Definition and cost composition of the all-in unit rate (GB/T 50500-2024 Clause 2.0.9, GB/T 50875-2013 Clause 2.2.58)
All-in unit rate = labour cost + material cost (including engineering equipment) + plant and small tools cost + overheads (company and site) + profit + risk cost within the agreed scope and range, required to complete one specified unit of measurement of a billed (BOQ) item; VAT is excluded (a price-exclusive tax). Basis: GB/T 50500-2024 Clause 2.0.9 and GB/T 50875-2013 Clause 2.2.58; building works BOQ-based pricing uses the "incomplete-cost" caliber excluding statutory levies and fees and taxes, while highways and other industries may use the fully loaded caliber including statutory levies and fees and taxes — confirm the applicable industry standard before citing.
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准 第2.0.9条
- GB/T 50875-2013 工程造价术语标准 第2.2.58条
Topic Positioning
The all-in unit rate is the core pricing unit of pricing on a bill of quantities basis. This card covers its standard definition, cost composition, and differences in industry caliber, applicable to tender pricing, contract valuation, interim payment, and settlement reconciliation.
Core Conclusions
Per GB/T 50500-2024, the China national pricing standard for BOQ (Clause 2.0.9), the all-in unit rate is the cost required to complete one unit quantity of a billed (BOQ) item, comprehensively considering influencing factors such as technical standards and codes, construction duration, construction sequence, construction conditions, geography and climate, plus risks within the agreed scope and range. Composition = labour cost + material cost (including engineering equipment) + plant and small tools cost + overheads (company and site) + profit + risk cost within the agreed scope and range; VAT is a price-exclusive tax and is not included in the all-in unit rate. GB/T 50875-2013, the Standard for construction cost terminology, Clause 2.2.58, uses the same caliber. Along the pricing chain: quantity x all-in unit rate = item price; tender pricing, interim payment, and settlement all take the all-in unit rate as the benchmark.
Applicable Boundaries
This is the BOQ-based pricing caliber for building and general installation works (an "incomplete-cost all-in unit rate"), excluding statutory levies and fees and taxes — the 2024 edition removed the separate statutory-levy item, with social insurance and housing fund measured by bidders and apportioned into the labour unit price and the overheads percentage rate. In highways and other industries the all-in unit rate may include permanent equipment procurement cost, preliminaries, statutory levies and fees, and taxes (a "fully loaded all-in rate"); confirm the industry/local standard's pricing caliber before citing, and never mix the two directly.
Further Reading
See GB/T 50500-2024 Clause 2.0.9 (all-in unit rate term), Clause 3.1.6 (fully inclusive price excluding VAT tender caliber), and Clause 3.2.11 (VAT listed separately and its taxable base); GB/T 50875-2013 Clause 2.2.58. Application of the all-in unit rate in adjustment of provisional prices after procurement, adjustment for cost fluctuation, and quantity deviation: 2024 edition Sections 8.4, 8.7, and 8.9.
Keywords
- all-in unit rate
- fully loaded all-in rate (incl. taxes and specified on-costs)
- All-in Unit Rate
- pricing on a bill of quantities basis
- rate build-up
- GB/T 50500-2024
- GB/T 50875-2013
Related Cards
- →
GB/T 50500-2024 rules for adjusting price differences, management fee, and tax after the actual price of provisionally priced materials/equipment is determined (Section 8.4)
Per GB/T 50500-2024 Section 8.4, once the actual price of provisionally priced materials (including engineering equipment) is determined, only the material provisional-price item in the all-in unit rate is adjusted (pre-tax difference = confirmed actual pre-tax unit price − provisional pre-tax unit price, times quantity); labor, machinery, management fee, profit and other costs are not adjusted; VAT is charged additionally on the difference and the contract price is adjusted. Replacement price: for items subject to mandatory tendering by law, the pre-tax winning purchase price replaces it; otherwise, the pre-tax inquiry/own-quote price confirmed by the employer. Specialist-work provisional prices are VAT-inclusive, replaced wholesale by the winning VAT-inclusive subcontract price — a different rule.
- →
Unbalanced bidding: definition, common tactics, risks for both employer and contractor, and response paths
Unbalanced bidding is a tender-pricing method that adjusts the unit prices of BOQ items after the total tender price is fixed in order to maximize returns ('total unchanged, unit prices mismatched'); it is lawful in itself. Common tactics: front-loading, quantity gaming, and high pricing of provisional items. The employer bears cash-flow occupation, settlement overruns and audit exposure; the contractor bears blowback from quantity misforecasting, locked-in all-in unit rates and compliance risks. The normative hedge: clear evaluation criteria in the tender documents plus organized adjustment at the bid-clarification stage (without changing the total price, confirmed by both parties).
