Distinguishing the quantity calculation of cable trays (bridges), wireways, and conduits (GB/T 50856-2024 electrical installation measurement)
Cable trays (the collective term for ladder racks, trays, and channel boxes) carry cables, wireways carry insulated wires, conduits protect wiring; the bodies of all three are measured by length (m) per the design dimensions, without deducting the lengths occupied by intermediate junction boxes (outlet boxes), lamp boxes, switch boxes, socket boxes, or fittings — the boxes are counted separately by "count"; conduits add junction/pull boxes when exceeding 40 m without bends, 30 m with 1 bend, 20 m with 2 bends, or 10 m with 3 bends.
Applicable Codes
- GB/T 50856-2024 通用安装工程工程量计算标准
- GB/T 50857-2024 市政工程工程量计算标准
- GB 50311-2016 综合布线系统工程设计规范
- GB 50575-2010 1kV及以下配线工程施工与验收规范
- SJG 111.3-2022 城市地下综合管廊工程消耗量标准(Vol. 3)
Topic Positioning
Clarifying the conceptual distinction and BOQ measurement rules of the three electrical carriers — cable trays, wireways, and conduits (mainly per GB/T 50856-2024 Standard for Measurement of General Installation Works Quantities, with the municipal caliber consistent) — preventing mis-listing, missed boxes, and misapplied reservation rules.
Core Conclusions
- Concepts: the cable tray is the collective term for ladder racks, trays, and channel boxes (GB 50311-2016 terminology), mainly laying cables; the wireway is a channel specially designed for laying and fixing wires (GB 50575-2010 terminology), laying insulated wires; the conduit is a wire protection tube (galvanized steel pipe, JDG, KBG, flexible metal conduit, plastic pipe, etc.) for wire pulling. One-line mnemonic: trays carry cables, wireways carry wires, conduits protect pulled wires.
- Measurement: the bodies of all three are computed by length (m) per the design dimensions. For conduits (030412001) and wireways (030412002), the computed length does not deduct the portions occupied by junction boxes (outlet boxes), lamp boxes, switch boxes, socket boxes, or fittings along the route; the municipal caliber GB/T 50857-2024 H.8.10 and the utility tunnel caliber SJG 111.3-2022 Clause 2.2.11 are the same.
- Boxes counted separately: junction boxes, switch boxes, and socket boxes themselves are counted by "count" per the design quantities (switch and socket boxes are listed under the junction-box code) — length not deducted, quantity counted separately; miss neither end.
- Pull-box addition rules (for measurement when the design has no requirement): add junction/pull boxes when the pipe length without bends exceeds 40 m, with 1 bend exceeds 30 m, with 2 bends exceeds 20 m, with 3 bends exceeds 10 m; for vertical runs add when exceeding 30 m for conductor cross-sections <=50 mm2, 20 m for 70~95 mm2, 18 m for 120~240 mm2.
- Companion listings: chases and grooves needed for conduits are listed separately under Appendix N other and auxiliary works; supports and hangers are generally already in the installation work content (Clause 3.0.10), listed separately under Appendix N or M with special design requirements.
- Comparison reminder: cable quantity = laying length + reserved additional lengths (unlike tray length); wire in conduit = conduit length + entry/exit reservations at boards, cabinets, and panels (Table D.17.3-8).
Applicable Boundaries
Applies to general installation works measured per GB/T 50856-2024, and to municipal (GB/T 50857-2024) and utility tunnel (SJG 111.3-2022) works with consistent measurement calibers. For the specific values of cable reserved/additional lengths see the "cable laying reserved (additional) lengths" card; local consumption standards may differ in quota listing and work content — pricing follows the consumption standard of the project location.
Further Reading
GB/T 50856-2024 Appendix D Table D.12.1 (conduit and wireway listing) and the table's problem notes (pull-box rule item 4, junction-box listing items 5/8), Table D.9.1 (cable installation, tray listing), Clause 3.0.10 (support/hanger work content), Appendix N; GB/T 50857-2024 Appendix H Table H.8.10 (municipal conduits without box deduction); GB 50311-2016 terminology "cable tray"; GB 50575-2010 terminology "wireway".
Keywords
- 桥架
- 线槽
- 配管
- 配管配线
- 接线盒
- 拉线盒
- quantity take-off (measurement)
- 电气安装
- 电缆桥架
Related Cards
Cited By
- ←
Fixing the quota home of communication cables in low-current systems: separating control cables / multicore flexible cords / twisted-pair cables / telecom optic-electric cables by the product standard behind the type code, with laying items banded by 'method + section + cores', conversion factors, and the treatment of screened and armoured constructions
Fix the product identity first, then the item - never the system it serves or the signal it carries: KVV / KVVP / KVV22 / KVVR (GB/T 9330.2 plastic-insulated control cables) run the electrical 'control-cable laying' items, banded by method + single-core section + core count; RVV / RVVP (JB/T 8734.3 flexible cords) run the 'multicore flexible cord' wiring items (drawn into conduit / laid in trunking, trays and on brackets), screened cords on the same items with labour x 1.20, sheathed cords over eight cores in conduit reverting to control-cable items; twisted-pair and large-pair-count cables are structured cabling, on the intelligent-building 'twisted-pair / multipair' items; local telephone cables belong to the information-communication volume's 'optic (electric) cable laying'. Under DB11/T 2382-2024 clause 6.4.54, screening, armouring and flexible construction never open separate laying items (only cable terminations split armoured / unarmoured); compiled on three-core (three-core-with-earth) copper, five-core x 1.15, single-core x 0.67, aluminium or alloy x 0.67.
