipment installation items; only interlocking across equipment and across systems is listed separately under Annex J Table J.9.1 fire protection system commissioning (code 030909): water extinguishing control devices counted in points (branches) by the number of water flow indicators (sprinkler systems), hydrant pump-start buttons and fire monitors; automatic alarm and the other systems take their points from the device and component counts and are measured as 'systems'; gaseous extinguishing counts points by the cylinder head valves; fire barrier control devices by the piece and fire lifts by the lift; water extinguishing commissioning and fire alarm commissioning must be itemised separately.
- ←
BOQ measurement of system commissioning versus single-machine trial runs: heating and air-conditioning water system commissioning (code 031008) and ventilation works inspection, commissioning and testing (code 030704) listed 'by system', while equipment installation items already include commissioning of the unit and single-machine trial runs and are not separately payable
GB/T 50856-2024 Clause 3.0.11 provides that the equipment installation work content of this standard includes commissioning of the equipment itself and single-machine trial runs - single-machine trial runs may therefore not be listed as a separate BOQ item nor priced under a separate commissioning quota item; what is listed separately and measured 'by system' is the system (interlock) commissioning group of BOQ items: heating and air-conditioning water system commissioning per Table K.8.1 (code 031008), ventilation works inspection, commissioning and testing per Table G.4.1 (code 030704), and fire protection system commissioning under Annex J code 030909.
- ←
Quota measurement-unit conversion and line-item splitting for fabrication and erection of supports and hangers (pipe supports / metal supports and steelwork): the three bases 100kg, kg and t; the support-quantity reference table where the design is silent; the switch to equipment supports above 50kg per assembly; and the no-double-count test where the cable tray line item already includes support and hanger erection
Quota quantity = support net weight (kg) divided by the quota unit weight: the same net weight of 100.381kg gives 1.004 under the pipe-support fabrication line item in '100kg' units, 100.381 under the metal-support fabrication line item in 'kg' units, and 0.100381 t under the railway 't' unit - conversion is division only, and wastage is already inside the item and must not be multiplied in again. Under DB11/T 2382-2024 table C.10.23-1, C10-4-1 fabrication and C10-4-2 erection of general pipe stands are per 100kg (section steel 105kg per 100kg, implying about 5% wastage), steelwork-type metal supports are per kg, and railway items such as TB/T 10832-2024 PY-365~370 are per t; where the design is silent, pipe support quantities may be taken as the kg/m reference values of table 6.10.39 x pipe length; where one assembly weighs more than 50kg, equipment-support fabrication and erection applies. The cable tray erection line item already includes support and hanger erection, so the site-fabrication route adds only the 'fabrication' item - erection must not be charged again.
- ←
Commissioning of power supply and distribution apparatus systems - unit of measurement and the rules for splitting the number of 'systems': division per the electrical schematic diagram, systems counted by qualifying circuit breakers (rated tripping current no less than 100 A, etc.), circuits from distribution boards direct to motors counting only motor commissioning, and cable tests and insulation withstand already included
Commissioning of power supply and distribution apparatus systems is measured in 'systems' (GB/T 50856-2024 Table D.16.1 electrical testing and commissioning, code 030416, quantities per the design drawings), the systems being divided on the electrical schematic diagram; the items up to 10 kV apply to low-voltage supply circuits from distribution apparatus to sub-distribution boards, the quantity being the number of circuit breakers in the works meeting all of: rated tripping current no less than 100 A; not a breaker on the HV or LV side of a transformer or inside a motor control board or cabinet; not a breaker serving only maintenance isolation with no protective role in the design - and each unit works counts at least one circuit; circuits from a distribution board direct to a motor count only motor commissioning; cable tests and insulation withstand are already inside system commissioning and are not counted again.
- ←
Cable laying in vertical shafts (electrical risers): choosing the quota line item, the labour factor adjustment, and pricing the shaft and horizontal sections separately (including where reserve lengths sit and the link to the BOQ code)
DB11/T 2382-2024 clause 6.4.59: cable laying in vertical shafts does not distinguish whether floors exist within the shaft - it follows the corresponding cable laying items, with labour consumption preferably multiplied by a factor of 1.30 (the 2021 edition said labour workdays multiplied by factor 1.3); the factor adjusts labour only and acts on the shaft section only, so one cable must be priced in a shaft section and a horizontal section under separate line items - multiplying the whole cable on the shaft basis does not hold; pre-fabricated branch cables are already comprehensively measured for shaft laying and take no factor; the cable laying length already includes reserve (additional) length, and no separate item is listed; on the BOQ side cable installation is Table D.9.1 code 030409, and shaft laying is a different item description from other laying methods.
- ←
Attribution of quantity gaps between BOQ quantities and quota quantities, and the rate conversion: all-in unit rate P = Sum(Tn) / Q, four destinations of quantity gaps (into the BOQ quantity / into the rate / into quota consumption / into the risk allowance), and conversion points for typical work items
BOQ quantities and quota quantities must be kept on two separate tracks and never swapped: first attribute each quantity gap to one of four classes - content already built into the measurement rules (working space for earthworks) goes into the BOQ quantity; content listed under 'work content' but given no quantity (battering, shoring boards, base trimming and clearing) goes only into the ancillary-works cost or risk allowance inside the all-in unit rate; content carried by the quota through wastage rates or contents (material wastage, rebar wastage plus construction bars at 5%, permissible overbreak in rock works, 0.50m over-concreting of bored piles) goes into the numerator, the quota line-item totals; whatever neither the BOQ nor the quota provides can only go into the rate risk allowance. The conversion formula is P = Sum(Tn) / Q (P rounded to 2 decimal places, Tn kept at full precision without rounding, Q rounded to 3 decimal places). Quoting with quota quantities passed off as BOQ quantities is an explicit error: the dimensional bases differ, the all-in unit rate is understated (omission ratio = 1 - quota rate / all-in rate), and it blurs the parties' respective responsibilities for BOQ accuracy.
- ←
Choosing the format of the all-in unit rate analysis sheet, its mandatory preparation requirements, and its roles across tendering, settlement and audit (GB/T 50500-2024 Appendix E, tables E.2.2-1 and E.2.2-2)
GB/T 50500-2024 Appendix E provides that detailed all-in unit rate analysis shall follow table E.2.2-1 and simplified analysis table E.2.2-2, the choice being fixed by the tender requirements and the contract; the rates in the analysis sheet and the prices of lump-priced items must be 'completely consistent' with the corresponding figures in the BOQ (clause 3.1.7); at tender the sheet, together with tables E.3.2, E.3.3 (which must list initial set-up, mid-term operation and final dismantling costs) and E.3.4, must be submitted in full, consistent with the priced BOQ (clauses 6.2.12 and 6.2.13). The all-in unit rate carries risk costs within the agreed scope and bands and excludes VAT (clauses 2.0.9 and 3.2.2), so the risk allowance sits inside the rate build-up rather than as a stand-alone charge. At settlement, clause 3.1.6 requires item-by-item checking that rates match the priced BOQ in the contract, with no adjustment except for variations and agreed matters; dayworks and additional works may draw on 'the detailed price make-up in the all-in unit rate analysis sheet of similar BOQ items' (clause 8.6.3; cost expert assessment guideline clause 4.8.4); audit examines whether new rate build-ups follow the quota pricing rules agreed in the contract, whether every line-item price is fixed, and whether common material prices are reasonable.
- ←
Re-derivation of the all-in unit rate when a changed construction method makes the quota machine-shift consumption inapplicable: the three-path quota conversion test, the hierarchy of bases for recalculating plant consumption, the requirements for recasting the all-in unit rate analysis sheet, and the procedure for confirmation by the employer
Changes of construction method and plant usage are factors expressly listed in GB/T 50500-2024 Clause 8.9.1 as changes of item description or construction condition that can trigger adjustment of the all-in unit rate, but conversion must step down level by level: a conversion line item within the same chapter (DL/T 5468-2013 Clause 4.1.4 item 1: 'where the technical conditions prescribed by the quota (index) differ materially from the actual conditions of the works, the applicable quota (index) may be adjusted and applied according to the technical conditions of the works and the provisions of the quota') -> an express quota coefficient -> borrowing a similar process -> building up a rate from supplementary consumption (GB/T 51095-2015 Clause 5.3.12; TB 10801-2024 Clause 2.4.3); with no express coefficient, none may be invented. The hierarchy for recalculating machine-shift consumption is: contractor's in-house norms (GB/T 50875-2013 Clause 2.3.3) -> construction quotas (Clause 2.3.5) -> budgets or final accounts of similar works, or site measurement records certified by both parties (DL/T 5468-2013 Clause 4.1.4 item 2). After conversion, the all-in unit rate analysis sheet must be recast (GB/T 51095-2015 Clause 5.3.9; GB/T 50500-2024 Clause 6.2.12 and Annex E Table E.2.2-1) and submitted to the employer under the 'submission, checking, review, re-examination and confirmation' procedure (Clauses 8.1.2 and 8.1.3; for additional works, the project execution plan or implementation scheme and the priced offer must also be submitted before execution, Clause 8.10.2). The original quota line item must never be applied in departure from the approved construction scheme.
- ←
Pricing comparison method for prefabricated supports versus site-fabricated supports: precondition test of the billing itemisation basis, item-by-item comparison of cost components (principal materials / wastage / fabrication labour and plant / anti-corrosion and galvanising / installation labour), comparison of fabrication and installation quota line items, and the code-based selection rule that favours prefabrication
Prefabricated supports (billed per set) and site-fabricated supports (steel sections priced by kg through fabrication plus installation quota line items) cannot be compared directly as CNY/kg against CNY/set. The billing itemisation basis must first be tested under GB/T 50856-2024 clause 3.0.10: without a special design requirement, supports and hangers are already included in the all-in unit rate for pipe installation and must not be listed separately; with a special design requirement (Annex N, code 031301), prefabricated supports are billed per set and supports and hangers per kg, while seismic supports are always coded as prefabricated supports per set and must not be converted into kg to apply fabrication line items. The cost component differences concentrate in four points: whether the principal materials include fittings, anchors and galvanising; site fabrication labour and hot-work cutting plant; consumables such as welding materials and gases; and the anti-corrosion grade (fabrication line items include ordinary anti-rust paint plus ready-mixed paint only, and hot-dip galvanising must be priced separately).