- →
Contractor's objection period and tiered remedies against final account review results (GB/T 50500-2024)
After receiving the settlement verification/review result, the contractor must raise itemized written objections within the agreed objection period (28 days absent agreement), failing which the result is deemed accepted (GB/T 50500-2024 Clauses 10.3.8, 10.3.10); if dissatisfied, escalate through the ladder: recheck → incomplete settlement first for undisputed parts → negotiation/professional conferencing → dispute review/mediation → administrative mediation (within one month) → arbitration/litigation, while continuing performance during the dispute.
- →
Framework for distinguishing quantity risk from price risk in contracts: risk objects, responsible parties, and quantified trigger lines (GB/T 50500-2024)
Quantity risk governs "how much is built" (BOQ defects, quantity changes and item additions/deletions from changes); price risk governs "how much per unit" (input prices and all-in unit-rate levels). On allocation, Article 3.3.2 lists owner risks (unit-rate BOQ defects, erroneous source data, approved changes, legislative changes, beyond-band fluctuations); Article 3.3.3 lists contractor risks (preliminaries lists, total-price BOQ defects, own technical/management risks, within-band fluctuations). Quantified triggers: quantity change 15% (8.9.1/8.9.2); price fluctuation 5% or the contract-agreed band (8.7.2/8.7.6).
- →
Maximum bid price (former tender price ceiling) compilation framework and cost composition under GB/T 50500-2024
State-funded projects must set a maximum bid price (the former tender price ceiling), compiled and reviewed by the tenderer or a commissioned cost consultant, published in detail with the tender documents, and not to be raised or discounted; compilation basis: the seven items of GB/T 50500-2024, Clause 5.2.1. Cost composition: divisional and elemental work costs (pre-tax fully loaded all-in unit rate, including risk costs and auxiliary work costs) plus preliminaries (statutory safety provisions, non-competitive) plus other-item costs (provisional sums, provisional prices, dayworks, general contractor's service fee, etc.) plus taxes (VAT listed separately). Note the 2024 edition abolishes the separate line item for statutory fees, absorbing them into the all-in unit rate - different from the 2013 edition and some local documents; confirm the applicable edition before compiling.
Cited By
- ←
Units of measurement for installing fans, fan coil units and air handling units (all measured per unit, computed from the quantities shown on the design drawings), comparison of tiering parameters (model, equipment weight, air volume, installation method) across the standard systems, and the cost boundary between installation of the equipment itself and base grouting, supports and height-related inefficiency
Installation line items for the three equipment classes are all measured per unit from the design drawings, so the unit itself is not in dispute - the disputes are all about the tiering parameters. The fan tiering basis varies with the standard system: the civil-building ventilation and air-conditioning volume tiers by fan type/model + installation method (DB11/T 2382-2024 clause 6.1.37 states that 'fan installation for general industrial and civil building works shall follow the corresponding ventilation and air-conditioning items'); industrial fans go to the machinery installation volume and tier by equipment weight (clauses 6.1.33 and 6.1.39; direct-drive includes body + motor + base, non-direct-drive excludes the motor); the railway building works volume tiers by air volume (TB/T 10831-2024 FY-2635 to FY-2646) and the railway motive power and rolling stock volume by equipment weight (TB/T 10833-2024 JY-1174 to JY-1177); fan coil units tier by installation method (clause 6.7.11), with induction units and multi-split indoor units absorbed into the fan coil items (clause 6.7.7); combined air handling units tier by cooling capacity or air volume (clause 6.7.10), with fresh-air units absorbed into the combined AHU items (clause 6.7.8). Base concreting goes to the building and finishing works volume and secondary grouting to machinery installation (clause 6.7.1); supports and packing supplied with the equipment are included in its installation, site-fabricated supports by weight and fan hangers by model (clauses 6.7.5 and 6.7.24).
- ←
Constituent requirements of BOQ item descriptions and the three common defects (vague description / missing measurable parameters / disconnect from the work process), with corrected drafting (GB/T 50500-2024 clauses 2.0.5, 2.0.27, 4.1.7, 4.2.2, 4.2.4; GB/T 50854-2024 clause 4.1.2)
An item description, by definition (GB/T 50500-2024 clause 2.0.5), is 'a textual description stating the nature and requirements of the BOQ item itself ...'; a description written wrongly falls under clause 2.0.27, BOQ errors (including 'mismatched item description'), and enters the price-adjustment channel rather than mere textual polish. The hard yardstick of accurate description is GB/T 50854-2024 clause 4.1.2 - 'item descriptions must be given accurately and comprehensively ... sufficient to satisfy the need to determine the all-in unit rate' - and they must be 'prepared on the basis of the design documents and in combination with the completion and handover requirements' (GB/T 50500-2024 clause 4.2.2); any parameter whose variation would change labour, material and plant consumption or the basis of percentage charges must be stated, while decorative words that do not change the price are useless if stated.
