Applying quotas to copper wire in conduit: distinguishing "lighting" vs "power" wire-pulling sub-items (<=4 mm2 classified by use; Beijing 2024 C4-11-284/C4-11-288 compared)
Conduit wire-pulling sub-items are classified by use, not cross-section alone: wires <= 4 mm2 for lighting and similar uses (including ordinary 220 V socket circuits) take lighting sub-items; power uses or lighting circuits > 4 mm2 take power sub-items. 4 mm2 is the overlap tier between Beijing 2024's lighting table (C4-11-284) and power table (C4-11-288) — attribution follows use; Shenzhen SJG 181.7-2024 Clause 6.1.2 states expressly: lighting-circuit conductors >= 6 mm2 execute the corresponding power-circuit wire-pulling sub-items.
Applicable Codes
- DB11/T 2382-2024 建设工程施工消耗量标准(App. C Table C.4.94-1.1、Table C.4.94-1.2;正文6.4)
- SJG 181.7-2024 市政工程消耗量标准 Vol. 7 电力通道、通信管道及照明工程(第6.1.2条)
- https://zjw.beijing.gov.cn/bjjs/gcjs/jzjnyjcjg/tzgg/543399172/index.shtml
Topic Positioning
The classification rule between "lighting" and "power" wire-pulling sub-items in conduit-wiring pricing. Taking the 4 mm2 tier: in Beijing 2024 this section appears in both tables (overlap tier), so attribution depends on circuit use, not the section itself. For quota-classification disputes in electrical wiring pricing and review.
Core Conclusions
- Classification principle: by use, not section alone. The prevailing Q&A wording: "Wires <= 4 mm2 for lighting and similar uses take the lighting-wire quota; wires for power, or lighting circuits > 4 mm2, take the power-wire quota. Socket wiring above 4 mm2, whether power or lighting, uniformly takes power wiring... Socket wiring below 4 mm2 in ordinary housing takes lighting wire-pulling." (From an adopted expert answer on a cost platform — a practical consensus, not an official document.) In sum: <= 4 mm2 lighting and similar (including ordinary 220 V socket circuits) -> lighting; power use or lighting > 4 mm2 -> power.
- Beijing 2024 (DB11/T 2382-2024 Appendix C) table structure: lighting Table C.4.94-1.1 covers 1-4 mm2, the 4 mm2 sub-item C4-11-284 "copper wire in conduit, lighting circuits, section within 4 mm2"; power Table C.4.94-1.2 starts at 4 mm2 (to 240), sub-item C4-11-288. Unit m. Identical work content: "pulling fish tape, cleaning conduit, talc, paying out, pulling, marking, soldering/crimping lugs, etc." Consumption comparison at 4 mm2 (per m):
| Item | C4-11-284 lighting | C4-11-288 power |
|---|---|---|
| Composite labor class II | 0.0050 workdays | 0.0050 workdays |
| Insulated wire | 1.1600 m | 1.0500 m |
| Acetylene | 0.0013 kg | 0.0010 kg |
| Plastic tape 25 mm x 10 m | 0.0025 rolls | - |
| Self-adhesive tape 20 mm x 20 m | - | 0.0080 rolls |
| Black tape 20 mm x 20 m | 0.0013 rolls | 0.0040 rolls |
| Copper lug 185 | 0.0010 kg | 0.0010 kg |
| Other materials / tools | 3.0000% / 3.0000% | 3.0000% / 3.0000% |
- Local standard corroboration: SJG 181.7-2024 Clause 6.1.2: "Lighting-circuit conductors of section >= 6 mm2 execute the corresponding power-circuit wire-pulling sub-items." Conversely, < 6 mm2 (including 4 mm2) lighting circuits take lighting sub-items.
- Beijing 2024 text 6.4 (electrical equipment installation) has no explicit lighting/power split clause for wire pulling, only Clause 6.4.26 "distribution boxes/panels installed without distinguishing power and lighting". Mis-tabled costs differ little, but it is a "wrong application" in review — attributing by use is safest.
Applicable Boundaries
- Item 1 is a national practical consensus, not official; in settlement disputes support with circuit-use descriptions and the local cost station's interpretation.
- The "above/below 4 mm2" boundary is the source of such disputes; the mainstream reading includes 4 mm2 in the "<=4 lighting" tier.
- Workshop sockets, sockets feeding power equipment, and three-phase sockets are power; fire-alarm wiring is generally not power circuits.
- The consumption table maps only to the Beijing sub-items; other regions follow their own standards.
- This card is a pricing practice reference, not a substitute for the contract, drawings' circuit definitions, or the final review caliber.
Further Reading
- DB11/T 2382-2024 Appendix C: Tables C.4.94-1.1/1.2, sub-items C4-11-284, C4-11-288; text 6.4.
- SJG 181.7-2024 Clause 6.1.2.
- Q&A source: Glodon Service New GX answer "how to distinguish power and lighting wires in electrical wiring": https://www.fwxgx.com/questions/1268941
- Beijing Municipal Housing and Urban-Rural Development Commission notices (Beijing pricing basis verification): https://zjw.beijing.gov.cn/bjjs/gcjs/jzjnyjcjg/tzgg/543399172/index.shtml
Keywords
- 照明穿线
- 动力穿线
- 管内穿铜芯线
- 插座线定额
- 照明线路与动力线路划分
- C4-11-284
- C4-11-288
- DB11/T 2382-2024