- ←
Pricing yardstick of the railway works budget quota manual for demolition works: counting only labour and machine-shift consumption multiplied by demolition coefficients by object category, excluding material cost, plus operating-height adjustment coefficients
The railway quota system sets no separate demolition line items: the corresponding installation line item is taken and multiplied by a demolition coefficient. The Volume 8 (Power Works) preamble Table 3 of TB/T 10829-2024 multiplies both labour and machine-shift consumption by 0.40 for lighting fittings, transformer and distribution boxes, control/power/lighting packaged cabinets (boxes), cable brackets, cable troughs and trays; 0.75 for concrete poles and foundations; 0.80 for angle-steel towers, steel-tube towers, beacon towers, light bridges, steel columns, busbar structures and their foundations; 0.50 for overhead lines and cables; 0.65 for underground cable routes. The information works and signal works volumes under Guotie Kefa [2017] No. 33 give 0.7 for wiring systems and outdoor/indoor cables and 0.5 for equipment and materials, and expressly count 'only labour and machine-shift consumption (excluding instruments and meters)' with no material cost.
- ←
Determining whether vertical transport preliminaries double count the machine-shift rates of tower cranes and builder's hoists: the BOQ item coding basis, the inclusion and exclusion boundaries in provincial consumption quota chapter notes, and a method of checking whether the plant rate is included or excluded via the machine-shift content and unit of measurement of quota line items
No double counting. The machine-shift running rates of tower cranes and builder's hoists are already embedded in the pricing of the vertical transport preliminary item (GB/T 50854-2024 Table R.1.1 preliminary items, code 011601; former GB 50854-2013 Table S.3, code 011703); the vertical transport charge is the very pricing carrier of those machine-shifts, and no separate 'tower crane machine-shift charge' or 'builder's hoist machine-shift charge' may be listed. Only the parts expressly excluded by the quota chapter notes may be priced separately: off-site transport of plant, first-time erection and dismantling, subgrade bedding, track laying and removal, plus the foundations of tower cranes and hoists and the connections of cranes and hoists to the building. Determination uses a three-step check: read the inclusion and exclusion lists in the chapter notes -> check whether the labour, material and plant columns of the line item already list those machine-shifts -> check the unit of measurement and pricing basis (pricing per gross floor area is a lump-sum basis; pricing by hired machine-days must not also be charged by area).
- ←
BOQ rules for measuring cable trays and raceways by the metre, and the pricing boundary of fittings such as elbows and tees (no separate BOQ itemisation, the installation cost of fittings included in the tray installation quota line item, fire stopping measured separately)
Cable trays and raceways are invariably measured in length 'm' as shown on the design drawings, not by 'piece/unit'; the lengths occupied by elbows, tees, crosses and reducers are not deducted (DB11/T 2382-2024 Clauses 6.4.106 and 6.4.111); at BOQ level they are not itemised separately, and at quota level the installation cost of the fittings is already included in the work content of the tray installation line item (e.g. Beijing line item C4-11-253, whose work content includes 'elbows, tees or crosses... support and hanger installation, earthing'), so no separate installation line item may be applied 'per piece'; fire stopping of holes where trays pass through fire compartment walls is measured separately under fire barrier board and similar items (Beijing C4-8-497, in m2) and is not included in tray installation.
- ←
The pricing boundary between cable laying costs and cable termination fabrication and installation costs: two measurement lines (m and count), the split of work content, and four no-double-counting tests (Jing Jian Fa [2021] No. 201, general installation, volume 4, chapter 8, cables)
Cable laying is measured in 'm' and power and control cable terminations in 'count' - two parallel measurement lines; the coexistence of the two costs on one cable is not by itself duplication. Duplication arises only in three situations: the laying item's rate (work content includes only 'temporary sealing', with no stripping, no crimping of lugs, no termination installation) already contains the termination process; the termination count does not match cables x ends + joints; the 1.5 m maintenance allowance at terminations and the 2.0 m reserve at each end of joint boxes are added a second time outside the laying length. The tests: different units; mutually exclusive work content; reserves counted once only; quantities and factors not stacked (10kV single-core terminations / joints x 0.4; five-core laying x 1.15 applies to laying consumption only).
- ←
Stages and charging of landscape greenery maintenance: the start points of construction-period, establishment and conservation (routine) maintenance, the period adjustment factors and the quantity measurement objects
Greenery maintenance divides into three non-overlapping stages: construction-period maintenance (planting to completion acceptance) is inside the planting items, never charged again; establishment maintenance runs in 'months', quantities by plant counts for trees, shrubs, climbers, standards and bamboos, length for hedges, area for lawns, flowers, colour bands, perennials and aquatics - Beijing counts from completion of planting, part months as whole months, and the part beyond one year at x 0.85 (Hunan: within one year of the planting unit works' passing acceptance - months 1-3 on establishment items, months 4-12 labour-material-plant x 0.8); conservation (routine) maintenance runs in 'years' from passing completion acceptance, its term per design or contract. Hence aquatics etc. 'plant by count, maintain by area'.
- ←
Selecting quota items for drip lines and drip grooves: the two routes of mortar beads / pressed grooves versus proprietary drip strips, the application and unit of moulded-render (decorative-line) items (extended metres or area), and avoiding double pricing against the element's finish plaster
No edition of the building and decoration consumption (budget) quotas carries an item named 'drip line / drip groove': for mortar-bead or pressed-groove drips, where the local quota has a 'moulded render (decorative line)' item, apply that item by extended metres (10m / 100m); without it, merge into the element's plaster by area with no extra charge. Proprietary metal / PVC drip strips take the proprietary decorative-line items with main-material conversion, by the metre. Where window-sill lines, string courses, eaves projections, parapet cappings, sun-shade edges etc. have already been priced as moulded render, the drip formation is deemed included - no further extended-metre drip line may be added.
- ←
Curtain boxes and curtain tracks (rods): BOQ itemisation, quota item selection and units - proprietary erection and site fabrication listed apart, measurement by extended metres, tracks never merged with boxes
Curtains, curtain boxes and tracks are itemised per GB/T 50854-2024 Table H.10.1 (code 010810), measured by length (extended metres) from the drawings, never developed area; proprietary boxes take 'proprietary erection' items and site-made boxes 'fabrication and erection' items, the proprietary box entering as an unpriced main material; curtain tracks and rods are not inside the box items - every quota volume sets separate items, and they must be listed apart.
- ←
Whether roof steel purlins, horizontal bracing and tie rods list separately: purlins are independent flexural members listed apart by mass; bracing and ties take 'horizontal steel bracing / tie rod' items - never merged into roof trusses nor mistaken for excavation-retention struts
Steel purlins run across the trusses carrying the roof build-up - independent flexural members functionally unlike trusses - and list separately in both quota and BOQ, by mass (t) from the drawings. Railway TB/T 10831-2024 Volume 10 sets 'steel purlin fabrication and erection' apart: fabrication in three bands - pipe (FY-724), C and Z sections (FY-725), other sections (FY-726) - plus one erection item (FY-727), all in t; in its member classification purlins, bracing and ties all sit in class II. Beijing DB11/T 2382-2024 Appendix A.6.5 sets 'horizontal steel bracing / tie rods (cold-formed)' items taking the top-chord plan bracing, bottom-chord horizontal bracing, column bracing and ties, by t; roof bracing never takes the excavation-retention strut items.
- ←
The depth standard for describing item descriptions in the bill of quantities: describe item by item per the appendices, satisfy the needs of fixing the all-in unit rate, and never substitute the quota work content (trades)
The item description is the pricing parameter that fixes the all-in unit rate; the depth floor is 'describe item by item per the item descriptions prescribed in the appendices of the corresponding discipline measurement standard + satisfy the needs of fixing the all-in unit rate' (GB/T 50854-2024 clauses 4.2.4, 4.1.2). Citing a standard drawing collection or drawing number covers only 'the part it can satisfy' - the rest still needs words (GB 50860-2013 clause 4.2.4 commentary). Copying the work content (trades) of the quota / appendices replaces no item description: work content defines the included scope of the offer and the trade boundaries, and trades must not be split into separate items - copying produces no pricing parameters such as material, grade or strength class, and invites trade-splitting double pricing.
- ←
Classifying and measuring slope treatment works by protection type: plant protection by slope area, masonry protection by masonry volume, anchoring and facing listed apart (anchor length / mass + facing area), SNS flexible nets by laid area with anchors and posts separate
Slope treatment pricing first fixes the sector system (railway / highway / municipal) and the protection type, then itemises on the measurement line: (1) plant protection (grass seeding, hydro-seeding, geotextile mats, planting bags) by laid slope area; (2) masonry protection (mortared rubble slope protection, skeleton (rib) protection, protection walls) by solid masonry volume, rendering and pointing extra by area; (3) anchoring + facing (anchor-mesh hydro-seeding, shot-seed-mix, anchor-mesh shotcrete) split with anchors by design length / mass and facings by area / volume; (4) SNS flexible protection nets by design laid area, with anchors and post foundations / posts listed separately. What the work content already includes (meshing, scaffolds, energy dissipators etc.) is never listed again.
