Engineering Knowledge Cards.
Confidence HighUpdated 2026-10-25

Content boundary between duct fabrication and installation line items and supports and hangers (hanging/supporting brackets), and preventing double counting: the BOQ layer 'items include supports and hangers' versus the quota layer 'volume preamble plus line-item work content', three parallel yardsticks (included / priced separately / composite duct as a complete set), the weight linkage to 100 kg support line items when priced separately, and no separate charge for stiffening

The test runs on two layers. At the BOQ layer, GB/T 50856-2024 Table G.2.1 note 6 (ventilation duct items include fabrication and installation of supports and hangers; where listed separately, itemise under Appendix N) and Clause 3.0.10. At the quota layer, the volume preamble plus the work-content column of the governing line item must be checked: railway TB/T 10831-2024 volume preamble 'the thin steel sheet and GRP ventilation duct fabrication and installation quotas include flanges, stiffening frames and hanging/supporting brackets, but exclude floor-standing frames spanning ducts (price floor-standing frames under the equipment support quota)'; Shenzhen SJG 111.3-2022 4.1.7-3 same yardstick; Beijing DB11/T 2382-2024 line item C7-2-87 work content includes making and installing hanging/supporting brackets - all fall under 'included', and supports and hangers must not be priced separately. Two further yardsticks exist: 'excluded, price support line items separately per design quantity (in kg / 100 kg)' and 'composite duct supports supplied with the complete product, installation only'. The same support or hanger may be charged once only; duct stiffening (beading / stiffening ribs / stiffening frames) is inside the fabrication line item and must not be charged again; floor-standing frames spanning ducts are the sole exception to the 'included' yardstick.

Applicable Codes

  • GB/T 50856-2024 通用安装工程工程量计算标准 App. G Table G.2.1(code 030702)说明1~6
  • GB/T 50856-2024 第3.0.10条
  • TB/T 10831-2024 铁路工程预算定额 Vol. 10 房屋工程 册说明十三(三)
  • DB11/T 2382-2024 建设工程施工消耗量标准 第6.7.24、6.7.26、6.7.31、6.7.32、6.7.37、6.7.40条
  • SJG 111.3-2022 城市地下综合管廊工程消耗量标准(Vol. 3 附属设施安装工程)第4.1.7条

Topic positioning

The pricing boundary between duct (thin steel sheet / stainless steel / composite) fabrication and installation line items and supports and hangers: how the BOQ measurement layer and the quota consumption layer are each determined, the linkage from separately priced supports to support line items in 100 kg units and the weight build-up, the negative conclusion that duct stiffening must not be charged again, and a 'content comparison' check table against double counting.

Core conclusions

I. BOQ measurement layer (GB/T 50856-2024)

  • Appendix G, Table G.2.1 fabrication and installation of ventilation ducts (code 030702), note 6: 'Ventilation duct items include the fabrication and installation of supports and hangers. Where the fabrication and installation of supports and hangers is to be listed separately, itemise under the corresponding item codes of Appendix N, other and auxiliary works, of this standard.'
  • Clause 3.0.10: 'The work content of the equipment, piping and fittings installation items of this standard includes the fabrication, installation and painting of supports, hangers and base channels; where special design requirements exist, itemise under the corresponding item codes of Appendix N, other and auxiliary works, or Appendix M, painting, anti-corrosion and thermal insulation works, of this standard.'
  • Boundary notes accompanying the same table: note 1 - the developed area of ducts deducts no area occupied by inspection openings, measuring holes, supply outlets or exhaust inlets; duct length follows the centreline shown on the design drawings (main and branch ducts divided at their centreline intersection), including the lengths of bends, tees, reducers and square-to-round fittings but excluding lengths occupied by duct components; the developed area excludes the overlap areas of ducts and pipe ends; tapered ducts are computed circular by mean diameter and rectangular by mean perimeter. Note 2: 'wall sleeves are computed by developed area and included in the ventilation duct quantities of the corresponding material and thickness'. Note 3: where the section steel used for clean-air ventilation ducts is required to be galvanised, the work content shall state galvanising of the section steel. Note 4: 'factory-made ducts are itemised under the corresponding ventilation duct item codes'. Note 5: 'stainless steel smoke-exhaust ducts are itemised under the corresponding stainless steel sheet ventilation duct codes'.

