Beijing DB11/T 2382-2024 consumption standard: pipe supports must be computed separately with dedicated items (C10-4-1/C10-4-2 per 100kg, factory-made seismic braces per pair, factory pipe clamps per piece, industrial pipe racks C8-14-1)

Beijing DB11/T 2382-2024 sets independent items for pipe-support fabrication and installation — budgets must compute and apply them separately: general racks C10-4-1 (fabrication) / C10-4-2 (installation) per 100kg; factory seismic braces C10-4-3/C10-4-4 per "pair" (side-longitudinal braces under the transverse item, labor x 1.05; main material includes anchors and undercut anchors); factory pipe clamps C10-4-5 per "piece"; industrial pipe racks C8-14-1 per 100kg (special-shaped racks x 1.3, stainless racks x 1.1). Wood-cushion and spring racks use the corresponding pipe-support fabrication/installation items, with anti-corrosion wood cushions and spring dampers as separately priced materials; outdoor above-ground shaped-steel supports use Annex C.3.

Applicable Codes

  • DB11/T 2382-2024 · Standard for Construction Consumption of Construction Works (Beijing) 第6.10节(6.10.20、6.10.29条)
  • DB11/T 2382-2024 App. C Table C.10.23-1 管道支架制作(C10-4-1、C10-4-2)
  • DB11/T 2382-2024 App. C Table C.10.23-3 成品抗震支架安装(C10-4-3、C10-4-4)
  • DB11/T 2382-2024 App. C Table C.8.83 管架制作安装(C8-14-1)
  • GB/T 50856-2024 · Standard for measurement of general mechanical, electrical, plumbing and fire services 第3.0.10条

Topic Positioning

When compiling construction consumption (budgets, bid ceilings, etc.) under Beijing DB11/T 2382-2024: whether pipe supports need separate computation, which items apply, and the coefficients and separately priced materials — for water/sewer/heating/gas works (Section 6.10) and industrial piping calibers.

Core Conclusions

Pipe supports must be computed and priced with dedicated support items; they are not by default included in pipe installation items. Per DB11/T 2382-2024:

1. General pipe racks (Table C.10.23-1 pipe support fabrication): C10-4-1 "fabrication, general rack", C10-4-2 "installation, general rack", both per 100kg, applied per computed support mass.

  • C10-4-1 work: in-plant hauling, lofting, cutting, straightening, hot-bending, drilling, beveling, welding, fabrication; 105.0000 kg shaped steel per 100kg; labor (class II) 4.27 workdays/100kg.
  • C10-4-2 work: measuring, positioning, setting expansion anchors, assembling, fixing the rack; labor 2.646 workdays/100kg.
  • Wood-cushion and spring racks use the corresponding fabrication/installation items; anti-corrosion wood cushions and spring dampers are separately priced materials.
  • Outdoor pipes on above-ground shaped-steel supports use the corresponding items of Annex C.3 static equipment and process metal structures.

2. Factory seismic braces (Table C.10.23-3): single-pipe transverse braces C10-4-3/C10-4-4 per "pair"; work: measuring, positioning, cutting, assembling, planting (embedding) bolts, installing, correcting, fixing; installation splits single-pipe transverse and portal transverse; side-longitudinal braces use the corresponding transverse items with labor x 1.05; the main material "seismic brace (incl. anchors)" includes anchors and undercut anchors.

3. Factory pipe clamps: C10-4-5 (DN <= 15mm) per "piece"; for all factory clamps and cradle seats; work: measuring, positioning, drilling, fixing clamps, sealing holes.

4. Industrial pipe racks (Table C.8.83, C8-14-1 general rack, 100kg): except wood-cushion and spring racks, all rack types use the general-rack item; wood-cushion racks already cover factory and self-made cushions; spring racks exclude spring dampers (materials priced separately); special-shaped racks welded from formed steel pipes take the general-rack item x 1.3; stainless racks x 1.1.

5. Section pointers (Section 6.10): outdoor pipes — "pipe support installation per 6.11.35-6.11.38" (6.10.20); indoor pipes — "indoor pipe support installation per 6.10.39-6.10.42" (6.10.29).

Applicable Boundaries

  • Applies to Beijing projects using DB11/T 2382-2024 for water/sewer/heating/gas and industrial piping; other regions follow local standards.
  • This is an item-application rule running parallel to BOQ itemization: ordinary pipe supports are already in the pipe installation BOQ work content (GB/T 50856-2024, 3.0.10) and normally not itemized separately — apply the fabrication/installation items separately in pricing, avoid double counting.
  • Seismic braces are factory items (materials incl. anchors and undercut anchors), quantities per the seismic layout drawings; wood cushions and spring dampers priced separately.
  • Item setup, consumptions, and coefficients per the current DB11/T 2382-2024 text.

Further Reading

  • DB11/T 2382-2024 Section 6.10 water/sewer/heating/gas: general rules 6.10.1-6.10.14, outdoor pipes 6.10.15-6.10.23, indoor from 6.10.24; support clauses 6.10.20, 6.10.29.
  • Annex C: Table C.10.23-1 (C10-4-1/2); Table C.10.23-3 (C10-4-3/4); clamp item C10-4-5 and larger sizes; Table C.8.83 (C8-14-1).
  • BOQ-layer comparison: GB/T 50856-2024, 3.0.10 and Annex N (code 031301).