- ←
BOQ itemisation and quantity take-off of non-destructive testing of pipe welds: 030813 non-destructive testing and heat treatment, 030308 non-destructive inspection, and the number of radiographic films derived from the 250mm effective film length
Non-destructive testing of pipe welds must be a separate BOQ item, not merged into pipe installation: industrial pipework per GB/T 50856-2024 Appendix H Table H.13.1 (code 030813, non-destructive testing and heat treatment); static equipment and process metal structures per Appendix C Table C.8.1 (code 030308, non-destructive inspection); heat treatment and NDT of water supply and drainage, heating and gas pipework revert to the corresponding Appendix H codes. The number of radiographic films = the total length of welds to be inspected computed per the design / the effective film length, the effective film length being taken as 250mm where the design is silent. Inspection cost is built up by fixing the physical quantity as method x ratio x base - not estimated as a percentage of the pipe cost.
- ←
Pricing and measurement of CCTV/QV/sonar in-pipe inspection: extended metres along the centre line of the pipe or culvert without deducting manholes, line items banded by diameter and inspection method, working conditions (water level, clearing and cleaning) and excluded work charged separately
CCTV in-pipe inspection of pipelines is measured in metres (m) by the extended length of the centre line of the pipe or culvert as designed (actually inspected), without deducting the length occupied by fittings or manholes; the CCTV line items are banded by internal diameter or height of the pipe, with 100m as the line-item unit, and QV and sonar likewise. The line items comprehensively allow for differences of pipe type, material and age, but exclude pipe plugging and reinstatement, desilting, culvert-wall washing, dewatering, and image analysis and assessment, digital mapping and archiving, and compilation of inspection deliverables, which are charged separately when they occur; desilting for the inspection and repair categories is charged at the labour, material and plant of the corresponding items multiplied by a factor of 1.5.
- ←
Split quota pricing of motorised two-way control valves (temperature-control valves) on chilled-water systems: valve-body item plus electric-actuator item (plus a wiring item) as three charges, versus the single all-in item for ordinary globe and gate valves, and the criteria for charging wiring
A motorised two-way control valve is not covered by one valve line item but split into three charges: the valve body takes a valve-installation line item by connection form and size (DB11/T 2382-2024: threaded valve DN20 is C10-5-2, all-in labour category II 0.060 workdays per valve; welded-flange valve DN50 is C10-5-35, 0.295 workdays per valve); the electric actuator takes the building-equipment-monitoring 'motorised two-way control valve' item (C5-3-59 up to DN50, 0.522 workdays per valve; C5-3-63 up to DN100, 1.017 workdays per valve, the work content already including actuator installation, wiring and testing); wiring is charged separately or not depending on which volume applies (electrical volume C4-4-156 'valve wiring', 0.126 workdays per valve; instrumentation volume C6-2-45/C6-2-46 'valve check-out and wiring', 0.290/0.336 workdays per unit, only for control valves already installed on industrial pipework). Ordinary globe and gate valves are covered by one line item whose work content already includes pipe cutting, beveling, flange gasket fabrication and installation, valve and flange installation and pressure-test-pump machine-shifts.
- ←
Measurement unit rules for landscape greening maintenance: trees and single shrubs per plant, massed shrubs, ground cover, flowers and lawns by area, single and double hedges by extended metres, with item units as plant-months / 10 plants per month / 100 plants and the like
Maintenance measures by plant class: trees (evergreen / deciduous), single shrubs, palms and climbing plants count per plant on drawn quantity, items often converted to 100 plants, 10 plants / month or plant-months (railway LY-339 / 340 tree upkeep per 100 plants; Beijing E-2-547 establishment upkeep of evergreen trees in plant-months; Shaanxi 1-542 to 1-545 evergreen tree upkeep per 10 plants / month); massed shrubs, ground cover, open-ground flowers, lawns and vertical-wall greening by drawn area (massed shrubs often per 10 m2); single and double hedge upkeep by drawn extended metres (railway LY-343 / 344 per 100 m); water-truck watering by water volume or plant size.
- ←
Pricing and member-wise itemisation of stone balustrades (granite balustrades): the basis test, the post / panel / sill items and their measurement rules
Stone balustrades route by works basis first: landscape / scenic and antique-style balustrades (posts + panels + continuous sill as grouped stonework) take Beijing 2024 antique volume B.2 stonework (B-2-15 to B-2-19) or landscape volume E.3.3-10 / 11; modern stone panels of stairs, corridors and outdoor platforms take building volume A.15.3-7. Member-wise measurement: sill stones by length m (landscape) or volume m3 (antique); posts by size per piece; Xunzhang and Luohan panels by drawn height x base length in m2; drum-end stones by base length x mean height in m2. BOQ itemisation per GB/T 50855-2024 Table B.2.1 (code 020202) or GB/T 50854-2024 Table Q.3.1 (code 011503).
- ←
Measuring and pricing the hand-laminated joints of GRP pipes and ducts (resin-impregnated lay-up joints, resin filling and joint reinforcement): the lamination sits inside the pipe / fitting / duct installation items' work content, not itemised separately; only where the joint form exceeds the quota range does it count separately per joint or per developed lamination area
The hand-laminated joint of GRP pipes and ducts is no independent quota item: its resin filling, glass-cloth reinforcement and glue-smeared insertion are written into the work content of the pipe (fitting) / duct installation items, so pricing follows pipe length (m, unit 10 m, on the drawn centre line without deducting fittings and valves), fitting count (pieces, unit 10) or duct developed area (m2, unit 10 m2), not per joint; only where the designed joint form exceeds the quota's scope (site butt joints with double-sided lamination, hand-laminated joints of finished ducts on site) does it count separately per joint or per developed lamination area, applying hand-laminated GRP items (GB/T 50856-2024 Appendix M Table M.3.1, code 031203) or a supplementary quota compiled on quota principles and approved.
- ←
Measuring and pricing drainage (discharge) pipes: fixing the measurement basis and quota items by scenario - roofs, urban rail transit, municipal bridges and culverts, railway bridge decks
Drainage pipe measurement splits by scenario: pipe bodies (downpipes / drainage pipes / the discharge pipes themselves) by drawn length in m (extended metres), and finished parts - discharge outlets, rainwater heads, hoppers, drain inlets - by count (per set / per piece). Building roofs follow DB11/T 2382-2024 Articles 4.10.21 to 4.10.23 (downpipes by length; hoppers, bends and drain inlets by count; roof drain (drip) pipes and vent pipes by count); urban rail follows Article 10.1.90 of the same standard (discharge pipes by length); municipal bridges follow SJG 181.2-2024 Article 7.2.4 (drainage pipes and weep holes by length in metres); railway bridge-deck drainage quotas count per 10 extended metres. The same member carries different units across industry quotas - apply the volume the project executes.
- ←
The per-set (per-group) measurement of sanitary ware: what water and drainage fittings a set contains, how twin (double-basin) wash basins count, and whether fixture-matched fittings charge separately
GB/T 50856-2024 Table K.3.1 sanitary ware (code 031003) counts per set on the drawn quantity; one set = the fixture + the full water supply fittings (taps, flexible hoses, valves, flush pipes, sprays) + the full drainage fittings (traps, waste plugs, drain inlets) + the fixture's connecting pipes; non-independently installed fittings already sit in the fixture's work content and are not re-listed. The standards set no twin wording for double basins - deriving from one set = one basin position: two basins each independently supplied and drained count 2 sets; a one-piece twin sharing one supply and drain counts 1. Fitting installation costs are inside the fixture items and not re-charged, materials priced separately as unset main materials; only independently installed taps, floor drains and floor cleanouts itemise and measure alone.
- ←
Routing grouting items when existing-line strengthening uses grouting under the 2024 railway budget quotas: the bridges and culverts volume's existing-line strengthening and protection items exclude grouting; grouting routes by location and slurry type to the subgrade volume's underground cavity treatment, the buildings volume's grouting reinforcement and the tunnel volume's mining-method support items
The existing-line strengthening and protection items of TB/T 10823-2024 Volume 2 Bridges and Culverts (QY-843 to QY-846, banded by strengthening length up to 5 m / 7 m x timber / concrete sleeper sections, unit per track) have work content limited to hoisted rail beam erection and removal, sleeper replacement, track dressing and ballast topping-up and track protection (concrete-sleeper sections adding reinstatement of reinforced concrete sleepers) - no grouting. Grouting in existing-line strengthening routes separately by location plus slurry type: subgrade / underground cavities under TB/T 10822-2024 Volume 1 Chapter 7 underground cavity treatment (drilling LY-443-446; grouting LY-447 cement mortar, LY-449 sleeve-valve cement grout, LY-448 sleeve-valve cement-silicate double slurry 1:0.8); general soil under TB/T 10831-2024 Volume 10 grouting reinforcement (layered grouting FY-293/294, compaction grouting FY-295/296); tunnel locations under TB/T 10824-2024 Volume 3 mining-method tunnel support (advance-support grouting SY-119/120, advance reinforcement SY-123-129, perimeter reinforcement SY-130-132, surface reinforcement SY-133-137). Drilling and grouting are separate paired items; double-slurry items carry far higher material shares than plain cement grout.
- ←
Routing monitoring / signal poles and their concrete foundations to quota disciplines: poles to general installation or municipal works, foundations always charged separately under building civil works
The discipline routing of monitoring / signal poles turns on whether the road sits within municipal jurisdiction: poles (monitoring poles, street lights) along plant and residential-estate roads follow general installation works electrical equipment installation (GB/T 50856-2024 Appendix D); only city-road lighting systems / municipal traffic facilities follow GB/T 50857 municipal itemisation. The concrete foundations of poles and equipment (including foundation earthworks and anchor-bolt embedment) are excluded by every installation item and follow the building and decoration (or structures) works items, with secondary grouting under machinery installation.