- ←
BOQ classification under GB/T 50856-2024 of power cable earthing, handover tests and insulation checking: termination earthing included in the termination installation itself, cables (wires) used as earth conductors billed under cable installation / conduits and wiring, stand-alone lightning protection and earthing installations under 030410, tests under 030416 (electrical adjustment and testing), with the billing scope of cable installation 030409 and the boundaries drawn by the D.17 problem notes
Earthing of the metal sheath, armour or screen at cable terminations (power cable terminations, cable joints, control cable terminations) is work content of the termination installation itself ('termination earthing') - no separate BOQ item and no separate earthing item; where cables or wires serve as earth conductors, bill under the relevant item codes of Appendix D.9 cable installation and Appendix D.12 conduits and wiring; stand-alone earth electrodes, earth bars, down conductors, grading rings, air-termination tapes (meshes), air-termination rods, equipotential bonding terminal boxes, earthing bonding jumpers and the like are billed separately under 030410 (table D.10.1). Power cable tests (including insulation resistance measurement and withstand voltage tests) and earthing installation commissioning go to table D.16.1 electrical adjustment and testing (code 030416); 'insulation checking' has no stand-alone code in the BOQ, and its test items and voltage application follow GB 50150-2016 clauses 17.0.1 and 17.0.2. Within cable installation (030409), cable trays / raceways, protective conduits for cables entering buildings, and cable branch boxes are billed instead under the relevant codes of Appendix D.12 and Appendix D.5.
- ←
Pricing clash-detour increments of MEP services: the attribution boundary of detailing versus variation, the valuation entries (8.9.1 / 8.9.2 and 2013's 9.3.1), the material and labour increments of cable-tray extended metres, bends and supports, and the separate claim channel for stoppage and the site-record anchors
Three gates before pricing a detour: (1) difference nature - contract versus actual drawings = variation; refinement within one drawing set is no variation; (2) attribution - the employer's design errors and base-data faults are employer risk; the contractor's routine detailing avoidance is contractor risk, generally unadjusted (T/ZBD 100.4-2023 clause 4.4.6) save contracts settling on the contractor's detailing drawings; (3) the entry - variations with quantity moves within 15% price on the five bands of 8.9.1, beyond 15% on 8.9.2 with purchase-discount adjustments. Quantity magnitude fixes 'how to price', never 'whether to pay'. Stoppage, waiting and idle losses claim separately under 8.11.9 / 8.11.10 - never merged into variation rates.
- ←
Calculation rules and values of reserved (additional) lengths in cable laying quantities
Cable quantity = the single-cable laying length shown on the design + various reserved (additional) lengths; where the design stipulates, follow the design, otherwise take the standard values: slack/bending/crossing add 2.5% (on the base of the drawn length plus the sum of reservations); terminations 0.5 m, joints 0.5 m, entry to distribution panels 1 m, power distribution boards 1.5 m, control panels 2 m, plant transformers 3 m, main transformers 5 m, etc. (GB 50217-2018 Appendix G); directly buried cables entering buildings may take 5% of the route length.
- ←
Separating conduit, trunking wiring and cable laying in the BOQ: GB/T 50856-2024 Annex D codes (030412/030409) against the 2013 old codes (030411/030408), a three-column comparison of object measured x unit x item description, the tests for splitting conduit and cable segments of one circuit, and the quota chapter mapping
Under the 2024 edition, 'electrical conduits and trunking' are itemised under 030412 (Table D.12.1) and 'cable laying' under 030409 (Table D.9.1); the 2013 old codes 030411 (conduit and wiring) and 030408 (cable installation) have been rearranged - 030411 is now overhead power distribution lines of 10kV and below and 030408 is trolley conductor rail installation - so retaining the old codes is a BOQ error. All three are measured in 'm' but on different bases: conduit by conduit length (no deduction for junction boxes, luminaire boxes, switch boxes, socket boxes and pull boxes along the run), wiring by single-wire length including reserves, and cable by single-cable length including reserved and additional lengths; the dividing criterion is the conductor form (insulated wires in conduit or trunking versus the cable itself), not the routing.
