Cable-tray support and hanger mass calculation and norm charging: count positions by spacing, unit mass from section-steel theoretical mass; Beijing 2024 "tray installation includes support installation; support fabrication listed separately per kg"
Total support mass W = sum(single length x theoretical mass); round hanger rods w = 0.00617 x d2 (kg/m), flats/plates w = 0.00785 x b x t. Under Beijing 2024: tray installation items include "support/hanger installation" (do not re-charge) but exclude fabrication — support fabrication (cutting, welding, painting) is priced separately per kg under "metal support fabrication" (C4-13-1, C4-13-2), whose work content already includes painting — do not re-charge painting.
Applicable Codes
- GB/T 50856-2024 通用安装工程工程量计算标准 第3.0.10条、App. N(N.2.3、N.2.4)、App. M
- DB11/T 2382-2024 建设工程施工消耗量标准 App. C Table C.4.93-1.2、Table C.4.117-1(C4-13-1、C4-13-2);第3.3.1、3.3.6、6.3.44条
- 京建发〔2021〕201号 北京市预算消耗量标准 通用安装第四册 电气设备安装工程(下册)第十三章 附属工程 第一节 铁构件(13-1、13-2)
- DB11/T 1832.19-2023 建筑工程施工工艺规程 第19部分:弱电系统工程 第3.4.4条
- GB 50397-2007 冶金电气设备工程安装验收规范 第16.2.1条
- SJG 111.4-2022 城市地下综合管廊工程消耗量标准(Vol. 4 入廊管线安装工程)第3.2.1条
- SJG 181.7-2024 市政工程消耗量标准 Vol. 7 电力通道、通信管道及照明工程
- GB/T 706-2016 热轧型钢(型钢单位长度理论重量表值)
Topic Positioning
The complete algorithm and charging caliber for cable-tray supports from "spacing layout -> positions -> mass -> norm items", answering "when does the norm include supports and when are they charged separately".
Core Conclusions
1. Layout to positions: where design is silent, supports are spaced 1.5-3.0m horizontally and <= 2m vertically, with fixing points 0.3-0.5m from branches/ends (GB 50303-2015, 11.2.3); support points within 500mm of box/panel entries, corners, bends, and both ends of expansion joints and the three ends of T-joints (DB11/T 1832.17-2021, 9.4.2). Do not just divide straight runs — add points at ends, branches, bends, and entries; fix "positions", then multiply by unit mass. 2. Mass calculation: W = sum(Li x wi), Li single length (m), wi theoretical mass (kg/m).
- Round rods/hangers: w = 0.00617 x d2 (d in mm); φ10 = 0.617 kg/m;
- Flats/plates: w = 0.00785 x b x t (b, t in mm);
- Angles/channels: from theoretical-mass tables or 0.00785 x section area.
- Example (30m run at 1.5m spacing incl. ends): positions = 30/1.5 + 1 = 21; L50x5 angle arm 0.8m x 3.770 = 3.016 kg; two φ10 rods 2 x 0.6m x 0.617 = 0.74 kg; 3.756 kg per position; total approx. 78.88 kg — priced per kg under the fabrication item. 3. Norm charging (Beijing DB11/T 2382-2024):
- Included, not relisted: tray installation items (C4-11 series, e.g., C4-11-253 steel tray) work content "assembling, installing, fixing, bends, tees/crosses, covers, dividers, accessories and support/hanger installation, earthing, etc." — support/hanger placement and fixing are included; no section-steel main material in the consumption.
- Charged separately: support fabrication is not in the tray items — per kg under Table C.4.117-1 "metal support fabrication/installation" (e.g., C4-13-1, C4-13-2), work "straightening, marking, cutting, drilling, assembling, welding, painting, embedding, etc.", section-steel main material in the fabrication item; painting already included — do not re-charge.
- General comparison: GB/T 50856-2024, 3.0.10 — equipment, pipe, and accessory installation items include support/hanger/foundation-channel fabrication, installation, and painting; where specially designed, itemize under Annex N or Annex M. Final charging follows the contracted basis (measurement standard or local consumption standard) item work contents.
Applicable Boundaries
- The norm conclusions target Beijing 2024; other provinces follow their current norms' work contents and rules (the "installation included / fabrication separate" split may differ — check item work contents first).
- Mass formulas and the example are generic: dimensions per drawings and approved technical documents; spacings are defaults where design is silent — design governs.
- Tray items include "support/hanger installation"; factory supports priced separately per the applicable basis — do not mix with site-fabrication calibers.
Further Reading
- DB11/T 2382-2024 Annex C: Table C.4.93-1.2 steel trays (C4-11-253 etc.), Table C.4.117-1 metal supports (C4-13-1/2).
- GB/T 50856-2024, 3.0.10, Annexes N and M.
- Layout: GB 50303-2015, 11.2.3; DB11/T 1832.17-2021, 9.4.2.
Keywords
- 支吊架
- 型钢理论重量
- 金属支架制作
- C4-13-1
- 制作损耗率
- 成品支架
- 桥架支架
- 悬臂式龙门式吊杆式