- ←
Where statutory levies went after the 2024 BOQ pricing system dropped them as a separate line: social insurance and housing fund for production workers into labour cost; social insurance and housing fund for management staff and the works pollution charge (environmental protection tax) into overheads; urban maintenance and construction tax and surcharges likewise into overheads
The levies were not abolished but 'unbundled and no longer separately listed': GB/T 50500-2024 clause 3.1.2 makes the BOQ four parts - the works bill, the bill of preliminaries, the bill of provisional sums and other charges, and value added tax - leaving no slot for statutory levies at BOQ level; clause 3.1.6 requires the all-in unit rate and the item price to be 'fully inclusive pre-tax prices excluding VAT', which semantically absorbs the former levies into labour cost and overheads. The concrete destinations are fixed by the provincial expense norms: social insurance and housing fund for production workers (construction workers) go into labour cost; social insurance and housing fund for management staff and the works pollution charge (adjusted to the environmental protection tax under state provisions) go into overheads; urban maintenance and construction tax, education surcharge and local education surcharge also go into overheads.
- ←
Definition, BOQ item (011601002) and cost composition of vertical transport: the pricing vehicle for machine-shifts of large vertical handling plant and their attending labour; a preliminaries item priced as a lump sum per item and held fixed; and its boundary against the plant costs of work items (concrete pumping, extra height for concrete placing)
Vertical transport cost is the price of BOQ item 011601002 'vertical transport' in the preliminaries bill, covering only the machine-shifts of large vertical handling plant during construction (tower cranes, builder's hoists / external hoists, material hoists and the like) plus the plant-mounted and attending labour; vertical transport done with other lifting plant or manual aids is already included in the work content of the relevant work items and must not be charged again (GB/T 50854-2024 Appendix R.2.3; GB/T 50860-2024 Appendix C.2.3). The item work content covers mobilisation and demobilisation with erection and dismantling of the plant, fabrication and installation of anchorage devices and bases, laying and removal of tracks for travelling plant, and plant operation and use; pricing follows GB/T 50500-2024 clause 3.2.1, 'the preliminaries bill is preferably priced on a lump-sum basis', priced per item, with the composition entered per Appendix E schedule E.3.2 'composition detail analysis sheet for preliminaries items', held fixed under clause 3.3.7 and not re-measured or adjusted under clause 7.3.1 (save for variations, provisional-sum works not fully foreseen, employer causes and other statutory events).
- ←
Composition and attribution of inspection and testing costs: ordinary verification inside overheads (already in the all-in unit rate), third-party and works quality-acceptance testing listed by the employer under other construction costs, failed retests of certified materials borne by the supplier
Inspection and testing cost is an overheads component - the contractor's ordinary verification and checking of the works, materials, members and installations per the standards (including own-laboratory consumables), already inside the all-in unit rate's fee build-up, never charged again; it excludes tests on new structures and materials, destructive member tests and special examinations, and testing commissioned by the employer - those are listed by the employer under other construction costs; where testing of materials holding conformity certificates fails, the testing cost falls on the supplying (contracting) party, and on the employer when they pass.
- ←
Reading published price information as tax-inclusive or net, and the de-taxing conversion: de-tax by element (goods 13%, transport 9%, levy rate 3%), then custody, then into the all-in unit rate - with the order-bias test and double-tax prevention
Published prices are often tax-inclusive or freight-inclusive: read the release notes first. Tax-inclusive prices de-tax by each element's own rate (goods 13%, transport services 9%, simplified levy 3%) before purchasing and custody; a tax-inclusive delivered price divided once by 1.13 never adds freight or custody again. 'Add freight then divide the whole by 13%' differs algebraically from 'divide first, add later' only in form - both de-tax freight at 13%; the bias test is delta = F x (1/1.09 - 1/1.13) x (1+k). Net prices enter the all-in unit rate with VAT listed separately - one VAT only, throughout (GB/T 50500-2024 clauses 2.0.9, 3.1.6, 3.2.11).
- ←
Fee boundary for material price adjustment: the price difference carries VAT only, with no management fee or profit; the eight cost categories under Clause 8.7.6 are not adjusted (GB/T 50500-2024)
Per GB/T 50500-2024 Clause 3.3.5 item 4, price differences of labor, materials, and machinery fuel/power carry VAT only — no management fee or profit; Clause 8.7.6 lists eight categories not adjusted for price changes (construction consumables, small tool usage, preliminaries, other machinery usage beyond fuel/power, materials outside agreed adjustable items, changes beyond the agreed scope and band, management fee and profit, contractor's own-cause costs); Clause 8.7.3 opens a negotiation exception for abnormal, unforeseeable fluctuations.