- ←
Deciding when large plant mobilisation and erection charges are priced separately, and the cost make-up (with quota item codes, trip counts and haul-distance rules)
Large-plant mobilisation and erection charges follow a three-type test: plant needing no erection, self-moving or fixed in position is uncounted; light plant with simple erection but needing cranes and transport to move is spread into the machine-shift rate (erection charge = budget price x erection coefficient / total durable machine-shifts); heavy plant with complex erection and crane / transport moves (tower cranes, builder's hoists, shields) is itemised per machine per trip and computed separately. The same sum must not be counted both in the machine-shift rate and as preliminaries; tower crane and builder's hoist bases and ground improvement are charged separately. Codes: building 011601, structures 070304, landscape 050404, urban rail per GB/T 50861-2024 Appendix M M.2.4.
- ←
Where waterproofing primers (cold primer oil / primer coat / substrate treatment agent) sit in membrane waterproofing quotas: included in the membrane items or to be itemised separately
The test is not the operation's name but whether the executed membrane item's work content states brushing the primer and its consumption table lists the primer material: stated and listed means included - no separate itemisation, which would double count. The railway TB/T 10831-2024 Volume 10 roofing membranes FY-983 to FY-1000 and basement / kitchen / bathroom membranes FY-941 to FY-957 all list brushing primer in the work content - included, not recharged; TB/T 10834-2024 Volume 13 station works notes state that membrane seams, edge terminations and screed joint sealing are already in the quota while the cement mortar screed itself is not (screed chargeable, its sealing included). Beijing DB11/T 2382-2024 membrane items include brushing primer and set no separate cold-primer item; a few systems do set one (Jiangsu 2026 items 9-132 / 9-133 cold primer oil, first and each additional coat; Shenzhen SJG 181.5-2024 dedicated primer under other waterproofing), used only where the quota excludes it or the design requires separate application.
- ←
Adjusting haul-distance changes in quota transport items: items are compiled as a base-haul band plus increment bands; cost is not proportional to distance, so scaling by distance ratio is forbidden
Quota transport items come in a banded ladder of a base haul band plus an increment band; each band's cost carries distance-independent fixed consumptions - loading and unloading, waiting, empty returns - so cost is not proportional to distance: a shortened haul must not be scaled by ratio (1 km cut to 200 m is not x 0.2); where a first band up to 200 m exists, apply that band directly; where the first band is 1 km or more, 200 m still falls within it and the base item applies without reduction; only beyond the first band does base item + increment item x number of increments stack, the count rounding at the half (a remainder under half an increment unit is dropped, at half or more it counts as one); adjusted items must carry a conversion mark on the item number.
- ←
Measurement basis split for pricing daylighting canopies (PC multiwall sheet / glass / stainless steel frame) by quota: the surface layer by area, independent supporting frame by mass
A daylighting canopy cannot be priced under one blanket basis; it splits into two layers: the surface layer (PC multiwall sheet, glass, metal sheet) applies the sunlight-sheet roof / daylighting roof items, measured in area (m2) on the dimensions shown on the drawings, with the attached framing already included in the item and not listed separately; the load-bearing steel columns, beams, trusses, monitor frames, supports and the like apply the metal structure works items, measured in mass (t) on the dimensions shown (no deduction for holes; welding electrodes, rivets and bolts add no mass). Paint and fireproofing coating are not in the metal member items and require the painting works items separately. The dividing test: frame members belonging to the daylighting item's attached framing merge into the surface layer by area; independent load-bearing structure is listed separately by mass. The national standard takes the same view - GB/T 50854-2024 Appendix J requires the roof trusses, purlins and other supporting structures of sunlight-sheet and GRP roofs to be itemised under Appendix F metal structure works and Appendix G timber structure works codes.
- ←
Construction of screed division joints and the charging boundary of their sealing: the cement mortar screed itself is not in the waterproofing quota and is chargeable, but membrane seams, edge terminations and screed joint sealing are already included and must not be recharged
The dividing line runs between the screed itself and the sealing of the screed: per the volume notes of TB/T 10834-2024 Volume 13 Station and Yard Works, the waterproofing quota does not include the cement mortar screed, which may be charged separately under the relevant quotas; but the seams and edge terminations of the waterproof membrane and the sealing of the screed are already included and must not be charged again. So under the railway station waterproofing items, sealing the screed division joints with waterproof mastic is not listed separately; only in systems carrying sealing as an independent item by metre (e.g. DB11/T 2382-2024 Table A.9.6-2 sealing, A-9-268 roof concrete division joint sealing, A-9-269 movement joint sealing) is it listed by metre under those items. Construction-wise the division joints are mandatory: screed division joints at spacing preferably not over 6 m both ways, width preferably 5-20 mm, with division joints also between the screed and parapets and the walls of roof-mounted tank rooms, stair enclosures and vent cowls, the joints filled with sealing mastic (DB11/T 1832.9-2022 Article 3.4.8).
- ←
Choosing the pricing route and item attribution for electrical handholes / manholes under quotas (power cable chambers, street-lighting pull pits, telecom manholes / handholes, precast vs cast-in-place)
Pricing a cable working chamber first chooses between two routes: (1) whole-chamber comprehensive items (unit per chamber, work content covering the base, masonry or casting, rendered and waterproofed walls, covers and frames, even pit excavation and backfill outside - no further sub-items covered by them); (2) split combined items (blinding / masonry base / formwork / rendering / cover fabrication and installation / cover and seat listed separately, units m3 / m2 / set). Power (electric cable) chambers go to the power / cable line chapters (e.g. TB/T 10829-2024 Volume 8 DY-341 to DY-349 cable manhole fabrication); street-lighting pull pits and telecom manholes / handholes go to the telecommunications / ducting chapters (e.g. TB/T 10826-2024 Volume 5 TY-60 to TY-69 masonry manholes / handholes). Whether precast concrete chambers can be applied depends on the item's workmanship: DB11/T 2382-2024 Table F.1.5-2.3 standard concrete cable chambers is a cast-in-place work content and cannot be applied as precast; precast members and shafts are measured by volume / length per Articles 7.4.15 / 7.4.16, and where no precast chamber item exists it is a gap requiring a supplementary quota and approval.
- ←
Three-step test for the unit price basis of cofferdam and island-building clay (borrowed fill): no extra charge where the quota already includes borrowing; priced per quota consumption where clay is listed as a material and adjusted as executed; purchased fill follows the fill material cost / norm-based material price basis
Cofferdam clay unit prices follow a three-step test (a decision order, not three alternatives): (1) where the quota item's work content already includes borrowing, no clay material cost is charged - the railway TB/T 10823-2024 Volume 2 plastic woven sack cofferdam work content includes excavation, manual bagging and haulage within 20 m, and its consumption table lists no soil material; (2) where the quota lists clay in the material consumption, price by the quota consumption and adjust at settlement per the actual borrowing (SJG 181.2-2024 Article 8.1.7 paragraph 2); (3) where purchase is genuinely required, the railway uses the fill material cost basis - fill material cost = sum of fill consumption x fill price (TB 10801-2024 Article 3.5.2), the fill price excluding deductible input VAT and being determined by the design institute through investigation and analysis (TB 10811-2024 Article 2.5.1); highways take purchased materials by reference to published prices combined with surveyed market prices, and self-quarried clay at the quota winning price plus auxiliary production on-costs and mineral resources tax.
- ←
Whether duct elbow (duct) turning vanes are separately itemised, their quantity measurement basis and pricing rules: duct items exclude turning vanes and local consumption standards set separate items; Shenzhen measures vane area in m2, Beijing counts the quantity shown on the drawings
Duct elbow turning vanes must be separately itemised and separately priced - the duct body items' work content covers only fittings such as elbows, tees, reducers and square-to-round transitions plus flanges, stiffening frames and hangers, not turning vanes; local consumption standards set separate elbow turning vane fabrication and installation (assembly) items, and single vanes and banana-type double vanes all apply the same item. Two measurement routes: Shenzhen SJG 111.3-2022 Article 4.2.2 paragraph 4 - elbow turning vane fabrication and installation is measured in square metres by the vane area shown on the drawings, and where the design is silent by Tables 4.2.2-1 (approximate area of each vane in rectangular bends) and 4.2.2-2 (number of vanes in rectangular bends); Beijing DB11/T 2382-2024 Article 6.7.33 - elbow turning vane fabrication and assembly quantities are calculated per the quantity shown on the drawings or per code requirements. GB/T 50856-2024 Appendix G Table G.2.1 (duct fabrication and installation, 030702) sets no vane BOQ item; in pricing, itemise as a supplementary BOQ item or, after stating it in the 030702 item description / work content, include it in the all-in unit rate, per the contract pricing rules - never both merge it into the duct all-in unit rate and list a separate item.
- ←
BOQ itemisation and quota item scope for lightning protection and earthing devices in street lighting works: code 040806, the chapter's item composition, and excluded contents such as lump-sum earthworks, testing and soil replacement
The BOQ item for lightning protection and earthing devices in street lighting works follows GB/T 50857-2024 Appendix H Table H.6.1 lightning protection and earthing works (code 040806); in quota terms the chapter's items are earth electrode fabrication and installation, earth busbar laying, earthing jumper installation, lightning rod installation and lightning protection down-conductor laying, of which the earth electrode and earth busbar items exclude construction by blasting, soil replacement in high-resistivity soils, chemically treated earthing devices and earth resistance testing; earth busbar laying is comprehensively compiled for natural ground level and ordinary soil, including trench excavation, backfill and compaction - applying the chapter's items, earthworks are not calculated again, while rock, slag, ponded water and obstructions are calculated separately. Under the general installation basis, earthing electrodes and busbars are itemised and measured per GB/T 50856-2024 Appendix D and must not be mixed with the municipal code 040806.
