The rate build-up path from quota line items to the all-in unit rate of a BOQ item and the cost calculation procedure: divisional work item cost as BOQ quantity x all-in rate, sum of quota line item amounts / BOQ item quantity (3 decimal places for quantities, 2 for rates), the three pricing methods, the analysis sheet identical to the BOQ rate, and the taxed versus tax-exclusive cost structures
The all-in unit rate of a BOQ item is converted as 'sum of quota line item amounts / BOQ item quantity' (item amounts at full precision with no rounding, BOQ quantities to 3 decimals, all-in rates to 2), and divisional work item cost = sum of (item quantity x all-in rate); the rates and prices in the all-in unit rate analysis sheet must exactly match those in the BOQ (GB/T 50500-2024 clause 3.1.7); pricing methods are unit-rate, lump-sum and percentage-rate, with divisional items and dayworks best priced at unit rates and preliminary items by lump sum or percentage; the taxed cost follows 'tax-exclusive cost of works = (divisional items + unit-rate preliminaries) + lump-sum preliminaries + other charges, and VAT = tax-exclusive cost x rate'; the scope of the all-in rate must be confirmed first - GB/T 50500-2024 clause 2.0.9 excludes VAT, while GB/T 51095-2015 clause 5.3.8 and article 5 of Ministry of Construction Order No. 107 are full-cost scopes including statutory levies and taxes.
Applicable Codes
- GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第 2.0.9、2.0.10、3.1.5、3.1.7 条
- GB/T 51095-2015 · Code for construction cost consultation 第 5.3.8、5.3.9 条及App. C
- GB/T 50875-2013 · Standard glossary of project costs 第 2.3.6 条
- 建设部令第 107 号《建筑工程施工发包与承包计价管理办法》第五条
- DBJ/T 15-145-2018《建设工程政府投资项目造价数据标准》第 6.1.4 条
- TB 10801-2024 · Measures for Compilation of Design Estimates and Budgets of Railway Capital Construction Projects Table 2.6.2
Topic positioning
Under BOQ-based pricing, a BOQ item gives only the quantity and the item description, with no labour, material and plant contents; the all-in unit rate must be derived by 'applying quota line items - converting - summing', then aggregated into divisional work item cost as 'BOQ quantity x all-in rate', and finally topped up with preliminaries, other charges and VAT to form the cost of works. This card gives the formulas along this bridging path, the decimal precision rules, the analysis-sheet consistency requirement and the taxed / tax-exclusive calculation procedures, and flags the scope differences of the all-in unit rate.
Core conclusions
1. One-way bridge: the BOQ is the pricing unit, the quota is the build-up tool
BOQ-based pricing and quota-based pricing are not mutually exclusive: GB/T 50875-2013 clause 2.3.6 states that the budget quota 'broadly reflects the labour, material and plant consumption and the corresponding costs of completing a sub-divisional work or structural member... and may also be used to compute all-in unit rates in BOQ-based pricing, being the basis of construction pricing at the tendering and contracting stage'. In build-up, quota line items supply the consumptions, prices are taken at market levels of the preparation period, and overheads, profit, statutory levies and taxes are computed per the companion on-cost norms (charging standards) (GB/T 51095-2015 clause 5.3.9), with the all-in unit rate analysis sheet compiled alongside.
2. The formula for the all-in unit rate of a BOQ item (conversion core)
The all-in unit rate of a BOQ item is P = T / Q, where T is the sum of the applied quota line item amounts (calculated at full precision, decimals unrounded), Q is the BOQ item quantity rounded to 3 decimals, and P is rounded to 2 decimals. That is, 'for a BOQ item priced through quotas, the all-in unit rate is set as the sum of the applied quota line item amounts divided by the BOQ item quantity' (DBJ/T 15-145-2018 clause 6.1.4, standardising this method at the data-standard level).
3. Aggregating divisional work item cost and the content of the all-in rate
GB/T 51095-2015 clause 5.3.8: the divisional work item cost of a building works budget is aggregated from each item's quantity times its all-in rate, item quantities being computed per the budget quota's work breakdown and its quantity take-off rules. GB/T 50500-2024 clause 2.0.9: the all-in unit rate is 'the cost of completing one unit quantity of a BOQ item, comprehensively allowing for technical standards, construction period, construction sequence, construction conditions, geography and climate, and risks within the agreed scope and band. The all-in rate of a BOQ item covers labour cost, material cost, plant and small tools cost, overheads, profit and risk costs within a defined range, excluding VAT.'