II. Quota consumption layer (the volume preamble plus the line-item work-content column of the volume applied must be checked volume by volume)

(1) Included yardstick (supported by original text; supports and hangers must not be priced under separate fabrication and installation line items):

  • TB/T 10831-2024 Railway Works Budget Quota Manual, Volume 10: Building Works, volume preamble, XIII (III) II.4: 'The thin steel sheet and GRP ventilation duct fabrication and installation quotas include bends, tees, reducers, square-to-round fittings, flanges, stiffening frames and hanging/supporting brackets, but exclude floor-standing frames spanning the ducts; floor-standing frames are priced under the equipment support quota.' Its galvanised thin steel sheet duct line items (FY-2677 to 2682 etc.) list the work content 'setting out, cutting, rolling, folding, seaming, grooving, making straight ducts, fittings, flanges and hanging/supporting brackets, drilling, riveting and welding, mounting flanges, fitting up, making bracket holes in walls, embedding, assembling, duct positioning, levelling and aligning, making and inserting gaskets, bolting and tightening' - fabrication and embedding of supports and hangers are inside the line item. The composite duct line items (FY-2695 to 2703) likewise include 'installation of fittings, flanges, stiffening frames and hanging/supporting brackets'.
  • SJG 111.3-2022 Clause 4.1.7 item 3: 'The thin steel sheet ventilation duct fabrication and installation line items include the fabrication and installation of bends, tees, reducers, square-to-round fittings and other fittings, flanges, stiffening frames and hanging/supporting brackets (the quantity ratio of flanges and stiffening frames to hanging/supporting brackets is taken as 7:3), but exclude floor-standing frames spanning the ducts; fabrication and installation of floor-standing frames spanning ducts follows the corresponding equipment support fabrication and installation line items of this chapter.' The same clause also provides: duct fabrication and installation excludes derusting and painting (thin steel sheet duct painting follows the corresponding line item, outer or inner face only x 1.20, both faces x 1.10, with flanges, stiffening frames and hanging/supporting brackets already inside these factors; where the design requires the duct unpainted but the flanges, stiffening frames and hanging/supporting brackets painted, follow the painting line items at their quantities; derusting, whatever the corrosion degree, follows the light-derusting line item at the first-coat painting quantity); tapered ducts for uniform supply take the circular mean diameter and rectangular mean perimeter by reference to the corresponding size line items, labour x 2.50; only flanged joints are listed, no adjustment for flange-less joints; duct sleeve fabrication and installation follows the duct line item of the corresponding material.
  • DB11/T 2382-2024 Beijing: Clause 6.7.26 'the consumption for ventilation duct support and hanger installation shall include the fitting of timber pads'; line item C7-2-87 (galvanised thin steel sheet common-flange rectangular duct fabrication and installation) work content includes 'beading... tie-rod internal stiffening... making hanging/supporting brackets' and 'installing... installing hanging/supporting brackets', and the material columns clearly contain section steel and expansion bolts (angle steel 63, round steel up to d10, galvanised expansion bolts M8/M10); Clause 6.7.31 'fabrication and installation of floor-standing frames spanning ducts shall comply with Clause 6.7.24 of this standard' (Clause 6.7.24: equipment support fabrication and installation quantities are distinguished by the weight of each support and computed per the design weight; fan hangers are computed by count by fan model; packing under equipment is computed by material per the design weight); Clause 6.7.37 seismic bracket installation quantities are computed by type per the design count; Clause 6.7.32 duct wall-sleeve installation is computed by the developed area of the sleeve and follows the corresponding duct fabrication and installation items, and duct end caps are computed by the cross-sectional area of the duct blocked.