- ←
Cable-tray support and hanger mass calculation and norm charging: count positions by spacing, unit mass from section-steel theoretical mass; Beijing 2024 "tray installation includes support installation; support fabrication listed separately per kg"
Total support mass W = sum(single length x theoretical mass); round hanger rods w = 0.00617 x d2 (kg/m), flats/plates w = 0.00785 x b x t. Under Beijing 2024: tray installation items include "support/hanger installation" (do not re-charge) but exclude fabrication — support fabrication (cutting, welding, painting) is priced separately per kg under "metal support fabrication" (C4-13-1, C4-13-2), whose work content already includes painting — do not re-charge painting.
- ←
Re-decomposition and re-pricing of cost when a design variation moves wire-in-conduit wiring to cable-tray wiring: choosing the variation valuation clause (2013 edition clause 9.3.1 four tiers / 2024 edition clauses 8.9.1~8.9.3 five tiers); the deduction basis for the original conduit and wiring quantities; itemisation and measurement of tray, supports and hangers, and wiring; attribution of demolition of work already done and material write-off, and the rework confirmation procedure
Changing wires from conduit to cable tray is a change of 'item description + construction method': the original conduit rate does not apply to the tray (under the 2013 edition, clause 9.4.2 first re-determines the all-in unit rate on the description actually built, then the four tiers of clause 9.3.1 apply - the contract rate where an applicable item exists, an analogous rate by reference where a similar one exists, and where neither exists the contractor proposes a rate built from published price information and its tender float rate for employer confirmation, or from market-enquiry prices where the published information lacks the item); conduit and wiring quantities are recalculated from the variation instruction and the drawings as actually built and set against the original BOQ for deduction (conduit deducted by length, the length occupied by junction boxes not deducted); the added tray is measured by length (m); whether supports and hangers are listed separately depends on the consumption standard applied (DB11/T 2382-2024 includes support erection, fabrication of non-finished supports being listed separately; SJG 111.3-2022 expressly excludes support fabrication and erection); wiring is recalculated as single-wire length including reservations; demolition and material write-off for rework must rest on a rework confirmation sheet or site instruction record raised within the contractually agreed time - borne by the employer where the cause is not attributable to the contractor, and serving as the basis for rework pricing under chapter 8; raised late, the work is deemed to have caused no rework and is not measured.
- ←
Measurement boundaries and no-double-counting rules where several circuits share one cable tray and branch conduits run from the tray into the premises (GB/T 50856-2024 Annex D conduit and wiring 030412 + consumption-standard cross-check)
The tray itself is measured once along the design centre-line length (not multiplied by the number of circuits, no deduction for bends or tees); the wiring run inside the tray belongs to the tray alone; the outlet hole where it leaves the tray is the start point of the conduit and the outer edge of the box, cabinet or panel (the conduit mouth) is its end point, the reserve length into the box belonging to the cable or wire (tables D.17.3-8 / D.17.3-5); conduits are measured separately in metres per dedicated branch conduit, with no deduction for the lengths taken up by junction boxes, lamp boxes, switch boxes, socket boxes or connection cabinets. Codes must follow the 2024 edition: conduit 030412001, trunking 030412002 (table D.12.1, code 030412); the 2013 code 030411 (conduit and wiring) is withdrawn, and 030411 in the 2024 edition now denotes overhead power distribution lines of 10kV and below.
- ←
Conduit for electrical wiring (including rigid plastic conduit and trunking) crossing building movement joints requires a compensation device fixed at both ends: the code provisions, the two practices (flexible metal conduit / a junction box on each side), segmented measurement on both sides of the joint, and no deduction for the lengths boxes occupy
Where wiring conduits cross building movement joints (expansion, settlement or seismic joints) a compensation device fixed at both ends shall be installed (GB 50575-2010 Clause 3.0.6; GB 51348-2019 Clause 8.6.10; GB 50166-2019 Clause 3.2.3), with conductors fixed on both sides of the crossing and left with suitable slack. The detail may be a flexible metal conduit transition for surface-laid steel conduit (connected via a junction box or an adapter), or a junction box cast in on each side (the far box opened vertically in its base with a bore no smaller than twice the incoming conduit bore) plus a compensating bonding strap connected across. For measurement, the runs on the two sides are each taken to the face of that side's box and gathered as separate segments; the lengths the boxes occupy are not deducted, and the boxes are counted separately per the design drawings; whether the compensation device proper and the bonding strap are itemised separately is checked against the work content of the quota line items in the applicable consumption quota standard.
- ←
Quantity take-off of electrical conduit: GB/T 50856-2024 table D.12.1 (code 030412) measures by design-drawn length; the horizontal plus vertical segment method, attribution of reserved lengths, and listing rules for exposed versus concealed installation
Under GB/T 50856-2024, conduit and wiring form table D.12.1 with code 030412 (the 2013 edition's table D.11 / code 030411 is superseded; in the 2024 edition 030411 now designates overhead distribution lines of 10kV and below). Conduit is measured in m, calculated as length from the design drawings, without deducting the lengths occupied by junction boxes, luminaire boxes, switch boxes, socket boxes and wiring cabinets within the run. The quantity is L = sum of L_h,i + sum of L_v,j: horizontal segments follow the drawn path of the conduit centreline on the plan (not the straight-line distance between two points), and vertical segments are L_v = upper installation level minus lower installation level. This formula is a take-off decomposition method, not standard text; the reserved length for entering cabinets and panels belongs to the wiring (table D.17.3-8) and must not also be counted into the conduit itself, to avoid double counting.
