Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Decision path for selecting quota line items: item description matching -> direct application -> adjusted application -> similar construction process -> supplementary quota item submitted for approval

Applying a quota line item starts with matching "item description (work item specification) + work content": where fully consistent, apply directly (labour/material/machinery consumption taken from the line item, prices taken as market prices at the compilation date, on-costs per the matching norms for on-costs and expenses); where technical conditions differ greatly, apply with adjustment per the quota provisions; for missing items, preferentially refer to quota norms for similar construction processes (cross-industry/local allowed); where no reference exists, compile a supplementary quota item per the project's technical conditions and submit it to the quota administration agency for approval. Red lines: applying a higher-grade quota item and splitting processes for double counting are prohibited.

Applicable Codes

  • GB/T 50860-2024 构筑物工程工程量计算标准
  • GB/T 51095-2015 建设工程造价咨询规范
  • DL/T 5468-2013 输变电工程施工图预算编制导则
  • DL/T 5469-2013 输变电工程可行性研究投资估算编制导则

Topic Positioning

Which quota line item a construction item should apply: the decision path of "item description (work item specification) + work content" matching with step-down handling of missing items, applicable to rate build-up under both BOQ-based pricing and quota-based pricing.

Core Conclusions

Four steps in progression: ① Description first — the item description (work item specification) is an indispensable basis for determining the all-in unit rate and must be described accurately and completely; the appendix work content lists main content only, and auxiliary content such as machinery movement and material transport is deemed included; processes must not be split into separately listed BOQ items (GB/T 50860-2024 Clause 4.1.2). ② Description matches -> direct application: labour/material/machinery consumption taken from the line item, prices taken as market prices at the compilation date, on-costs charged per the matching norms for on-costs and expenses (GB/T 51095-2015 Clause 5.3.9). ③ Large differences in technical conditions -> adjusted application per the quota provisions, which requires a quota basis. ④ Missing item -> preferentially refer to quota norms for similar construction processes; where no reference exists, compile a supplementary quota item based on budget/settlement data of similar projects or the project's technical conditions, and submit it to the quota administration agency for approval before use (DL/T 5468-2013 Clause 4.1.4). Red lines: applying a higher-grade quota item (e.g., applying C30 where C25 is used) and splitting processes for double counting are prohibited.

Applicable Boundaries

Applies to rate build-up for divisional/sub-divisional works at the construction contracting stage. Line-item division and on-cost bases differ across industries; when referencing similar line items across industries, on-costs follow the industry basis of the quota applied; supplementary quota items are submitted for approval through the industry's channel. This card only answers "which line item to apply"; conversion and supplementary quota item compilation details are in the referenced cards.

Further Reading

GB/T 50860-2024 Clause 4.1.2; GB/T 51095-2015 Clauses 5.3.9, 5.3.12; DL/T 5468-2013 and DL/T 5469-2013 Clause 4.1.4.

Keywords

Cited By