- ←
Cost items expressly excluded from the all-in unit rate in BOQ-based pricing (VAT, statutory levies and fees, main contractor's attendance and coordination provisions, provisional sums, employer-borne costs, statutory safety provisions), the correct billing position of each, and audit identification of mixed allocation
Under GB/T 50500-2024 Clause 2.0.9 the all-in unit rate 'includes labour cost, material cost, plant and small tools cost, management cost, profit and risk costs within a defined range, and excludes VAT', and Clause 3.1.6 makes it a 'fully inclusive price excluding VAT'. Hence VAT (charged at the summary level under Clause 3.2.11), main contractor's attendance and coordination provisions (Clauses 2.0.17, 3.2.9 and 4.2.6, listed separately in the bill of provisional sums and other charges by item or by percentage rate), provisional sums (Clauses 2.0.13 and 8.3.1, at the employer's disposal and not owned by the contractor), the price of employer-supplied materials with their delivery and unloading charges and the material cost of the employer-borne permitted wastage (Clauses 3.2.4 and 6.2.4), and statutory safety provisions (Clause 3.2.5, non-competitive and separately listed in the bill of preliminaries) must not enter the all-in unit rate of work items; the 2024 edition cost composition no longer has a 'statutory levies and fees' heading (the five insurances and one housing fund for production workers now go into labour cost, and those for management staff plus the construction effluent fee go into overheads), so adding a separate statutory levies heading and charging it again is an error.
- ←
Labour cost pricing basis within the all-in unit rate: norm-based labour cost (base-period workday rate) versus current-period published labour price information and labour market prices, the applicable rules at the tender price ceiling and tender stages, and the test that the labour cost differential and the labour cost inside the all-in unit rate are not adjusted twice
Labour cost in the all-in unit rate = norm (budget) labour consumption x the current-period labour rate (published price information or a market price confirmed by the parties): consumption is locked to the quota manual while the rate is opened to the current-period market (GB/T 51095-2015, clause 5.3.9). The base-period workday rate published with the quota manuals is not itself the pricing input for BOQ rate build-up; it is a component of norm-based labour cost and the comparison base of the labour cost differential. At the tender price ceiling stage the published labour rates / published price information take precedence (GB/T 50500-2024, clauses 5.2.1 and 5.2.8); the tender is priced freely by the tenderer on its in-house norms and the market, but not below cost and not above the tender price ceiling (clauses 6.1.1, 6.1.3, 6.2.1). Differentials caused by changes in costs carry VAT only, not overheads or profit (clause 3.3.5); the same labour differential may be taken once only, in either the current-period-price pricing system or the base-period-price-plus-differential system, and must not be stacked on the labour cost already inside the all-in unit rate.
- ←
Attribution of quantity gaps between BOQ quantities and quota quantities, and the rate conversion: all-in unit rate P = Sum(Tn) / Q, four destinations of quantity gaps (into the BOQ quantity / into the rate / into quota consumption / into the risk allowance), and conversion points for typical work items
BOQ quantities and quota quantities must be kept on two separate tracks and never swapped: first attribute each quantity gap to one of four classes - content already built into the measurement rules (working space for earthworks) goes into the BOQ quantity; content listed under 'work content' but given no quantity (battering, shoring boards, base trimming and clearing) goes only into the ancillary-works cost or risk allowance inside the all-in unit rate; content carried by the quota through wastage rates or contents (material wastage, rebar wastage plus construction bars at 5%, permissible overbreak in rock works, 0.50m over-concreting of bored piles) goes into the numerator, the quota line-item totals; whatever neither the BOQ nor the quota provides can only go into the rate risk allowance. The conversion formula is P = Sum(Tn) / Q (P rounded to 2 decimal places, Tn kept at full precision without rounding, Q rounded to 3 decimal places). Quoting with quota quantities passed off as BOQ quantities is an explicit error: the dimensional bases differ, the all-in unit rate is understated (omission ratio = 1 - quota rate / all-in rate), and it blurs the parties' respective responsibilities for BOQ accuracy.