- ←
Quota application and the four-stage pricing and measurement method (mixing, haulage, spreading and rolling, curing) for cement-stabilised crushed stone (cement-stabilised base) base courses
Pricing a cement-stabilised crushed stone base starts from the mix source: with purchased commercial mix, only one base spreading-and-rolling item is applied - mixing is already in the priced material and is not itemised again, and curing is in the item's work content and not itemised; with site mixing (in-place road mixing / central plant mixing) the works split into mixing + haulage + spreading and rolling. Haulage stacks a base haul distance plus increment hauls; where the average haul exceeds 15 km the haulage cost is calculated at market rates; where the mix proportion differs, materials are converted by Ci = [Cd + Bd x (H - H0)] x Li / Ld; where the compacted thickness exceeds the limit and mixing and rolling are done in layers, grader and roller machine-shifts are doubled per the quota quantities (DB63 road base over 15 cm: doubled plus 1.5 workdays per 1000 m2; TB/T 10834 station surfaces over 15 cm and base and cushion courses over 20 cm: x 2.0 coefficient).
- ←
Rules for charging vertical transport in high-rise steel structure works, and its cost boundaries against comprehensive scaffolding and steel member erection lifting (preventing double counting)
Vertical transport and comprehensive scaffolding are two parallel preliminary items, each charged under its own rules with no inclusion of the other; steel member erection line items already include member lifting, which must not be charged again through vertical transport. Vertical transport covers only large vertical transport plant (tower cranes, builder's hoists, material hoists etc.), charged by gross floor area (including basements) with line items banded by structural type and eaves height: for steel structures within 20 m eaves height there are dedicated line items (single storey up to 7 m, multi storey up to 20 m and per additional 1 m); above 20 m eaves height the items are no longer split by structural type, only banded by eaves height (20-30 m, 30-40 m, per additional 10 m) and include external builder's hoist machine-shifts; single-storey buildings with eaves height within 3.60 m are excluded; the above-height increase applies one band per additional 10 m, where an excess under 10 m but over 5 m counts as 10 m and 5 m or less is not counted.
- ←
Double-counting test for BOQ items of anti-corrosion coating and fireproofing coating in steel structures: duplicate item-description wording is not double counting; the test is whether both point to the same coating operation / the same coat
Repetition of item-description wording is not in itself double counting - anti-corrosion paint and fireproofing coating are brushed onto the same member surfaces, so similar descriptions are normal. The test is whether the two point to the same coating operation / the same coat: coats in different systems (primer / intermediate coat / topcoat vs fireproofing coating) are independent items settled as executed; only where the same operation is described in two line items, or where one line item's quota work content already covers the other's operation (e.g. a fireproofing coating item whose work content already includes surface rust removal and primer), is the duplicated portion disallowed. Basis: GB/T 50854-2024 Appendix F.10.11 and GB 50205-2020 Appendix J.0.4 (two independent measurement bases), and GB/T 50854-2024 Article 4.1.2 (necessary work already included in the work content must not be split out as a separate item).
- ←
Routing cast-in-situ and precast terrazzo floors under the quota: monolithic finishes (cast, ground and waxed on site - railway FY-1209 to 1213, Beijing A-11-24 to A-11-27) versus tile (precast slab) finishes laid on a bed with the main material swapped - banding and adjustment rules
Terrazzo routing ignores the word "terrazzo" and reads the construction form: site-mixed casting with grinding and waxing is a MONOLITHIC finish taking the terrazzo monolithic items (TB/T 10831-2024 Volume 10 FY-1209 to FY-1213: 15 mm with divider strips / 15 mm with strips, colour-split / mirror 20 mm with strips / mirror 20 mm with strips, colour-split / per 1 mm up or down, all per 10 m2); factory-precast slabs laid on a bed are a TILE finish - GB 50209-2010 clause 6.4.1 "precast slab finishes of cement concrete, terrazzo and artificial stone slabs shall be laid on a bed" - taking tile items with the main material swapped to precast terrazzo slabs (mainstream quotas set no precast terrazzo floor item). Banding follows divider material and grade: ordinary terrazzo takes glass strips, artistic (coloured) takes brass strips; coloured / artistic and mirror stand as separate items, never coefficient-converted.
- ←
Pricing the core filling of hollow blocks (core-column concrete): never merged into the block-wall items - apply the cast-in-place concrete column "core column" item, quantities on hole section area times design-shown height
Block-wall items cover only "mixing mortar, cutting, laying and the like" - core filling is outside; apply the "core column" item among the cast-in-place concrete columns (Beijing DB11/T 2382-2024 A-5-13; 2021 edition 5-13), unit m3; quantities on the hole cross-section area times the design-shown height by volume. Plain and reinforced core columns take the same item; the bars, ties and inserts within them execute under the concrete and reinforced concrete rules. Regions differ (Shaanxi, e.g., already counts the core mortar of vertically laid blocks at opening jambs inside the walling mortar) - apply per the local quota notes.
- ←
Splitting rules for applying consumption items to framed partitions: framing and boards set apart, infills charged separately as insulation, double-faced boards doubled, fire rating never a selection basis (Beijing DB11/T 2382-2024 chapter 4.13 and Annex A.12)
Applying consumption items to fire rock-wool board partitions turns on the build-up and board type, never the fire rating (no "fire partition" subject exists; fire endurance is a design requirement): framed partitions itemise framing and boards separately per DB11/T 2382-2024 clause 4.13.16 item 2; rock-wool and like infills sit outside the partition items per 4.13.20 and execute under 4.11.1 to 4.11.10 (insulation); boards are determined per face, doubled where two-faced, per 4.13.16 item 3; partition quantities per 4.13.27 compute on the frame envelope area without deducting single holes of 0.30 m2 or less.
- ←
Wall and column plaster items in TB/T 10831-2024 Railway Works Budget Quota Manual Volume 10 (building works) - general plaster FY-1346 to 1358, decorative plaster FY-1359 to 1376 - the missing wall levelling screed, and plaster measurement rules
Volume 10 "section 2 wall and column works" sets only (1) general plaster (FY-1346 to FY-1358) and (2) decorative plaster (FY-1359 to FY-1376) - no standalone "wall levelling screed" item; general plaster content already includes "multi-coat levelling and finish trowelling", and only decorative backing runs on FY-1374 "decorative plaster, backing and levelling, 15 thick". Levelling a wall with no finish is a quota gap - never borrow FY-1189 to FY-1193 floor levelling screeds or roof screeds (position, process and measurement all differ).
- ←
Quota line-item application for pneumatic ON/OFF valves (gate/ball valves) under the consumption standard: no separate line item by actuation mode - valve body installation under the piping chapters, checking and wiring under the automatic control instrumentation / electrical chapters, complete-set actuators not split off (DB11/T 2382-2024)
Pneumatic ON/OFF valves (gate/ball valves) are priced as two separate entries: (1) valve body installation applies the valve installation line items of the piping chapter the valve belongs to - industrial pipeline works set items "according to influencing factors such as valve type and size" (6.8.48; likewise medium- and high-pressure), while water supply and drainage, heating and gas works set items "according to influencing factors such as valve type, connection form and size" (6.10.47); the actuation mode (pneumatic/electric) does not create separate line items; (2) checking and wiring follows the corresponding "valve checking and wiring" items of the automatic control instrumentation works (6.6.20 item 1, for regulating valves already installed on the pipelines, such as butterfly valves, on/off valves and shut-off valves), while checking and wiring of electrically actuated valves follows the corresponding items of the electrical equipment installation works (6.8.51). Quantities of electrically and pneumatically actuated regulating valves are measured as complete-set installation and commissioning, including the actuator and the valve, the handwheel and the supplied complete-set accessories, and must not be split off and counted separately (6.6.21).
- ←
Beijing DB11/T 2382-2024 consumption standard: pricing application of the water-tightness test and ball-passing test of drainage pipelines (water-tightness test included in the pipe-laying sub-items, ball-passing test handled by coefficient adjustment on the indoor pipe-installation sub-item - neither itemized separately)
Under Beijing DB11/T 2382-2024 neither test is applied under a separate sub-item: the water-tightness test is already included in the consumptions of "drainage pipeline laying" (7.4.26 - no separate sub-item, no separate BOQ item); the ball-passing test is handled by coefficient adjustment on the indoor drainage pipe installation sub-item (labor x 1.10, other-materials fee ratio +1.00%, other-tools fee ratio +0.05%, 6.10.30, triggered only when required by the design or the code); indoor pipe hydrostatic testing and water flushing are included in the installation consumptions (6.10.25), and the work content of drainage plastic-pipe sub-items additionally includes the water-filling test (e.g. C10-2-104).
- ←
Applying quotas to copper wire in conduit: distinguishing "lighting" vs "power" wire-pulling sub-items (<=4 mm2 classified by use; Beijing 2024 C4-11-284/C4-11-288 compared)
Conduit wire-pulling sub-items are classified by use, not cross-section alone: wires <= 4 mm2 for lighting and similar uses (including ordinary 220 V socket circuits) take lighting sub-items; power uses or lighting circuits > 4 mm2 take power sub-items. 4 mm2 is the overlap tier between Beijing 2024's lighting table (C4-11-284) and power table (C4-11-288) — attribution follows use; Shenzhen SJG 181.7-2024 Clause 6.1.2 states expressly: lighting-circuit conductors >= 6 mm2 execute the corresponding power-circuit wire-pulling sub-items.
- ←
Pricing pavement removal: selection criteria between milling and demolition sub-items, with corresponding Beijing DB11/T 2382-2024 Appendix D municipal sub-items and consumptions
Pavement removal is not a binary choice but split by construction essence: asphalt course shaving (maintenance/overlay, milling machine, milled material loaded and recycled) applies milling sub-items; wholesale pavement excavation (structure abolition, pipeline trenching) applies demolition sub-items; full-depth cement-concrete removal can only apply demolition (the milling group has only a "texturing within 1 cm" tier); pre-overlay surface texturing applies milling - texturing. Criteria: material, depth, and the approved method-statement process — all three indispensable. Beijing 2024: milling group D1-6-14-19 (100 m2), demolition group D1-6-1-6, 8-9, 10-11, 26-29 (pneumatic-pick type per 10 m2, mechanical per 100 m2); milling work content already includes loading (do not double-count loading), demolition only "piling old material" without loading/haul — count separately; demolition of pavement/base courses is computed by area.
