Quota line item classification for factory-finished spiral welded steel pipe (large diameters DN800/DN1000): apply the low-pressure carbon steel plate-rolled pipe (spiral rolled pipe) installation item with the pipe as an unpriced principal material; do not apply the finished carbon steel pipe installation item, and do not add any pipe rolling fabrication item
Under Chapter 6.8 of DB11/T 2382-2024: low-pressure spiral rolled pipe installation shall follow the corresponding carbon steel plate-rolled pipe items (6.8.16), and the pipe is an unpriced principal material (shown in brackets under 6.8.13). When factory-finished spiral welded pipe arrives on site for direct installation, only the installation item applies; no pipe rolling fabrication item may be added (the chapter contains only 'pipe fittings fabrication' items 6.8.80-6.8.82, with no pipe-body fabrication item). Large diameters DN800/DN1000 exceed the size bands of the finished carbon steel pipe installation items; borrow the nearest band of the plate-rolled / spiral rolled pipe installation items at the same pressure class and connection type. Upgrading to higher-priced items and splitting fabrication from installation for double counting are both prohibited.
Applicable Codes
- DB11/T 2382-2024 · Standard for Construction Consumption of Construction Works (Beijing) 第 6.8 章 工业管道工程
- GB/T 50856-2024 · Standard for measurement of general mechanical, electrical, plumbing and fire services App. H 工业管道工程(Table H.1.1 低压管道,编码 030801)
- GB 50468-2008《焊管工艺设计规范》第 2.0.4、2.0.12、2.0.15 条、第 4.0.1 条
- GB 50901-2013《钢-混凝土组合结构施工规范》第 5.2.1 条
- DB 51/T 5051-2007《钢结构工程施工工艺规程》第 4.3.16 条及表 4.3.16
Topic Positioning
Resolves the quota line item classification of large-diameter factory-finished spiral welded steel pipe (e.g. DN800, DN1000) under consumption standards / quota pricing: whether to apply 'carbon steel plate-rolled pipe (spiral rolled pipe) installation' or 'finished carbon steel pipe installation', and whether a separate 'pipe rolling fabrication' item still applies once the finished pipe arrives on site. The core criterion is the pipe's ex-factory identity: a factory-finished pipe, or pipe rolled from steel plate on site or in a fabrication shop.
Core Conclusions
1. Identity and supply form of the three pipe types
- Welded pipe (GB 50468-2008, clause 2.0.4, original text): 'steel pipe bent into tubular form from steel plate or strip, with a longitudinal or spiral weld seam running the full length of the pipe body.'
- Spiral submerged-arc welded pipe (clause 2.0.12, original text): 'welded pipe having one spiral weld seam formed by the submerged-arc welding process along the pipe body.'
- Longitudinal-seam submerged-arc welded pipe (clause 2.0.15, original text): 'welded pipe having a longitudinal weld seam formed by the submerged-arc welding process along the pipe body.'
- Raw material form (GB 50468-2008, clause 4.0.1, original text): 'High-frequency longitudinal-seam welded pipe mills and spiral submerged-arc welded pipe mills should use coiled steel strip as raw material. Longitudinal-seam submerged-arc welded pipe mills should use single cut-to-length steel plates as raw material. Continuous-forming stainless steel welded pipe mills shall use coiled steel strip as raw material; single-piece forming stainless steel welded pipe mills should use single cut-to-length steel plates as raw material.'
- Manufacturing entity (GB 50901-2013, clause 5.2.1, item 3): 'spiral welded steel pipe shall be processed and manufactured by specialised production plants'; item 1 of the same clause: 'circular steel pipes may use straight-weld-seam or spiral-weld-seam steel pipe'; item 2, for rolling at normal temperature: 'the minimum rolling inner diameter shall be no less than 35 times the plate thickness for Q235, no less than 40 times for Q345, and no less than 45 times for Q390 or above'.
- Site / fabrication-shop rolling characteristics (DB 51/T 5051-2007, clause 4.3.16): longitudinal-seam pipe rolling may be done on three-roll or four-roll plate bending machines; 'in cold rolling the minimum pipe diameter is 1.1 to 1.2 times the top roll diameter; where plate thickness is no less than 1/40 of the inner diameter, hot rolling shall be used'; warm rolling heats to 500-600 C; inspection uses an arc template of chord length no less than 1500 mm or comparable to the pipe diameter, with the gap no greater than 2.0 mm; longitudinal welds must keep a minimum spacing of 100 mm, and cross welds are not allowed.
- One-line criterion: check whether the pipe body is already finished pipe when it leaves the factory. Spiral welded pipe is indeed bent and welded from plate or strip, but forming and welding happen on the pipe plant's units (a finished product arrives on site); pipe rolled into rounds from cut-to-length plate in a fabrication shop or on site and longitudinally welded is 'plate-rolled pipe (rolled)', not finished pipe.