- ←
Choosing the format of the all-in unit rate analysis sheet, its mandatory preparation requirements, and its roles across tendering, settlement and audit (GB/T 50500-2024 Appendix E, tables E.2.2-1 and E.2.2-2)
GB/T 50500-2024 Appendix E provides that detailed all-in unit rate analysis shall follow table E.2.2-1 and simplified analysis table E.2.2-2, the choice being fixed by the tender requirements and the contract; the rates in the analysis sheet and the prices of lump-priced items must be 'completely consistent' with the corresponding figures in the BOQ (clause 3.1.7); at tender the sheet, together with tables E.3.2, E.3.3 (which must list initial set-up, mid-term operation and final dismantling costs) and E.3.4, must be submitted in full, consistent with the priced BOQ (clauses 6.2.12 and 6.2.13). The all-in unit rate carries risk costs within the agreed scope and bands and excludes VAT (clauses 2.0.9 and 3.2.2), so the risk allowance sits inside the rate build-up rather than as a stand-alone charge. At settlement, clause 3.1.6 requires item-by-item checking that rates match the priced BOQ in the contract, with no adjustment except for variations and agreed matters; dayworks and additional works may draw on 'the detailed price make-up in the all-in unit rate analysis sheet of similar BOQ items' (clause 8.6.3; cost expert assessment guideline clause 4.8.4); audit examines whether new rate build-ups follow the quota pricing rules agreed in the contract, whether every line-item price is fixed, and whether common material prices are reasonable.
- ←
Determining plant and small tools cost within the all-in unit rate: consumption × plant rate per machine-shift, 7-item/4-item composition of the plant rate per machine-shift, and adjustment for price differentials
Plant and small tools cost = construction machinery usage cost + construction instrument and meter usage cost, both determined as machine-shift consumption under quota norms (prescribed resource consumption standards) × plant rate per machine-shift (GB/T 51095-2015 Clause 5.3.9; TB 10801-2024 Section 3.3). The plant rate per machine-shift for construction machinery has 7 items = depreciation + overhaul + maintenance + assembly and disassembly + labour + power + other costs; the plant rate per machine-shift for instrument and meter has 4 items = depreciation + maintenance + verification + power; both are computed on an 8-hour working shift. Where machine-shift cost quota norms exist, take the price per the quota norms (railway TB/T 10814-2024, base-period price excluding deductible input value added tax (VAT)); the difference between base period and compilation period is listed as an adjustment for price differentials of plant and small tools cost. When fuel and power prices fluctuate beyond the agreed risk band (no-adjustment tolerance, e.g. ±5%; where not agreed, 5%), price adjustment (for fluctuation) applies; the price difference carries VAT only, with no management fee or profit (GB/T 50500-2024 Clauses 8.7.2, 3.3.5).
- ←
Comparative review of the all-in unit rate of one BOQ item under two construction methods: the three-identity sameness test, quantity-price separated line-by-line comparison sheets, attribution on unit output (machine-shift consumption), build-up compliance anchors, method-price consistency checks, and detection of unbalanced rates
First run the three-identity test (BOQ code + item description + unit of measurement) to confirm it is the same BOQ item; if not, price under the GB/T 50500-2024 clause 8.9.1 variation valuation rules. Then attribute the rate gap line by line, quantity separated from price, to consumption and price gaps in labour, materials and plant and to overhead and profit rate gaps; plant cost must be reduced to unit output (machine-shift rate x machine-shift consumption per unit of quantity), not compared on machine-shift rates alone, and machine models and shifts must also close against the plant allocation in the method. Compliance anchors: the analysis sheet fully consistent with the priced BOQ rate (clause 3.1.7), not below cost and not above the tender price ceiling (clause 6.1.3), deviation from the evaluation benchmark price (DB37/T 5161-2020 clause 5.3.4). The standards set no uniform deviation-percentage threshold; judging 'unreasonably low or high' and any magnitude threshold must be agreed in the tender documents and evaluation rules.
- ←
The relationship between the risk allowance inside the all-in unit rate and contractual price adjustment for fluctuation: within the band the risk allowance absorbs the movement, beyond the band only the excess is adjusted, and the two are never counted twice
The risk allowance and contractual price adjustment are a two-stage allocation of the same pricing risk against the risk band r agreed in the contract: within r, the movement is absorbed by the risk allowance implied in the all-in unit rate (not billed as a separate item, not repaid at settlement); when the movement exceeds r, the adjustment rules adjust only the excess. The exclusion of double counting runs both ways - GB 50500-2013 Clause 6.2.2 states that 'when the risk content and its scope (band) that arises falls within the range agreed in the contract, the contract price shall not be adjusted'; GB/T 50500-2024 Clause 3.3.5 states that the price differential adjustment 'shall carry VAT but shall not carry management fee or profit', and Clause 8.7.6 states that management fee and profit, preliminaries and other plant and small tools costs shall not be adjusted for changes in costs, that is, an above-band adjustment may not be stacked with risk allowance / management fee / profit. Clause numbers must not be mixed across editions: in the 2013 edition the all-in unit rate is Clause 2.0.8 and the risk allowance is Clause 2.0.9; in the 2024 edition the all-in unit rate is Clause 2.0.9 (excluding VAT).