- ←
Quantity take-off of cable tray and wireway body length: the segmented formula L = Sum(L_h) + Sum(L_v) for horizontal segments (L_h) and vertical segments (L_v), measurement against the dimensions shown on the design drawings, and the rule of no deduction for bends and tees (Beijing 2021 Consumption Standard, Volume 4, Chapter 11)
Cable trays and wireways are measured by length (extended metres, unit m) against the dimensions shown on the design drawings, without deducting the length occupied by bends and tees. Practice applies the segmented summation formula L = Sum(L_h) + Sum(L_v): horizontal segments are measured along the tray centreline path shown on the plan, vertical segments follow the level difference of the two ends L_v = |H_top - H_bottom| (both ends taken from the same datum); different materials or sizes are accumulated separately, and path increments caused by MEP coordination detours do not adjust the quantity.
- ←
BOQ rules for measuring cable trays and raceways by the metre, and the pricing boundary of fittings such as elbows and tees (no separate BOQ itemisation, the installation cost of fittings included in the tray installation quota line item, fire stopping measured separately)
Cable trays and raceways are invariably measured in length 'm' as shown on the design drawings, not by 'piece/unit'; the lengths occupied by elbows, tees, crosses and reducers are not deducted (DB11/T 2382-2024 Clauses 6.4.106 and 6.4.111); at BOQ level they are not itemised separately, and at quota level the installation cost of the fittings is already included in the work content of the tray installation line item (e.g. Beijing line item C4-11-253, whose work content includes 'elbows, tees or crosses... support and hanger installation, earthing'), so no separate installation line item may be applied 'per piece'; fire stopping of holes where trays pass through fire compartment walls is measured separately under fire barrier board and similar items (Beijing C4-8-497, in m2) and is not included in tray installation.
- ←
Splitting the laying mode of fire low-current conduit (fire PA, fire telephone and fire door monitoring circuits of automatic fire alarm systems): by exposed / concealed wiring, not by the structural-embedding / decorative-stage construction phase - with the material constraints, measurement and quota item bases
The wire conduit of fire PA, fire telephone and fire door monitoring circuits is banded in pricing by the design laying mode, not by construction stage - quota items offer only exposed / concealed (including within suspended ceilings) bands; embedded-with-structure corresponds to concealed and decorative-stage exposed runs to exposed. Concealed means the conduit runs inside the structural layer of walls, floors, slabs or columns, enclosed by non-combustible structure with cover at least 30 mm (GB 50116-2013 Article 11.2.3 preferably not under 30 mm; GB 50166-2019 Article 3.2.2 not under 30 mm); exposed means on wall / ceiling surfaces, within ceilings or on supports with the pipe visible. Material constraints: concealed may use metal conduit, flexible (metal) electrical conduit or rigid plastic conduit of class B1 or better; exposed only metal conduit, flexible (metal) electrical conduit or closed metal trunking (no plastic) - so exposed runs take the metal-conduit exposed items. Measurement per GB/T 50856-2024 Appendix D Table D.12.1 (code 030412): conduit by drawn length in m, boxes per piece, chases under Appendix N.
- ←
Discipline attribution and quota application of split boxes (splitters): telecom cable split boxes, outdoor cable split boxes and CATV splitters / taps must not borrow items across volumes
The split box / splitter is not one single item: attribute by discipline first, never borrowing across volumes - telecom cable split boxes under railway TB/T 10826-2024 Volume 5 Telecommunications Works TY-256 to 259 (by G0D12 / G0D24 / G0D36 / G0D48 types, unit per piece); outdoor cable split boxes under Beijing DB11/T 2382-2024 Table G.3.27 (split by internal / external wall and pair-count bands, e.g. G3-5-27 internal wall up to 30 pairs, G3-5-29 external wall up to 100 pairs, unit per piece); CATV splitters / taps belong to intelligent building weak-current works, under Table C.5.59 line equipment C5-4-95 (subscriber taps and splitters up to 8 ways, unit per piece).
- ←
Luminaire classes and listing notes for the lighting installation bill (code 030413) of GB/T 50856-2024
Per GB/T 50856-2024 Annex D table D.13.1 (lighting installation, code 030413) notes: luminaires divide into ordinary lamps, decorative lamps, factory lamps, high-point (obstruction) lamps, medical lamps, neon, campus street lamps, landscape lamps and lighting switches; neon covers tubes, strips, transformers, controllers, relays, timers and control boxes - all components; mid-mast lamps mount on poles 19 m high or less, high-mast lamps on poles over 19 m; where measured in "m" the item description shall state the lamp width, in "m2" the lamp size.