2. Division of items (Chapter 6.8 Industrial Piping Works, DB11/T 2382-2024)
- 6.8.1: 'Construction consumption for industrial pipe installation shall be compiled on straight pipe runs and shall comprehensively cover hydraulic and pneumatic testing and similar content.' Installation items are compiled on straight runs and already include testing.
- 6.8.13: 'Consumption of principal materials such as pipe and fittings in industrial piping works shall be shown in brackets and shall not form the base of other material costs.' The pipe is an unpriced principal material.
- 6.8.16: 'Low-pressure spiral rolled pipe installation shall follow the corresponding low-pressure carbon steel plate-rolled pipe items.' Low-pressure installation of finished spiral rolled pipe (including finished spiral welded pipe) directly applies the low-pressure carbon steel plate-rolled pipe items.
- 6.8.21: quantities of medium-pressure pipe and square compensator installation follow 6.8.18 and 6.8.19 (medium pressure does not copy 6.8.16; the corresponding medium-pressure items apply).
- Chapter 6.8 contains only section XIV 'pipe fittings fabrication' (6.8.80-6.8.82) and no pipe-body fabrication item. 6.8.81, original text: 'Fabrication of various plate-rolled fittings shall be assumed to take place in structure (fabrication) plants; its construction consumption does not include horizontal transport of raw material (plate) and finished products, unrolling of coiled plate, sectional cutting, straightening and similar content; its welds are assumed to be tested by oil penetration, and single-piece pressure testing and non-destructive testing are not included.' 6.8.82: 'Fabrication quantities of fittings shall be distinguished by pressure, material and specification and calculated by the design-drawing quantities. Tees, equal or reducing, are calculated on the main diameter; reducers, concentric or eccentric, are calculated on the larger diameter.'
- Negative conclusion: where finished spiral welded pipe is installed directly on arrival, only the installation item applies (low pressure follows the low-pressure carbon steel plate-rolled pipe items per 6.8.16; medium pressure follows the medium-pressure spiral rolled pipe / medium-pressure pipe items), with the pipe taken in as unpriced principal material at the finished spiral welded pipe price; no further 'pipe rolling fabrication' or 'plate-rolled pipe fabrication' item may be applied - the current Beijing standard has no pipe fabrication item, fabrication cost is already inside the finished pipe price, and an extra item constitutes splitting the process into fabrication plus installation and double counting. The 'carbon steel plate-rolled pipe fabrication' items (fittings fabrication) themselves exclude plate, so they cannot stand in for pipe rolling either.
- Borrowing rule for large diameters: DN800 and DN1000 exceed the largest size band of the 'finished carbon steel pipe installation' items (DN600 band); this is a missing size band, and the nearest band of the plate-rolled / spiral rolled pipe installation items at the same pressure class and connection type is borrowed. Upgrading to higher-priced items is prohibited, as is splitting into 'fabrication + installation' for two-stage pricing; when borrowing, note the basis after the item and retain the conversion records.
3. Two pricing routes: finished-pipe principal material cost versus 'plate + rolling fabrication cost'
- Theoretical mass per metre (kg/m) = pi x (D - t) x t x 7.85/1000, where D is outside diameter and t is wall thickness (mm), steel density taken as 7.85 g/cm3.
- Route A (finished pipe delivered): principal material cost = theoretical mass per metre / 1000 x published price information for finished welded steel pipe (yuan/t) x the quota pipe consumption length. Example consumption in the plate-rolled pipe installation items: the DN800 band 10 m item contains 9.0898 m of finished carbon steel plate-rolled pipe (consumption coefficient 0.909), the DN1000 band 8.9958 m (coefficient 0.900).
- Route B (self-rolling from plate): plate cost = theoretical mass per metre x (1 + wastage rate, conventionally 5% in pricing practice) / 1000 x published price information for hot-rolled steel plate + rolling fabrication cost (fabrication shop charge or a supplementary unit-rate valuation).
- Route selection: a finished pipe with an ex-factory certificate and delivered to a spiral welded pipe standard takes Route A, with no separate rolling fabrication cost; rolling from cut-to-length plate on site or in a fabrication shop takes Route B, but as the current Beijing standard has no pipe fabrication item, a supplementary unit-rate build-up schedule must be compiled and submitted to the quota administration authority for approval, or the fabrication items of another province's industrial piping volume (e.g. Tianjin) may be borrowed; the two routes cannot be stacked.