- ←
Beijing DB11/T 2382-2024: determining chapter by chapter and material by material whether pipe installation quota line items include pipe fittings (gas piping: only galvanized steel pipe with threaded joints includes fittings; indoor water supply/drainage and heating piping include fittings)
Beijing DB11/T 2382-2024: in gas piping, only the galvanized steel pipe (threaded joints) installation items include fittings and pipe clamps (6.10.34); for welded steel pipe, PE pipe and other materials, the fittings must additionally follow the "fitting and pipe-clamp installation" items; the indoor water supply, drainage and heating piping runs the opposite way - the pipe installation items include the fitting installation content, the fitting materials being taken as the design-shown quantities or per Table 6.10.32 (6.10.32). Pipes are measured along the design-shown centreline length without deducting the lengths occupied by fittings, valves and accessories (6.10.36); fittings are measured as the design-shown number of pieces (6.10.37).
- ←
Measurement rules for the matching flanges of flanged valves: in water supply/drainage, heating and gas works the flanges are not applied separately, while in industrial-pipeline works the valve and its matching flanges are calculated separately (DB11/T 2382-2024)
Per the Beijing local standard DB11/T 2382-2024 "Construction Consumption Standard", general installation works: in water-supply-and-drainage, heating and gas works, the flanged-valve installation sub-items are compiled on the basis of flange connections on both sides - the matching flanges and bolts are included in the valve installation sub-items and flange installation sub-items are not applied separately (where only one side is flanged, the flange and bolt quantities are halved, a consumption adjustment); in industrial-pipeline works "the installation of all flanged valves and the installation of the matching flanges shall have their quantities calculated separately" (6.8.54) - the valve sub-item does not include installation of the flange body (only the installation of one gasket and one set of flange bolts, with bolt materials charged separately), and the matching flanges must be applied under separate flange-installation sub-items; the same basis applies to medium- and high-pressure valves (6.10.52, 6.8.73 to 6.8.79).
- ←
Quota sub-item application and BOQ itemizing basis for special switch panels (sound-light control / key-switch / sensor / residual-current protection) (Beijing DB11/T 2382-2024 sub-items + GB/T 50856-2024 BOQ rules)
The Beijing 2024 consumption standard sets dedicated sub-items for special switch panels (no need to borrow): sound-light control (time-delay energy-saving) applies C4-4-113 time-delay energy-saving concealed switch (0.052 work-days/unit); key-operated switch applies C4-4-115 (0.061 work-days/unit); sensor panels apply C4-4-117 (0.085 work-days/set); rail-mounted residual-current protective switches apply C4-4-48/49 "single-phase" and C4-4-50 "with fuse" (0.05/0.226/0.535 work-days/unit); main materials enter at actual prices. BOQ itemizing per GB/T 50856-2024: sound-light-control types fall under "lighting switches" (Table D.13.1 note 9), residual-current switches under "low-voltage electrical switches / residual-current protective switches" (Table D.5.1 note 1), smart-home panels under Table E.7.1 (code 030507).
- ←
Pricing steel ladders and the built-in ladders (steps) of inspection chambers: quantities by mass at design-shown dimensions, quota item attribution, and the "already inside the chamber item, not charged again" test
Steel ladders are measured by mass (t) at design-shown dimensions, without deducting holes and without adding welding rods, rivets or bolts (DB11/T 2382-2024 clause 4.7.17 item 1; municipal networks clause 7.4.17); steel ladders execute as "stepped steel ladders", embedded or welded-to-insert rolled-angle treads may execute as sundry steel members (clause 4.7.10). The steps / ladders inside inspection chambers are mostly already in the standard-chamber items' work content (e.g. D4-6-178 "chamber step and cover installation"; railway LY-441 "rung installation") and may not be listed again; where a separate item is truly needed, count in kg by design-shown weight (SJG 111.2-2022 clause 3.2.4); finished steps count by design-shown number (DB11/T 2382-2024 clause 9.3.5 item 6). Standard-chamber ladders are compiled in plastic-steel - differing designs convert the ladder material only, all else unchanged (SJG 181.4-2024 clause 3.1.3).
- ←
Attribution and pricing of round-to-rectangular transition ducts (rectangular-to-round reducers) in ventilation and air-conditioning: they are duct fittings priced with the duct fabrication and installation (030702), not listed as duct components (030703) - avoiding double counting
The round-to-rectangular transition (rectangular-to-round reducer) is a duct "fitting", not a "component": per GB/T 50856-2024 Annex G table G.2.1 (duct fabrication and installation, code 030702), note 1, duct length follows the design-shown centreline (mains and branches dividing at the centreline intersection), "including the lengths of elbows, tees, reducers, round-to-rectangular transitions and other fittings, but excluding the lengths occupied by components"; the transition's axial length merges into the connected duct's centreline length and its developed area into the duct's developed area, priced together under 030702 - neither a separate bill item nor a separate quota item; duct developed area deducts no inspection, measuring, supply or exhaust openings, excludes overlapping duct and mouth areas, and tapered runs compute on mean diameter (round) or mean girth (rectangular). Valves, diffusers, silencers and other components list separately per table G.3.1 (030703) - listing the transition as a component double counts.
- ←
Measurement boundaries and bill split of profiled-sheet composite floors (floor decking / rebar-truss decking): the steel sheet floor by horizontal projected area, the concrete above as solid slabs less the sheet volume
The profiled sheet / rebar-truss decking itself takes Annex F "steel sheet floors" (010605001) in m2 on the design-shown laid horizontal projection (no deduction for single columns, piers or holes of 0.3 m2 or less); the cast-in-place concrete above lists separately under Annex E "solid slabs" in m3, deducting the volume occupied by the sheeting and computing the concrete volume changes caused by the sheet profile; slab rebars take the Annex E rebar items in t; shear studs and high-strength bolts stay out of the steel member quantities and list under separate codes.
- ←
Quota application for tile-and-stone grout sealing on floors: the tiling items' work content ends at joint wiping and pointing, excluding grout sealing - it needs its own item; the grout item is chosen in three steps: dedicated item first, then a tile-finish table item carrying sealant consumption, else a supplementary quota or market rate build-up
The work content of tiling items ends at "joint wiping / pointing" (cement slurry or jointing compound fill) and excludes grout sealing; two-component sealants and epoxy coloured sand are separate workings needing separate items or description in the bill item descriptions. Choose the grout item in three steps: (1) where the region has a dedicated "grout sealing" item, apply it (e.g. Hunan 2024 (2025 edition in the source data) A11-200 tile grout sealing, m2); (2) else where the tile-finish table holds an item with sealant consumption, apply that (e.g. Beijing DB11/T 2382-2024 A-11-67: all-in labour Grade I 0.0240 workday/m2, two-component sealant 400 ml 0.1040 set/m2, other materials 1.5%, plant 2%, unit m2); (3) else compile a supplementary quota or build up from market labour and materials, confirmed by the employer / quota authority. Red lines: tiling items already contain wiping / pointing - never add a pointing item on top; never over-apply movement-joint caulking or curtain-wall silicone items.
- ←
Deciding quota pricing of combustible gas alarms across systems: the split between the industrial-instrument "safety monitoring device" (per set) and the fire "point-type detector" (per unit), the code basis and the unit difference
Pricing a combustible gas alarm is not "either-or, take the dearer" but a match on three gauges: (1) system attribution (which controller receives the alarm signal); (2) device make-up (a lone sensor head, or head plus alarm controller as a set); (3) the quota item's unit and work content. Signals into DCS / PLC used for process interlocks price under the automatic-control instrument "safety monitoring device - combustible gas alarm" per "set" (integral installation of head plus alarm, system test); signals into the fire alarm panel used only for warning and fire interlocks price as "point-type detector - combustible gas" per "unit" (head plus base, in-situ commissioning). The hardest basis is GB 50116-2013 clause 8.1.2: "the combustible gas detection and alarm system shall stand alone, and combustible gas detectors shall not connect into the detector loops of the fire alarm panel; where the gas alarm signal must enter the automatic fire alarm system, it shall be brought in through the combustible gas alarm controller." Writing one basis down (or up) into the other is mis-application / unsupported cross-system borrowing, refutable on the code.
- ←
Bill listing and quota application for installing water-treatment plant (plate-and-frame sludge dewatering machines / filter presses): the dividing line between general building services GB/T 50856 and municipal GB/T 50857, and the corresponding items of local municipal consumption standards
Plate-and-frame filter presses (plate-and-frame sludge dewatering machines) are "water-treatment plant": the bill must list them per GB/T 50857-2024 (quantity take-off standard for municipal works) Annex F water-treatment equipment (code 040602) per "unit" - GB/T 50856-2024 Annex C C.9.7 states "the installation of sewage treatment equipment and other water-treatment equipment shall be coded per the corresponding items of the current national standard GB/T 50857"; companion standard plant such as pumps, valves and instruments lists under GB/T 50856 (GB/T 50857-2024 F.3.2). Apply the equipment installation items of the municipal water-treatment volume (the specialist water-treatment items are not in the installation volumes): e.g. Beijing DB11/T 2382-2024 Annex D table D.5.29-4, items D5-2-228 (plates 810 x 810) / D5-2-229 (870 x 870); Shenzhen SJG 181.5-2024 Volume 5, 2.3.24; the Hunan 2024 municipal consumption standard, water-treatment equipment chapter, "sludge dewatering machine installation".