- ←
Applying quotas to copper wire in conduit: distinguishing "lighting" vs "power" wire-pulling sub-items (<=4 mm2 classified by use; Beijing 2024 C4-11-284/C4-11-288 compared)
Conduit wire-pulling sub-items are classified by use, not cross-section alone: wires <= 4 mm2 for lighting and similar uses (including ordinary 220 V socket circuits) take lighting sub-items; power uses or lighting circuits > 4 mm2 take power sub-items. 4 mm2 is the overlap tier between Beijing 2024's lighting table (C4-11-284) and power table (C4-11-288) — attribution follows use; Shenzhen SJG 181.7-2024 Clause 6.1.2 states expressly: lighting-circuit conductors >= 6 mm2 execute the corresponding power-circuit wire-pulling sub-items.
- ←
JDG (KBG) thin-wall steel conduit items: clamps and couplers (straight-pipe joints) are included in the conduit-laying items and must not be applied separately (DB11/T 2382-2024 Table C.4.91-4)
Beijing DB11/T 2382-2024 Table C.4.91-4 "snap/clip-type thin-wall steel conduit" (JDG/KBG) items already include clamps and straight-pipe couplers: the work content lists "fitting clamps, jointing, fixing" and the materials column carries them by content (e.g., exposed DN15: couplers 0.1648 pcs/m, clamps 1.4420 pcs/m) — JDG/KBG conduit runs must not add clamp or coupler items, else double pricing; concealed items contain no clamps (not needed when embedded).
- ←
Quota sub-item application and BOQ itemizing basis for special switch panels (sound-light control / key-switch / sensor / residual-current protection) (Beijing DB11/T 2382-2024 sub-items + GB/T 50856-2024 BOQ rules)
The Beijing 2024 consumption standard sets dedicated sub-items for special switch panels (no need to borrow): sound-light control (time-delay energy-saving) applies C4-4-113 time-delay energy-saving concealed switch (0.052 work-days/unit); key-operated switch applies C4-4-115 (0.061 work-days/unit); sensor panels apply C4-4-117 (0.085 work-days/set); rail-mounted residual-current protective switches apply C4-4-48/49 "single-phase" and C4-4-50 "with fuse" (0.05/0.226/0.535 work-days/unit); main materials enter at actual prices. BOQ itemizing per GB/T 50856-2024: sound-light-control types fall under "lighting switches" (Table D.13.1 note 9), residual-current switches under "low-voltage electrical switches / residual-current protective switches" (Table D.5.1 note 1), smart-home panels under Table E.7.1 (code 030507).
- ←
Sorting out the measurement of underfloor heating coils (floor radiant heating pipes): the bill measures the net area of heated rooms (m2), the quota measures the design-shown pipe length (m), and the boundary between heating pipes and manifolds
Bill (measurement) basis: GB/T 50856 Annex K table K.4.1 "heating appliances" (code 031004) measures floor radiant heating by net heated-room area in m2. Quota (consumption) basis: floor radiant heating pipe laying is computed by design-shown length in m (e.g. Beijing DB11/T 2382-2024 clause 6.10.76); the two are bridged by the net-area-to-pipe-length contents of table 6.10.76 (pipe OD 16 mm = 6.300, 20 mm = 5.775, in m per m2 of net area). The boundary with manifolds sits at the branch-pipe connections off the distributor: on the heating-pipe side, from the distributor outlet to the collector connection (including the riser from floor level to the connecting fitting); the heat-medium distribution and collection unit (manifold) is listed separately per "set".
- ←
Quantity calculation for lightning-protection grounding devices and determination of the number of "groups": grounding electrodes counted by "piece", commissioning of independent grounding devices (up to 6 electrodes) counted by "group", grounding-grid testing counted by "system"
Fabrication and installation of grounding electrodes is counted by "piece" (2.5 m per electrode where the design does not specify); "group" appears only in electrical adjustment and testing: commissioning of an independent grounding device is counted by "group" (applicable ceiling of up to 6 grounding electrodes), and grounding-grid testing by "system". One independent grounding device = 1 group; the number of groups follows the number of "locations", not "total electrodes / 6"; where there are more than 6 electrodes or a grid has formed, count by "system" instead, and electrodes within the grid may not be counted again for testing.