4. Volume positioning and measurement basis
- Pressure classes (6.8.6): low pressure 0 < P no more than 1.60 MPa; medium pressure above 1.60 and no more than 10 MPa; high pressure above 10 and no more than 42 MPa; steam pipe at no less than 9 MPa and working temperature no less than 500 C is high pressure. Class is set by design pressure and must not be back-derived from diameter or wall thickness.
- Industrial and municipal boundary (6.8.5): water supply is bounded at the inlet water meter chamber (the chamber counts as municipal); drainage at the first sewage manhole outside the plant wall (the manhole counts as municipal); steam and gas at the first metering device at the inlet or the connecting valve in the valve chamber (metering device, valve chamber and valve count as municipal).
- Civil medium transport piping follows the corresponding items of water supply and drainage, heating and gas works (6.8.2).
- Pipe installation quantities (6.8.18): calculated by length along the pipe centre line shown on the design drawings, without deducting the lengths of fittings and valves; at bends the quantity runs to the centre-line intersection of the two crossing pipes; buried outdoor pipe does not deduct lengths occupied by ancillary structures. 6.8.19: square compensators enter the pipe installation quantity by their occupied length.
- On the BOQ side this maps to Annex H Industrial Piping Works of GB/T 50856-2024 (Table H.1.1 low-pressure pipe, code 030801), with item description covering material, specification and connection form.
Applicability Boundaries
- The basis is Chapter 6.8 of the Beijing Construction Works Consumption Standard DB11/T 2382-2024; projects in other jurisdictions (e.g. Tianjin under Volume 6 Industrial Piping Works of the installation works budget pricing base) must verify items and coefficients against the local volume notes; the criterion logic (finished pipe attracts installation only, fabrication is not double counted) is universal, but item numbers and consumption quantities are not.
- 6.8.16 targets low-pressure spiral rolled pipe only; medium- and high-pressure pipe must not cite 6.8.16 and follows the corresponding items of 6.8.20-6.8.23.
- Where the size falls inside the bands covered by the finished carbon steel pipe installation items (small diameters, up to the DN600 band), finished welded pipe is priced under those items; borrowing plate-rolled / spiral rolled pipe installation items happens only for missing large-diameter bands.
- Not applicable to civil water supply and drainage, heating and gas piping (Chapter 6.10) or municipal pipe (the part split off by the 6.8.5 boundary).
- Fittings fabrication (6.8.80-6.8.82) is fitting processing; it can neither substitute for pipe rolling nor ground a claim for 'pipe fabrication cost'.
- The pipe's identity is judged from design documents, the supply contract and ex-factory technical records; a 'spiral weld seam' appearance alone is no ground for applying a fabrication item.
Further Reading
- Chapter 6.8 of DB11/T 2382-2024: I General Provisions (6.8.1-6.8.13), II Low-Pressure Pipe Installation (6.8.14-6.8.19), III Medium-Pressure Pipe Installation (6.8.20-6.8.21), IV High-Pressure Pipe Installation (6.8.22-6.8.23), XII/XIII Medium- and High-Pressure Flange Installation (6.8.72-6.8.79), XIV Pipe Fittings Fabrication (6.8.80-6.8.82), XV Pipe Supports and Other Items, Fabrication and Installation (6.8.83-6.8.88), XVI Weld Heat Treatment (6.8.89-6.8.91).
- Frequently used conversion coefficients in the same chapter: 6.8.8 work inside fully enclosed trenches, labour and plant consumption preferably x 1.15; 6.8.9 extra-low (high) carbon stainless pipe follows the stainless pipe items with labour and plant x 1.15; 6.8.12 super-height inefficiency coefficients 0.20 within 30 m, 0.50 within 50 m; 6.8.15 jacket pipe outer casing installation with labour consumption x 1.50, materials and plant x 1.20; 6.8.74 single-flange installation x 0.61 (bolt count unchanged), welded blind plate (head) follows the pipe fitting connection items x 0.60, medium-pressure threaded flange and medium-pressure slip-on flange follow the corresponding low-pressure items each x 1.20; 6.8.83 pipe support fabrication takes 65% and installation 35%, and where finished supports are used only installation is counted with the section-steel content deducted.
- Terminology and manufacturing basis: Chapter 2 terms (2.0.4, 2.0.12, 2.0.15) and clause 4.0.1 of GB 50468-2008, code for design of welded pipe process technology; clause 5.2.1 of GB 50901-2013, code for construction of steel and concrete composite structures (spiral welded steel pipe must be manufactured by specialised production plants; minimum rolling inner diameter limits); clause 4.3.16 and Table 4.3.16 of DB 51/T 5051-2007, specification for construction technology of steel structures (process flow and dimensional tolerances of longitudinal rolled pipe).
- BOQ itemisation: Annex H Industrial Piping Works of GB/T 50856-2024, standard for measurement of general installation works (Table H.1.1 low-pressure pipe, code 030801).