- ←
Deciding the quota items for pre-laid bond waterproof sheets: taking foundation sheet waterproofing under Beijing DB11/T 2382-2024 as the example, separating the "pre-laying method" items from the "torch-on method" items by construction process, with item work content, consumption and the companion measurement rules
Pre-laid bond (polymer self-adhesive film sheets) takes the "pre-laying method" items: Beijing DB11/T 2382-2024 foundation sheet waterproofing A-9-243 (HDPE self-adhesive film sheet, pre-laying, raft single layer, all-in labour Grade II 0.0630 workday/m2, HDPE film waterproof sheet 1.2 mm 1.3760 m2/m2) and A-9-244 (flat slab single layer, labour 0.0600 workday/m2, sheet 1.2510 m2/m2); the torch-on items must not be used. Basis: DB11/T 2382-2024 clause 4.10.8 "sheet waterproofing shall be itemised and determined by construction process"; the commentary to GB/T 51310-2018 clause 16.3.2 states plainly "cold-applied self-adhesive sheets must not be laid by the torch-on method".
- ←
Quota application and material attribution for stone-plastic composite (SPC) elevator door linings: classify by material into plastic decorative materials, take the finished door-and-window lining item with the main material swapped, or take the plastic decorative moulding and plastic decorative board finish items per the site detail
Stone-plastic composite (SPC - SPC boards, SPC mouldings) is a man-made composite finish material extruded from PVC resin and stone powder, belonging to the "plastic decorative materials" class - neither stone nor ceramic tile. It must not take the stone door-and-window lining items (e.g. Beijing DB11/T 2382-2024 Annex A table A.8.8, A-8-66 "door and window linings, stone", whose main material is locked to "finished stone 20 mm") nor the tile-finish items; the iron rule is "classify by the actual material, not by the stone-like pattern or the word 'stone' in the name". Current quotas carry no standalone "stone-plastic" item (absent in Beijing 2024, railway TB/T 10831-2024 Volume 10 and Hunan 2025) - a new-material gap: apply the item with "same process, similar material" and swap the main material (marking the conversion "converted"); where nothing is analogous, compile a supplementary unit-rate build-up schedule for approval. Finished SPC door linings take the "door and window linings" finished-set installation item (e.g. Beijing A-8-64, 0.0770 workday/m2 + finished timber door lining 1.000 m2/m2), swapping the finished timber lining for the finished SPC lining; moulding assembly takes the decorative moulding items (railway FY-1949 to FY-1957 plastic decorative mouldings); board adhesion takes the plastic decorative board finish items (Beijing A-12-176). Quantities by developed area at design-shown dimensions (Beijing 4.9.12; railway Volume 10 volume notes IX.7).
- ←
Sorting out the measurement of underfloor heating coils (floor radiant heating pipes): the bill measures the net area of heated rooms (m2), the quota measures the design-shown pipe length (m), and the boundary between heating pipes and manifolds
Bill (measurement) basis: GB/T 50856 Annex K table K.4.1 "heating appliances" (code 031004) measures floor radiant heating by net heated-room area in m2. Quota (consumption) basis: floor radiant heating pipe laying is computed by design-shown length in m (e.g. Beijing DB11/T 2382-2024 clause 6.10.76); the two are bridged by the net-area-to-pipe-length contents of table 6.10.76 (pipe OD 16 mm = 6.300, 20 mm = 5.775, in m per m2 of net area). The boundary with manifolds sits at the branch-pipe connections off the distributor: on the heating-pipe side, from the distributor outlet to the collector connection (including the riser from floor level to the connecting fitting); the heat-medium distribution and collection unit (manifold) is listed separately per "set".
- ←
Deciding how the pumping charge for ready-mixed concrete is applied: reading whether the published price information includes pumping, and the three mutually exclusive quota paths (a separate pumping item / convert materials by delivery method and apply the conveying item / included in the item, not charged again)
There is no national unified rule for pumping charges; two lines decide. (1) The publication notes of the current published price information - where issued as "ready-mixed concrete (pump type)" or marked as including pumping, it is included and never charged again; where issued by strength grade with a remark "pumping charge: truck pump +X, trailer (boom) pump +X yuan per m3", it is excluded and must be added. (2) The compilation basis of the quota item applied - "a separate concrete pumping item" (e.g. TB/T 10831-2024 Volume 10, FY-531 pump wagon 79.57 yuan per 10 m3, FY-532 stationary pump 107.25 yuan per 10 m3); "items exclude conveying - convert materials by delivery method and apply the conveying items of the chapter" (SJG 181.2-2024 Volume 2, clause 2.1.4); "items already include conveying, no further computation" (SJG 181.3-2024, SJG 181.4-2024 general rules). The three are mutually exclusive - one only; double charging is a high-frequency audit disallowance. Where no pumping item exists, charge by pumping plant machine-shifts (JTG/T 3833-2018 pump wagon 1781.5-2194.98 yuan per machine-shift, conveying pump 257.77-1241.61 yuan per machine-shift).
- ←
BOQ and quota item selection for compact package unit substations (prefabricated substations): the mainstream principle of billing the complete unit per set; splitting into transformer plus HV/LV panels only for non-package supply, missing quota bands or contract-required splits; with commissioning and handover-test interfaces and a Beijing / Shenzhen / railway / national-standard comparison
For package unit substations (compact / prefabricated substations) the principle is to bill the complete unit: apply one installation item per set by capacity band, the work content already covering positioning, wiring and checking, earthing and individual commissioning, with no split into transformer plus HV/LV panels; only non-package supply, missing quota bands or contract-required splits justify splitting, split and unsplit being mutually exclusive with strictly no double counting of included content. Beijing DB11/T 2382-2024 clause 6.4.19 (one container body counts as one unit), Shenzhen SJG 181.7-2024 (measured per set) and GB/T 50856-2024 (switchgear installation 030402 covers prefabricated substations; clause 3.0.11 - equipment installation includes commissioning of the equipment itself) are consistent; railway TB/T 10829-2024 splits installation (DY-1074 to DY-1084) and commissioning (DY-1407 to DY-1410) into two items per unit, likewise without splitting the body.
- ←
Applying static equipment and process metal structure fabrication/installation quotas: process-item determination of site-built tank shells and metal-weight measurement rules
Tank shells fabricated on site from delivered steel plate/section stock by cutting and welding (e.g., powder-silo shells) belong to installation works "static equipment and process metal structure fabrication and installation" — i.e., process items, not civil steel structures. Apply metal tank (storage tank) fabrication/installation or hopper/silo prefabrication/installation sub-items, measured in t (metal weight): computed from the geometric dimensions of the design nesting drawing / approved cutting and plating layout, including base plates, shell plates, roof plates, curb angles, and stiffening rings, without deducting hole areas; capacity by the nearest quota step.
- ←
Drainage-pipe testing caliber and pricing inclusion boundary: gravity pipes take leakage-tightness tests (water/air) not pressure tests/disinfection-flushing; tests are included in the pipe BOQ item, norm items listed separately != separate BOQ items, with a four-step omitted-item test for settlement
Drainage pipes are gravity pipes; their functional test is the leakage-tightness test (water test/air test) — there is no "pressure test" caliber and no water-supply disinfection-flushing: sewage, combined, and storm pipes in collapsible/expansive/quicksand soils must pass tightness tests before use (GB 50268-2008, 9.1.11, mandatory). At BOQ level the test is inside the pipe item (GB/T 50856-2024 Table K.1.1 note 9; GB/T 50857-2024 Annex E and 4.1.2 "shall not be split into separate items"); at norm level separate test items may price it (e.g., SJG 181.4-2024), but a separate norm item != a separate BOQ item. "Drainage-pipe disinfection-flushing/pressure test" in settlements is a wrong item — strike it.
- ←
Applying quota items to civil-defence duct airtight sleeves (airtight wall-penetrating spools with sealing flange rings) under the Beijing 2024 consumption quota standard: select Type I / III by the wall-penetration form, band by diameter within d300 / d600 / d1000, measured per "piece"; fabrication and installation of the sealing rib and the spool body are included in the item and not charged separately
Civil-defence duct airtight sleeves take the dedicated "pipes through airtight walls" tables: where a plain steel-plate duct is cast directly into the reinforced concrete wall, take Type I (C7-11-68/69/70, within d300/d600/d1000); where the duct is not cast in and a spool with a sealing flange ring is embedded, take Type III (C7-11-72/73/74), measured per "piece" (one per penetration); the sealing rib (sealing flange ring) and the spool body, both fabrication and installation, are already included in the item consumption (plate 2.6 mm to 3.2 mm is the spool body, 4.1 mm to 7 mm is the flange ring) - no separate sealing-rib / steel-piece item, and no duplicate charging of the main material.
- ←
Bill-of-quantities listing of railings, panels and handrails (GB/T 50854-2024 Annex Q table Q.3.1, code 011503) and mapping to the Beijing 2024 consumption standard quota items: glass panels, finished railings and cast-iron scroll railings, dual measurement by area and by length, and the rule that bend lengths enter the centreline length
Railing, panel and handrail decoration lists under GB/T 50854-2024 Annex Q table Q.3.1 (code 011503); material and post-cap differences go into the item description, not separate codes. Under Beijing DB11/T 2382-2024, railings (panels) are measured by area m2 at design-shown dimensions and handrails and accessibility railings by handrail centreline length m (bends included), with no addition for parts embedded in the structure; where railing / panel and handrail are installed as one unit, the railing / panel items execute and the handrail item does not. Item mapping: metal stair railings (panels) A-15-52 to A-15-61 mostly m2 (only A-15-60 accessibility railings by m), metal stair handrails A-15-62 to A-15-64 by m, hardwood handrails in the hardwood railing table A-15-67 to A-15-69 by m.