- ←
Method of selecting wire-conduit (raceway) diameters: the 40% cross-sectional fill rule, the diameter formula, and companion provisions on circuit grouping / wire-count limits / long runs with bends / pulling cables
The total cross-sectional area of insulated wires in a conduit (including insulation/outer sheath) shall not exceed 40% of the internal cross-section of the conduit; hence the minimum internal diameter D >= 1.58 x d x sqrt(n) (d = actual outside diameter of one wire, n = number of wires), rounded up to a standard diameter; alternatively read directly from the "500 V plastic-insulated wire-conduit compatibility table" of DL/T 5390-2014 Appendix F (applicable to BV single-core wires). The total number of wires per conduit should not exceed 8; different circuits, different voltage levels, and AC vs DC lines shall not share one conduit (one circuit in one conduit); metal conduits carrying only 2 insulated wires are exempt from the 40% limit; for cables, check that the internal diameter is not less than 1.5 x the cable outside diameter (preferably one cable per conduit); for long runs or many bends, fit junction boxes or go one diameter size up.
- ←
Quantity take-off (measurement) follows design-drawn dimensions (measurement per drawings): general principle, rule exceptions, and final account linkage
Quantities are in principle calculated from design-drawn dimensions (measurement per drawings), not from actual site dimensions; only items where the method of measurement "provides otherwise" (e.g. earthwork by natural in-situ (undisturbed) volume, depth taken from surveyed elevation) and site instruction / variation record items not specified in the design (flowing sand and silt provisionally estimated, concealed works) are measured per actual conditions / site instruction / variation record. Parts constructed beyond design dimensions without variation or site instruction / variation record support are generally not measured in the final account.
- ←
Calculating fire-protection system commissioning fees: BOQ listing, measurement units, and point-count rules (GB/T 50856-2024 Appendix J, code 030909)
Fire-protection system commissioning fees are listed separately in the BOQ (GB/T 50856-2024 code 030909), not charged as a percentage of the works cost, but measured by system/point/count with commissioning items: water extinguishing control devices by points from flow indicators/hydrant pump-start buttons/monitor counts, gas extinguishing by cylinder-valve count as points, automatic alarm and other systems by device counts as points and measured by "system", fire barrier control devices by count (valves) or unit (fire lifts); when applying quotas, price by the point-tier steps of the chosen quota — local standards differ in caliber.
- ←
Reserve rules for cables passing manholes and reserve (surplus) lengths for power / railway signal / urban rail signal / communication cables
Cables reserve at manholes: communication-duct manholes 1-2 m per end (max 3 m, GB 51158-2015 Clause 7.3.6); urban rail signal: 2 m in cable manholes, 2 m per end for entry/exit and termination, 3 m per terminal (DB11/T 2382-2024 Table 10.4.1); railway signal: 2 m per end for duct exit and termination, 2 m per splice, bending factor >= 2% (TB 10007-2017 Clause 17.0.11). Reserve (additional) length is a component of cable-laying quantity, not loss; design provisions govern, otherwise the standard reserve tables apply (GB 50217-2018 Clause 5.1.17).
- ←
Difference between grounding electrodes and grounding busbars, and their BOQ listing, measurement, and pricing calibers (GB/T 50856-2024 lightning protection and grounding devices, Table D.10.1)
The grounding electrode is the current-dispersing element, measured by design quantity in "pieces (blocks, sets)"; the grounding busbar is the connecting conductor, measured in "m" by total design length plus reserve (additional) length — separate items with different units, not interchangeable in pricing. Additional lengths of busbars, down-conductors, and lightning networks per Table D.17.3-6; TB/T 10829-2024 (per 10 m) and SJG 181.7-2024 (per linear meter) both add 3.9% to design length (turns, undulations, obstacle avoidance, splices).
- ←
JDG conduit (sleeved set-screw galvanised steel conduit): its definition, the "thin-wall 2 mm or less" boundary, the twist-off set-screw jointing process, the bonding-jumper practice, permitted and prohibited locations, and the distinction from KBG conduit and SC pipe
JDG conduit = sleeved set-screw steel conduit, a thin-wall galvanised steel conduit for running insulated conductors (with KBG conduit a fellow thin-wall steel conduit, a lightweight substitute for thick-wall SC welded steel pipe). The commentary to GB 50303-2015 clause 12.1.2 defines "thin-wall steel conduit means steel conduit with wall thickness 2 mm or less; above 2 mm it is called thick-wall steel conduit"; the same clause (mandatory): "steel conduit must not be butt fusion welded; galvanised steel conduit, or steel conduit with wall thickness 2 mm or less, must not be sleeve fusion welded". JDG joints are tightened with the dedicated tool until the set screw shears off (twist-off), and with electrical compound at the interface may omit the bonding jumper; sleeved set-screw steel conduit must not be laid in equipment foundations and must not be used outdoors, in civil-defence works, damp environments or flammable and explosive locations.