(2) Excluded, priced under support line items separately per design quantity (in kg / 100 kg): some local standards and the nationwide installation quota system adopt 'duct fabrication and installation line items exclude supports and hangers; supports and hangers follow the support fabrication and installation line items, measured in kilograms'. This yardstick must rest on the original text of the volume preamble or the line-item work content of the volume actually applied; different volumes and disciplines must not borrow from or extrapolate to each other.

(3) Composite duct complete-set yardstick: DB11/T 2382-2024 Clause 6.7.40 'composite ventilation duct installation shall set items by duct inner diameter size; except mechanical magnesia composite ducts, the fittings, flanges and stiffening frames of other ducts are all taken as finished products'; the Beijing rail transit volume sets both 'installation (including supports and hangers)' and 'installation (excluding supports and hangers)' line items for double-sided colour-steel composite ducts (G7-1-60 / G7-1-66, both up to 1000 mm major side, measured in m2); one of the two is used, never both; where supports are supplied with the duct as a complete set, their value is already in the unpriced main-material rate and only installation is charged, with no further support fabrication line item.

(4) Exception for composite duct flanges: C7-4-3 (composite circular duct installation, flange-less) work content 'does not include the flanges connecting the duct to valves and components; flanges follow the equipment support fabrication and installation item up to 20 kg, with labour, material and plant consumption x 1.4' - a flange borrowing the equipment support line item with a factor is a targeted treatment at rate level, not equivalent to supports and hangers being priced separately as a whole.

III. Linkage to the '100 kg' quota unit when supports and hangers are priced separately

Under the separate yardstick, support line items are mostly per 100 kg (e.g. railway Volume 10 equipment support fabrication and installation FY-2675 up to 50 kg and FY-2676 over 50 kg, both in 100 kg units): quota quantity (100 kg) = total net weight of supports (kg) / 100; total net weight = net weight per piece x number of positions; net weight per piece is built up piece by piece from net length of members x unit theoretical mass of the section steel (flat steel / plate g = 0.00785 x b x t kg/m, round steel hanger rod g = 0.00617 x d x d kg/m, angle / channel steel per GB/T 706 table values or g = A x 0.00785). Holes and cut corners are not deducted; connecting auxiliaries such as bolts and welding rods are already in the line-item consumption and do not enter the measured weight. The number of positions is taken per the support spacing limits, rounded per segment, plus ends, bends, branches, independent supports and densified anti-sway bracket points.

IV. Negative conclusions (no separate charge)

  • Duct stiffening (beading / ribs, stiffening ribs, stiffening frames, tie-rod internal stiffening) is inside the duct fabrication line item: Beijing C7-2-87 work content contains 'beading' and 'tie-rod internal stiffening', and Shenzhen 4.1.7-3 lists 'stiffening frames' inside the line item together with the quantity ratio against flanges and hanging/supporting brackets. Hence no separate 'duct stiffening' line item may be set, nor stiffening-frame weight charged again.
  • Seaming (pipe-end) overlap area is not added: GB/T 50856-2024 Table G.2.1 note 1 excludes the overlap from the developed area; TB/T 10831-2024 volume preamble 'the seaming overlap is already included in the quota and is not added'.
  • Wall sleeves are not set up as separate line items: included in the duct quantities of the corresponding material by developed area (BOQ note 2, Beijing 6.7.32, Shenzhen 4.1.7-9).
  • Floor-standing frames spanning ducts are the sole exception to the 'included' yardstick, priced under equipment support line items (in kg / 100 kg), counting the floor-standing frame only and never re-counting the hanging/supporting brackets alongside.