- ←
Re-derivation of the all-in unit rate when a changed construction method makes the quota machine-shift consumption inapplicable: the three-path quota conversion test, the hierarchy of bases for recalculating plant consumption, the requirements for recasting the all-in unit rate analysis sheet, and the procedure for confirmation by the employer
Changes of construction method and plant usage are factors expressly listed in GB/T 50500-2024 Clause 8.9.1 as changes of item description or construction condition that can trigger adjustment of the all-in unit rate, but conversion must step down level by level: a conversion line item within the same chapter (DL/T 5468-2013 Clause 4.1.4 item 1: 'where the technical conditions prescribed by the quota (index) differ materially from the actual conditions of the works, the applicable quota (index) may be adjusted and applied according to the technical conditions of the works and the provisions of the quota') -> an express quota coefficient -> borrowing a similar process -> building up a rate from supplementary consumption (GB/T 51095-2015 Clause 5.3.12; TB 10801-2024 Clause 2.4.3); with no express coefficient, none may be invented. The hierarchy for recalculating machine-shift consumption is: contractor's in-house norms (GB/T 50875-2013 Clause 2.3.3) -> construction quotas (Clause 2.3.5) -> budgets or final accounts of similar works, or site measurement records certified by both parties (DL/T 5468-2013 Clause 4.1.4 item 2). After conversion, the all-in unit rate analysis sheet must be recast (GB/T 51095-2015 Clause 5.3.9; GB/T 50500-2024 Clause 6.2.12 and Annex E Table E.2.2-1) and submitted to the employer under the 'submission, checking, review, re-examination and confirmation' procedure (Clauses 8.1.2 and 8.1.3; for additional works, the project execution plan or implementation scheme and the priced offer must also be submitted before execution, Clause 8.10.2). The original quota line item must never be applied in departure from the approved construction scheme.
- ←
Reading the all-in unit rate pricing schedule of the fee quota norms line by line: charging bases (labour cost / labour cost plus plant and small tools cost), the order of charging (overheads, profit, risk cost -> all-in unit rate; pre-tax project cost -> VAT -> unit works cost), and a comparison of provincial bases (Shaanxi 2025 tables 5-1/5-2/5-3; Hubei 2024) with sector bases (highway form 08; railway table 2.6.2)
The main line of the all-in unit rate pricing program: labour, materials and plant (including dynamic adjustment / price differentials) -> direct cost subtotal -> overheads and profit (base: 'labour cost plus plant and small tools cost'; some provinces use 'labour cost') x rate -> (the Hubei basis adds a separate risk-factor line) -> all-in unit rate = the sum of all items; unit works cost = element works + preliminaries + other items = pre-tax (net-of-tax) project cost, then x VAT rate and added. In the Shaanxi 2025 'Shaanxi construction works fee rules', table 5-2 (base = labour cost plus plant and small tools cost) and table 5-3 (base = labour cost) list the social security costs of construction workers separately into the all-in unit rate as labour cost x rate, and table 5-1 places VAT after 'pre-tax project cost'; in the Hubei 2024 fee quota norms, overheads / profit = (labour cost + plant and small tools cost) x rate with the risk factor alone on line 6, while Annex 4 (tender price ceiling program) still keeps an independent 'statutory levies and fees' line (a trace of the 2013 BOQ basis). Highway JTG 3830-2018 form 08: preliminaries / overheads take quota labour cost + quota plant cost (or quota direct cost) as base, statutory levies take labour cost as base, profit takes (quota direct cost + preliminaries + overheads) as base, and taxes and duties take (direct cost + preliminaries + overheads + statutory levies + profit) as base.
- ←
Whether varied works may be given newly built-up rates when the priced BOQ already contains an applicable rate: the three-tier decision table for variation valuation, the tests for 'applicable' and 'similar', and a clause-by-clause comparison of GB 50500-2013 clause 9.3.1 with GB/T 50500-2024 clause 8.9.1
For BOQ items whose applicable rate already exists in the contract, varied works may not be re-rated with newly built-up rates; the original contract all-in unit rate applies directly (GB 50500-2013 clause 9.3.1 item 1: 'the rate of that item shall be adopted'; GB/T 50500-2024 clause 8.9.1 item 1: 'for BOQ items executed under the same construction conditions with the same item descriptions, the corresponding contract unit rate shall be adopted'). The three tiers of variation valuation step down in order and stop once one is hit: (1) an applicable rate exists - apply the contract rate directly (only where the quantity deviation exceeds 15% is the rate adjusted up or down under clause 9.6.2 / clause 8.9.2, which is price adjustment, not new rate build-up); (2) only a similar rate exists - convert by reference to the similar item's rate (the 2024 edition: 'the all-in unit rate converted and adjusted from the contract rate of a similar BOQ item', converting only the differing elements while the levels of overheads and profit are retained); (3) neither applicable nor similar - the contractor proposes a new rate on the basis of the variation documents, executed after the employer confirms it (the 2024 edition: negotiate a market-reasonable all-in unit rate). Quantity-only changes and minor adjustments of secondary item description elements do not constitute re-rating; only substantive changes of material specification, construction method or construction conditions (differing in both the description and the conditions dimensions) trigger new rate build-up.