- ←
Exposed vs concealed runs of fire-protection lines above ceilings: fire-electrical conduit wiring is treated as "exposed (surface)"; fire water pipes are "concealed" per plumbing terminology — two opposite calibers
Two tracks: (1) conduit wiring of fire-electrical circuits (fire alarm, linkage, fire power) above ceilings is treated as "exposed (surface)" — GB 50016-2014 (2018 edition) Clause 10.1.10, Item 1 expressly includes "laid in ceilings" in exposed runs, requiring metal conduit or enclosed metal raceways with fire-protection measures; concealed = in combustible-free structure with cover >=30 mm, which ceilings do not provide. (2) Fire water pipes (sprinkler, hydrant) are "concealed" per plumbing terminology — GB 50015-2019 Clause 2.1.22 defines concealment to include "installation hidden by building decoration", and Clause 3.6.13 allows mains and risers in ceilings; but this "concealed" is a visibility classification, and pipe-installation sub-items are generally set by material, joint, and diameter, not split exposed/concealed.
- ←
Prefabricated branch cables: definition, applicable scenarios, fire-service selection, and shaft-riser installation essentials (GB 51348-2019 / GB 50054-2011 / T/ASC 23-2021 / DB11/T 1832.17-2021)
Prefabricated branch cables (trade name "pre-branch cables") are finished power cables whose branch joints are machine-prefabricated by the manufacturer per design section and branch spacing — for indoor low-voltage tree-trunk distribution in high-rise, multi-story, and large public buildings; single-phase branch cables preferably <= 120m, three-phase <= 300m (GB 51348-2019, 8.8.1/8.8.2). Fire-service feeders <= 400A on tree-trunk supply shall use fire-resistant (pre-)branch cables (T/ASC 23-2021, 5.3.5). Riser installation: fix the trunk cable 300mm above and below each branch joint edge; single-core bend radius >= 20x OD, multicore >= 15x; single-core cables forbid ferromagnetic clamps and pipe clips (DB11/T 1832.17-2021, 11.4.6).
- ←
Sorting out the names SC conduit, welded steel pipe, galvanised steel pipe and hot-dip galvanised welded steel pipe (four dimensions: drawing designation, base-pipe process, corrosion protection, full standard name), the code requirements on galvanising (hot-dip mandatory, cold galvanising banned), and the general rule for quota attribution in installation works
The four names are not four parallel pipes. Welded steel pipe = the base-pipe process name (GB/T 3091-2008; steel strip rolled and welded, carrying water, sewage, gas, air, oil, heating steam and other low-pressure fluids). Galvanised steel pipe = welded steel pipe with a rust-proofing zinc coat on the wall (cold-galvanised versus hot-dip processes; cold-galvanised production of welded steel pipe is obsolete). Hot-dip galvanised steel pipe / hot-dip galvanised welded steel pipe = pipe whose inner and outer surfaces are treated by hot-dip galvanising (GB/T 50680-2012 clause 6.2.20). SC conduit = the habitual drawing designation for steel conduit in electrical construction documents (not a standard name). GB 50261-2017 clause 3.2.2 requires galvanised steel pipe to be hot-dip galvanised inside and out; cold-galvanised pipe is not allowed; CJJ 127-2009 clause 3.2.4 likewise requires welded and seamless steel pipes for building drainage to be hot-dip galvanised inside and out, with cold-galvanised steel pipe banned. Three keys to quota attribution: fix the discipline first, then whether galvanised, finally the laying / jointing method; laying of galvanised electrical conduit (galvanised steel conduit) takes the "galvanised steel pipe laying" items, and KBG conduit takes the JDG items (SJG 111.3-2022, conduit works notes).
- ←
Quantity-calculation rules and itemizing method for busways (low-voltage enclosed plug-in busway / common-enclosure busway): by centre-line length, supports included, accessories listed separately by count - distinct from strip busbars
Common-enclosure busway and low-voltage enclosed plug-in busway installation quantities are calculated by the centre-line length of the dimensions shown on the design (m); support installation is included in the installation consumptions and not listed separately; tap-off (plug-in) boxes, end (staring) boxes, copper-busbar expansion joints, supporting insulators etc. are listed separately by the design quantities, and flexible copper connections are calculated per "phase/unit". Strip busbars follow different rules: calculated by per-phase length (including reservations) - 0.30 m/end for busbar terminations and 0.50 m/end for terminations to branch lines or equipment. Basis: DB11/T 2382-2024 Clauses 6.4.21-6.4.24 and Table 6.4.23; the BOQ basis is GB/T 50856-2024 Appendix D, Table D.3.1 (code 030403).
- ←
Cable-tray support (bearing frame) quantity calculation: measured in kg, count by support/hanger spacing, unit mass by section-steel theoretical mass
Cable-tray supports are measured by design finished mass in kg and itemized separately (GB/T 50856-2024, 3.0.10; SJG 181.7-2024, SJG 111.4-2022); counts follow support spacing — 1.5-3m horizontal, <= 2m vertical, densified at bends/branches/panel entries/expansion joints (GB 50397-2007, GB 50606-2010, GB/T 51239-2017, DB11/T 1832.17/19, etc.); unit mass = sum(member net length x unit theoretical mass), unit mass (kg/m) = section area (mm2) x 0.00785; factory supports (incl. seismic) count per piece/set without mass conversion.