4. Choosing the pricing method (sets the build-up granularity)
GB/T 50500-2024 clauses 2.0.10 and 3.1.5: BOQ pricing has three methods - unit-rate pricing, lump-sum pricing and percentage-rate pricing; divisional work items and dayworks are best unit-rate priced, the bill of preliminaries by lump sum or percentage, provisional sums and provisional sums for nominated specialist subcontract works by lump sum, and main contractor's attendance and coordination provisions by percentage or lump sum. Items unsuited to unit-rate or lump-sum pricing may use percentage-rate pricing or other methods, with the pricing requirements and price adjustment rules stated in the tender and contract documents. Unit-rate pricing means 'pricing by multiplying the quantity by the all-in unit rate' (clause 2.0.10).
5. The analysis sheet must exactly match the BOQ (the review handle)
GB/T 50500-2024 clause 3.1.7: 'the all-in unit rate analysis sheet shall make clear the cost make-up and calculation method of each BOQ item's all-in rate and of per-item prices, and those rates and prices shall be exactly identical to the corresponding all-in rates and prices in the BOQ.' The analysis sheet is the internal build-up; the external price must be locked identical, and at review the quota contents, consumptions and material rates can be traced back directly.
6. Calculation procedures for taxed and tax-exclusive cost (unit-works summary level)
Local building and installation on-cost norms give this unit-works cost procedure: 1 divisional work items plus unit-rate preliminary items (sum) -> 2 lump-sum preliminary items (sum) -> 3 other charges (sum) -> 4 tax-exclusive cost of works = (1 + 2 + 3) -> 5 VAT = 4 x rate -> 6 taxed cost of works = 4 + 5; items 1 and 3 each list labour cost and plant and small tools cost separately, for percentage charges and price adjustment based on 'labour plus plant'. The quota pricing path shares the same lineage but prices adjustments differently: in TB 10801-2024 table 2.6.2, base-period labour, material and plant costs first form the quota direct cost of works, then price differentials from base period to preparation period (labour, material and plant) are added to give the direct cost of works, with preliminaries and on-costs computed as (base-period labour + base-period plant) x percentage rate.
Boundaries of application
- Confirm the scope first: the all-in rate of GB/T 50500-2024 clause 2.0.9 excludes VAT (VAT is a price-exclusive tax); GB/T 51095-2015 clause 5.3.8 instead reads 'the all-in rate shall include labour, material and plant costs, overheads, profit, statutory levies and taxes' (a full-cost scope); the 'all-in rate method' in article 5 of Ministry of Construction Order No. 107 is a fully loaded rate including direct costs, on-costs, profit and taxes. Scopes must be unified before comparing rates across standards or industries, or the build-up results are not comparable.
- The formula only fits BOQ items built up through quotas: P = T / Q is a unified algorithm in the data-statistics sense; where a BOQ item is priced directly from market price enquiries or the contractor's in-house norms (without applying quota line items), the formula does not apply.
- Decimal precision must not be mixed: item amounts at full precision unrounded, BOQ quantities to 3 decimals and all-in rates to 2; rounding before accumulating unbalances the items against the summary.
- Analysis-sheet consistency runs both ways: the sheet must match the BOQ rate, and whenever a variation or price adjustment revises a rate, the sheet must be revised in step - otherwise the final account review finds 'two sets of prices, on and off the sheet'.
- Tax and percentage rates shift with the policy of the preparation period: VAT rates and on-cost percentages are region- and period-specific data and must not be carried across periods.
Further reading
- GB/T 50500-2024 clause 2.0.9 (definition of the all-in unit rate), clause 2.0.10 (unit-rate pricing and the three pricing methods), clause 3.1.5 (choice of pricing method), clause 3.1.7 (all-in unit rate analysis sheet).
- GB/T 51095-2015 clause 5.3.8 (divisional work item cost and rate make-up), clause 5.3.9 (build-up principles) and Annex C (analysis sheet format).
- GB/T 50875-2013 clauses 2.3.2 to 2.3.9 (pricing quota system and the budget quota definition).
- Ministry of Construction Order No. 107, article 5 (labour-and-material rate method and all-in rate method).
- DBJ/T 15-145-2018 clause 6.1.4 (rate formula and decimal precision for BOQ items).
- TB 10801-2024 table 2.6.2 (element estimate and budget procedure for works, with price differentials and percentage bases) and table 2.6.3 (equipment element procedure).
Keywords
- all-in unit rate
- rate build-up
- quota line item
- 综合单价分析表
- 单价计价
- 不含税工程造价
- value added tax (VAT)
- 有效位数