- ←
Composition of the tender bill of quantities: the five parts of GB 50500-2013 (bill of divisional and elemental work items, bill of preliminaries, bill of provisional sums and other charges, bill of statutory levies, bill of taxes and duties) with the itemisation rules of each, and the composition contrast under GB/T 50500-2024
GB 50500-2013 Clause 4.1.4: the tender bill of quantities shall be compiled with the individual work (or project) as the unit and shall consist of the bill of divisional and elemental work items, the bill of preliminaries, the bill of provisional sums and other charges, and the bills of statutory levies and of taxes and duties. Under Clause 4.4.1 the bill of other charges contains provisional sums, provisional prices (provisional unit prices for materials, provisional unit prices for permanent plant, provisional prices for nominated specialist works), dayworks, and the main contractor's attendance and coordination provisions; under Clause 4.5.1 statutory levies cover social insurance contributions (old-age, unemployment, medical, work-injury and maternity), the housing provident fund, and the works pollution discharge fee; under Clause 4.6.1 taxes and duties cover business tax, city maintenance and construction tax, the education surcharge and the local education surcharge. GB/T 50500-2024 Clause 3.1.2 instead compiles and prices the bill of divisional and elemental work items, the bill of preliminaries and the bill of other charges together with value added tax (the statutory levies and tax bills are no longer set up; the tax becomes value added tax, computed per Clause 3.2.11 by multiplying the total of the three bills, after deducting the provisional prices of nominated specialist works, by the VAT rate).
- ←
Deduction of employer-supplied (free-issue) materials from payments and allocation of costs: deduction mechanism, procurement/custody fee and wastage responsibility (GB/T 50500-2024, T/ZBD 100.4-2023)
Where employer-supplied (free-issue) material prices are not included in the all-in unit rate (stripped pricing), settlement naturally requires no deduction; where the contract stipulates prior inclusion, deduct from the settlement amount at actual consumption (issued quantity − stock) × the supply contract unit price. Procurement and custody costs follow the material and belong to the procuring party (the employer); the cost of the contractor's custody and assistance services is borne by the employer and charged under the main contractor's attendance and coordination provisions; wastage within the valid wastage rate is borne by the employer, over-drawing attributable to the contractor is borne by the contractor, and employer-caused causes (non-conforming specifications, untimely supply) are borne by the employer.
- ←
Layered build-up of the fully loaded all-in rate: the base chain from labour, materials and plant through overheads, profit, statutory levies and taxes; the three charging-base regimes; why percentage rates cannot be added directly; and the cost boundary and conversion against the BOQ all-in unit rate (which excludes statutory levies as a separate line and VAT)
The fully loaded all-in rate must be built up layer by layer: overheads and profit are usually charged on labour cost plus plant and small tools cost, or on labour cost alone; statutory levies mostly on labour cost; VAT on the fully inclusive price excluding VAT. Each layer has a different, progressively larger base, so multiplying one base by (1 + the sum of the rates) overstates the result (a worked example overstates by about 33%). The correct chain is D = A + B + C -> overheads E and profit F charged on their own bases -> fully inclusive price excluding VAT P = D + E + F -> VAT T = P x t -> Q = P + T. The BOQ all-in unit rate under GB/T 50500-2024 cl. 2.0.9 and 3.1.6 is a pre-tax price excluding VAT (cl. 3.1.2's four BOQ categories no longer list statutory levies separately); the conversion is fully loaded all-in rate Q = (BOQ all-in unit rate Qc + statutory levies R) x (1 + VAT rate t).