V. Double-counting check table (content comparison: item-by-item comparison of volume preamble work content)

Three checks in order; any check showing 'included' bars a separate charge:

1 Check the line-item work-content column - do entries such as 'hanging/supporting brackets', 'brackets', 'making bracket holes in walls, embedding', 'making and installing hanging/supporting brackets' appear (railway FY-2677 yes, Beijing C7-2-87 yes). 2 Check the volume or chapter preamble - does it say 'includes... flanges, stiffening frames and hanging/supporting brackets' with the exception sentence 'excludes floor-standing frames spanning ducts' (railway and Shenzhen yes); where the preamble declares supports and hangers excluded and priced under support line items, follow it and keep the original-text basis. 3 Check the line-item material and plant columns - do they contain section steel (angle, round, flat steel) and expansion bolts, welding machines and the like used for fabrication (Beijing C7-2-73 clearly yes).

Two further cross checks: (1) whether the same system applies both 'duct installation (including supports and hangers)' and 'duct installation (excluding supports and hangers)' line items (Beijing rail volume G7-1-60 / G7-1-66); (2) whether the support line-item quantity (kg) matches the number of positions x net weight per piece computed per the code spacing; a system showing 'section-steel content inside the line item' and 'a whole-system support line item' together is double counting.

Applicable boundaries

  • The BOQ yardstick 'items include fabrication and installation of supports and hangers' does not mean the quota line-item content already includes them: the BOQ sets itemisation rules, the quota sets consumption scope; each must be checked separately and neither substitutes for the other.
  • When borrowing across volumes (railway quotas / local consumption standards / nationwide installation quotas), the inclusion test must use the borrowed volume's own preamble and work content; the yardstick of another volume is no defence; 'heard that ducts exclude supports' without checking that volume's text is no pricing basis.
  • Seismic supports and hangers are always listed separately as prefabricated supports, measured by set or count; the 'included' test of this card does not apply.
  • This card covers supports and hangers of HVAC ventilation ducts (thin steel sheet, stainless steel, composite); measurement and content yardsticks for pipe supports and cable-tray supports follow the corresponding discipline rules.
  • Duct painting, derusting and galvanising of section steel are independent contents outside the line items (Shenzhen 4.1.7, BOQ note 3), outside the 'supports included' scope, handled under the corresponding painting / anti-corrosion items or by noting galvanising of section steel.

Further reading

  • GB/T 50856-2024 'Quantity take-off standard for installation works', Appendix G ventilation and air conditioning works, Table G.2.1 (code 030702) notes 1 to 6; Clause 3.0.10; Appendix N other and auxiliary works (supports and others, 031301); Appendix M painting, anti-corrosion and thermal insulation works.
  • TB/T 10831-2024 'Railway Works Budget Quota Manual, Volume 10: Building Works', volume preamble XIII, quantity take-off rules (III) ventilation and air conditioning works; Chapter 1 civil works, Chapter 3 building services works, Section 3 ventilation and air conditioning works: I. installation of ventilation and air conditioning equipment and components (VIII) equipment support fabrication and installation (FY-2675, FY-2676); II. ventilation duct fabrication and installation (I) galvanised thin steel sheet ventilation duct fabrication and installation (FY-2677 to 2682), (III) composite rectangular duct fabrication and installation (FY-2695 to 2703).
  • DB11/T 2382-2024 'Consumption standard for construction works', Chapter 6.7: 6.7.24, 6.7.26, 6.7.29 to 6.7.32, 6.7.37, 6.7.40; Appendix C C7-2-87, C7-4-3; Appendix G G7-1-60, G7-1-66.
  • SJG 111.3-2022 'Consumption standard for urban utility tunnel works (Volume 3: installation of auxiliary facilities)', Clause 4.1.7 ventilation works description.

Keywords

  • 风管支吊架
  • 吊托支架
  • 风管制作安装子目
  • 重复计费
  • 跨风管落地支架
  • 设备支架制作安装
  • 加固框
  • 定额工作内容