- ←
Beijing DB11/T 2382-2024 consumption standard: rules for determining whether pipe installation quota line items include pipe fittings - in the gas chapter only galvanized steel pipe (threaded joints) items include fittings and pipe clamps while fittings of other materials are billed separately; pipe items of the water supply/drainage and heating chapters include fitting installation
Under DB11/T 2382-2024 clauses 6.10.32/6.10.34: pipe line items for indoor water supply, drainage and heating "shall include the fitting installation content" (fitting material quantities taken as the design-shown quantities or per Table 6.10.32), so no separate fitting-installation item may be applied; for gas piping, only galvanized steel pipe (threaded joints) items include fittings and pipe clamps, while for other materials (welded steel pipe, PE pipe, steel-skeleton plastic composite pipe etc.) the fittings and clamps must follow the corresponding "fitting and pipe-clamp installation" items. Pipes are measured along the design-shown centreline length with no deduction for lengths occupied by fittings and valves (6.10.36); fittings are counted as the design-shown number of pieces (6.10.37) - in gas works "pipe (m)" and "fittings (piece)" are two independent billed items.
- ←
Route choice for pricing metal railings under quota standards: distinguishing factory-finished railings installed on site (decoration-works finished-railing items, by m2/m) from site fabrication and installation (steel-member items, by t) - covering Beijing DB11/T 2382-2024, the GB/T 50854-2024 bill-of-quantities position, and the railway TB/T 10831-2024 comparison
Metal railings first split into two routes by how the material arrives: where finished products are procured and only installed on site, apply the decoration-works finished-railing items (Beijing DB11/T 2382-2024 Annex A.15.3-1.1 metal stair railing (panel) table, A-15-52 to A-15-61, by m2/m, work content only "installation, fixing etc.", the main material being the finished railing); where material is cut, assembled and welded on site, apply the steel-member items (A.6.6 other steel members, A-6-35 steel guardrail, by t, main material "steel-pipe guardrail" 1.000 t/t entered as a semi-finished product). Bill-of-quantities position (GB/T 50854-2024): steel-member items are compiled on a semi-finished basis excluding fabrication - site fabrication is listed under the "fabrication of steel members" item code; metal products are compiled as finished products installed on site, excluding fabrication. Railway position (TB/T 10831-2024): steel-railing fabrication (FY-1975 to 1977, by angle steel / steel pipe / round and square steel) and installation (FY-1978) are separate, both by t; finished stainless-steel railings by 10 m (FY-1979 to 1981).
- ←
Sorting out the names SC conduit, welded steel pipe, galvanised steel pipe and hot-dip galvanised welded steel pipe (four dimensions: drawing designation, base-pipe process, corrosion protection, full standard name), the code requirements on galvanising (hot-dip mandatory, cold galvanising banned), and the general rule for quota attribution in installation works
The four names are not four parallel pipes. Welded steel pipe = the base-pipe process name (GB/T 3091-2008; steel strip rolled and welded, carrying water, sewage, gas, air, oil, heating steam and other low-pressure fluids). Galvanised steel pipe = welded steel pipe with a rust-proofing zinc coat on the wall (cold-galvanised versus hot-dip processes; cold-galvanised production of welded steel pipe is obsolete). Hot-dip galvanised steel pipe / hot-dip galvanised welded steel pipe = pipe whose inner and outer surfaces are treated by hot-dip galvanising (GB/T 50680-2012 clause 6.2.20). SC conduit = the habitual drawing designation for steel conduit in electrical construction documents (not a standard name). GB 50261-2017 clause 3.2.2 requires galvanised steel pipe to be hot-dip galvanised inside and out; cold-galvanised pipe is not allowed; CJJ 127-2009 clause 3.2.4 likewise requires welded and seamless steel pipes for building drainage to be hot-dip galvanised inside and out, with cold-galvanised steel pipe banned. Three keys to quota attribution: fix the discipline first, then whether galvanised, finally the laying / jointing method; laying of galvanised electrical conduit (galvanised steel conduit) takes the "galvanised steel pipe laying" items, and KBG conduit takes the JDG items (SJG 111.3-2022, conduit works notes).
- ←
Scenario split for applying quota line items to PE-ERT pipes under Beijing DB11/T 2382-2024: assignment between floor radiant heating pipes (C10-7-41 to 43) and plastic water supply pipes (C10-2 / C10-1 series), with a comparison against PP-R and PE-X
Under Beijing DB11/T 2382-2024, PE-ERT pipes are priced by use scenario. Floor radiant heating pipes take C10-7-41 to 43 (pipe OD within 16/20/25 mm, unit m, under the heating-appliances items); the stated work content already covers "pipes of polyethylene and similar materials", so the items apply directly without material conversion. For plastic water supply pipes (fusion jointed), indoor takes C10-2-77 to 87, buried / in-wall takes C10-2-89 to 92, and outdoor takes C10-1-43 to 52. The floor-heating and water-supply line item families must never be cross-applied (the table note states expressly that buried laying "is not applicable to floor heating"); PP-R and PE-ERT share the same tables and items (main material converted per the design type), while PE-X cannot be fusion jointed and must not directly take the fusion-connection items.
- ←
Building automation system (BAS) / HVAC automatic control - BOQ item setting and appendix attribution under GB/T 50856-2024 Appendix E (code 030503)
HVAC automatic control / building automation (BAS) corresponds to the "building automation system" (code 030503) in GB/T 50856-2024 and is listed under Appendix E Building Intelligentization Engineering; items are set per Table E.3.1 (communication network control equipment 030503001, controllers 030503002, etc.; the unit of measurement is "unit (set)" and quantities are calculated as the numbers shown on the design drawings). Civil building automation systems apply Appendix E, while industrial automation systems shall be itemized under Appendix F Automation Control Instrument Installation Engineering; conduit, raceways, cable trays, junction boxes and electrical equipment associated with the intelligentization works shall be itemized under Appendix D Electrical Equipment Installation Engineering and must not be double-counted in the intelligentization BOQ.
- ←
Whether one work content can apply multiple quota items: multi-sub-item rate build-up for BOQ items is allowed; duplicate application for the same process is prohibited
Determined in two layers: (1) one BOQ item applying multiple quota sub-items (pouring/formwork/rebar and other processes of different natures) is the normal practice of rate build-up — all-in unit rate = the sum of the sub-item amounts under the BOQ item divided by the BOQ quantity; (2) duplicate application for the same process or the same work content is prohibited — the quota work content is already complete, including all construction processes (preparation and finishing-up, on-site transport, small material handling, site cleaning, etc.), and applying separately for content already included is double counting; processes must not be split and separately listed. Judge by the nature of the process: processes of different natures may be applied separately; the same process only once.
- ←
Applying quota items to socket solvent-cement jointing of UPVC water and drainage pipes under Beijing DB11/T 2382-2024, and judging the fittings content: take the "(solvent cement)" series, never the fusion series; match indoor / outdoor tables and diameter bands; fittings take no separate installation item; material quantities per the design-shown numbers or the fittings reference tables
UPVC socket solvent-cement jointing takes the "(solvent cement)" series items (indoor water supply table C.10.15-1, indoor drainage table C.10.17-1, outdoor water supply table C.10.4-2, outdoor drainage table C.10.5-2) and must not take the "fusion connection" series; the pipe items' work content already includes fitting installation, fittings take no separate installation item, and fitting material quantities are computed per the design-shown numbers or per the fittings reference tables 6.10.32 (indoor) / 6.10.23 (outdoor); pipe quantities are computed by length on the design-shown pipe centreline, without deducting the lengths fittings occupy.
- ←
Deciding the quota pricing attribution of substrate treatment in plastering works (spatterdash / bonding agent): contained in the plastering item, or taken as a separate item
Substrate treatment (bonding-agent application, spatterdash / cement-splash roughening) is listed separately from the plaster finish in current mainstream quotas. Decide by "three checks": (1) check whether the plastering item's work content already lists interface treatment (if listed, no separate charge); (2) check whether the quota carries a dedicated bonding-agent / substrate-treatment item (if so, apply it separately on the treated area in m2); (3) check whether the item's material column already contains the bonding agent (if contained, no separate charge). Beijing DB11/T 2382-2024 states expressly: general plastering sets items separately for substrate treatment, base coat and finish coat; the substrate treatment of decorative plastering and of tile and stone finishes follows the general plastering items, the finish being listed separately. Railway TB/T 10831-2024 Volume 10 general plastering work content excludes interface treatment, and bonding-agent details carry dedicated items (FY-1375 wall bonding agent, FY-1376 neat cement mortar bonding agent) applied when occurring. Note the double meaning of "spatterdash": railway FY-1370 / FY-1371 "decorative plastering spatterdash" contain red-earth powder and are finish-coat practices; substrate spatterdash / cement splash must take neat-cement-mortar bonding-agent items - never confuse the two.
- ←
Railway 2024 quotas: applying concrete mixing/transport items — HT-0 placing items exclude mixing, transport, and materials; use basic-quota Chapter 4, with haul as loading/unloading + per-1 km increments (TB/T 10821-2024)
Under the railway 2024 quotas, concrete cost is applied in four segments: the discipline volumes' "HT-0" placing items exclude mixing, transport, and concrete materials — apply TB/T 10821-2024 Chapter 4 (mixing YY-41~46, transport YY-47~57); the unit 10 m3 means the concrete volume in the works; transport is two-step "loading/unloading item + per-1 km increment item", increments split plains/hills vs mountains/in-tunnel, small vehicles per 50 m.
- ←
Quota item selection for trenchless horizontal directional drilling (directional drilling / pipe pulling): process split, diameter banding, measurement rules and multi-pipe single-bore diameter determination
Trenchless directional drilling corresponds to "horizontal directional drilling": there is no all-in item; the three processes - pilot boring, reaming and pipe pull-back - are set as separate items and banded separately (Beijing DB11/T 2382-2024 items D4-11-152 to D4-11-166: pilot boring in three bands, reaming and pipe pull-back in six bands each). Measurement: pilot boring and reaming by the horizontal length between the two working pits; pipe pull-back by the pilot-bore length plus 1.5m. Where several pipes are pulled into one bore, the bore, reaming and pull-back diameters are determined by the smallest circumscribed circle of the pipe bundle. "Within" includes the stated figure; "beyond" excludes it.