- ←
Building automation system (BAS) / HVAC automatic control - BOQ item setting and appendix attribution under GB/T 50856-2024 Appendix E (code 030503)
HVAC automatic control / building automation (BAS) corresponds to the "building automation system" (code 030503) in GB/T 50856-2024 and is listed under Appendix E Building Intelligentization Engineering; items are set per Table E.3.1 (communication network control equipment 030503001, controllers 030503002, etc.; the unit of measurement is "unit (set)" and quantities are calculated as the numbers shown on the design drawings). Civil building automation systems apply Appendix E, while industrial automation systems shall be itemized under Appendix F Automation Control Instrument Installation Engineering; conduit, raceways, cable trays, junction boxes and electrical equipment associated with the intelligentization works shall be itemized under Appendix D Electrical Equipment Installation Engineering and must not be double-counted in the intelligentization BOQ.
- ←
Wiring (wire-pulling) rules for automatic fire alarm systems: protective conduit selection, conductor voltage rating and burning performance (not below B2), installation combinations, and workmanship (GB 50116-2013, GB 55036-2022, GB 50166-2019)
Transmission circuits of automatic fire alarm systems shall be protected by metal conduit, flexible (metal) electrical tubing, rigid plastic conduit of Class B1 or above, or enclosed raceways; concealed runs shall be in non-combustible structural layers with cover preferably not less than 30 mm, and exposed runs shall use metal conduit/flexible (metal) electrical tubing or enclosed metal raceways (mineral-insulated non-combustible cables may run exposed directly). Power-supply and fire-linkage control circuits shall use fire-resistant copper conductors/cables with burning performance not below B2; alarm buses, fire emergency broadcast, and fire-telephone transmission circuits shall use copper conductors/cables not below B2 (GB 55036-2022 Clause 12.0.16); transmission circuits and supply/control circuits below 50 V shall have a voltage rating not below AC 300/500 V, and 220/380 V supply/control circuits not below AC 450/750 V (GB 50116-2013 Clause 11.1.1). The system shall be wired separately; circuits of different loops/voltage classes/AC-DC shall not share conduit or raceway compartment; in horizontal conduit runs, except the alarm bus, circuits of different fire compartments shall not enter the same conduit (GB 50166-2019 Clause 3.2.12, GB 50116-2013 Clause 11.2.6).
- ←
Number of wires from fan coil to the thermostat / three-speed switch: depends on the control scheme - thermostat + normally-closed motorized two-way valve most commonly 6 wires, plain three-speed switch 4-5 wires (wire composition, take-off essentials and code basis included)
The wire count from fan coil to switch has no fixed value; it depends on the control scheme: thermostat + normally-closed two-wire motorized two-way valve, the most common, takes 6 wires (live L, neutral N, high/medium/low speed control lines and one valve-control line, one each); a plain three-speed switch alone takes 4-5 wires; thermostat + three-wire valve takes 7 wires; four-pipe systems (cooling/heating dual valves) or networked types take 8-10 or more. Distribution box -> fan coil is the power circuit (commonly BV-3x2.5) and fan coil -> switch is the control circuit; the two conduit runs are measured separately; the construction drawings and the manufacturer's wiring diagram finally govern.
- ←
Concrete quantity calculation rules: cast-in-place and precast members measured by volume per design-drawn dimensions
Concrete quantities are calculated by volume (m3) per design-drawn dimensions: for cast-in-place members, the volumes of rebar, steel wire, iron parts, bolts, and reserved grouting ducts are not deducted, and for walls and slabs, holes with individual area <= 0.3 sqm are not deducted (> 0.3 sqm shall be deducted); precast members are measured by solid volume (excluding hollow parts), without deducting rebar, iron parts, or prestressing reserved ducts. Columns, beams, walls, slabs, foundations, and stairs each have interface-attribution and deduction rules; all specialty quota norms apply the same measurement basis.
- ←
The definition of galvanised electrical conduit (thin-wall galvanised steel conduit for electrical raceways), the thin-wall / thick-wall thickness boundary, the minimum wall thickness in dry indoor locations, and the ban on fusion welding of steel conduit (GB 50303-2015, GB 55024-2022, DB11/T 1832.17-2021)
Galvanised electrical conduit is thin-wall galvanised steel conduit for running insulated conductors in electrical raceways, distinct from the thick-wall galvanised steel pipe designated SC on drawings. The commentary to GB 50303-2015 clause 12.1.2 defines "thin-wall steel conduit means steel conduit with wall thickness less than or equal to 2 mm; above 2 mm it is called thick-wall steel conduit". GB 55024-2022 clause 6.2.1 requires, for metal conduit wiring in dry indoor locations, "a wall thickness not less than 1.5 mm". GB 50303-2015 clause 12.1.2 (mandatory): "steel conduit must not be butt fusion welded; galvanised steel conduit, or steel conduit with wall thickness 2 mm or less, must not be sleeve fusion welded" - only threaded, set-screw, compression-gland and similar mechanical connections.