- ←
The rate build-up path from quota line items to the all-in unit rate of a BOQ item and the cost calculation procedure: divisional work item cost as BOQ quantity x all-in rate, sum of quota line item amounts / BOQ item quantity (3 decimal places for quantities, 2 for rates), the three pricing methods, the analysis sheet identical to the BOQ rate, and the taxed versus tax-exclusive cost structures
The all-in unit rate of a BOQ item is converted as 'sum of quota line item amounts / BOQ item quantity' (item amounts at full precision with no rounding, BOQ quantities to 3 decimals, all-in rates to 2), and divisional work item cost = sum of (item quantity x all-in rate); the rates and prices in the all-in unit rate analysis sheet must exactly match those in the BOQ (GB/T 50500-2024 clause 3.1.7); pricing methods are unit-rate, lump-sum and percentage-rate, with divisional items and dayworks best priced at unit rates and preliminary items by lump sum or percentage; the taxed cost follows 'tax-exclusive cost of works = (divisional items + unit-rate preliminaries) + lump-sum preliminaries + other charges, and VAT = tax-exclusive cost x rate'; the scope of the all-in rate must be confirmed first - GB/T 50500-2024 clause 2.0.9 excludes VAT, while GB/T 51095-2015 clause 5.3.8 and article 5 of Ministry of Construction Order No. 107 are full-cost scopes including statutory levies and taxes.
- ←
The VAT charging base of the bill of quantities and the non-duplication of tax on provisional sums for specialist works (GB/T 50500-2024 clauses 3.2.11 and 3.1.6)
VAT = [work-item list + preliminaries list + other-items list (less the provisional sums for specialist works)] total x the VAT rate set by the authorities; the specialist provisional sums are VAT-inclusive, and no further tax may be charged on them (clauses 3.2.11 and 3.1.6). Under general taxation the construction rate is 9% (price and tax separated); under the simplified scheme the levy rate is 3% (factor prices carry input tax, the base being the tax-exclusive works cost that already includes input tax).
- ←
Determining overheads (company and site) and profit within the all-in unit rate: the dual track of the percentage-rate method and independent market-level measurement (including railway on-costs percentage rates)
Overheads (company and site) and profit are determined on the dual track of fee standards/percentage-rate method + market-level correction: estimates/budgets and tender price ceilings (employer's maximum acceptable price) are computed per the percentage rates in the norms for on-costs and expenses (railway merges the two into on-costs (indirect costs) = (base-period labour cost + base-period plant and small tools cost) × on-costs percentage rate, TB 10811-2024 Table 2.9.1, 16 categories, 14.3%–58.6%); tenders (priced offers) are independently measured by the enterprise; profit is a competitive cost but bidding below enterprise cost is prohibited. Price adjustment for cost fluctuation carries value added tax (VAT) only, with no overheads or profit.
- ←
Setting overheads and profit in repricing variations and other price adjustments (GB/T 50500-2024 Articles 3.6.6, 8.4.6, 8.8.5, 8.9.1)
On repricing (no identical or similar rates), GB/T 50500-2024 Article 8.9.1 negotiates a market-reasonable all-in unit rate - by reference to the pricing rules and pricing level of analogous contract rates or to analogous items of similar works; the expert-assessment basis is reasonable cost plus the contract overheads and profit rates (T/ZBD 100.4-2023 Article 4.6.2), the supervision basis the cost-plus-profit principle (GB/T 50319-2013 Article 6.3.3). Similar-rate conversion (tier 2) swaps only the differing elements, the original overheads and profit preserved. Where employer-supplied materials become contractor-purchased, add to the original all-in unit rate the material cost (with reasonable wastage) plus overheads and profit, at the rates of the item's rate build-up or the nearest analogous item (Article 3.6.6). Reverse rules: on laws and policy changes, the overheads and profit within the total price and unit rates are not adjusted (8.8.5); provisional-sum materials adjust only the pre-tax provisional material price, nothing else (8.4.6); fluctuation differentials carry VAT only, no overheads or profit (3.3.5).
- ←
Pricing principles for variation works in construction cost expert assessment: identical contract items take their rates, similar items take similar rates, and absent both, a new all-in unit rate from reasonable cost per the appraisal records plus the contract overheads and profit rates, or per the pricing basis (T/ZBD 100.4-2023 Article 4.6.2)
Unless the contract provides otherwise, the expert appraiser assesses variation works on three tiers: 1 where the varied work has an identical item in the contract, apply the all-in unit rate or percentage rate of that identical item; 2 where there is no identical item, an analogous item's all-in unit rate or percentage rate may be applied; 3 where there is neither an identical nor an analogous item, determine a new all-in unit rate from the reasonable cost of executing the work calculated per the appraisal records submitted by the contractor plus the contract overheads and profit rates, or from the pricing basis of the construction authority or the relevant industry at the project's location plus the contract overheads and profit rates. Item 3 marks a major adjustment responding to governments phasing out budget quota publication: the contractor must be able to evidence cost where no identical or similar all-in unit rate exists, and the appraiser assesses from those records together with the contract rates and the works as actually executed.
- ←
Determining the all-in unit rate of additional works (outside the contract-agreed scope of works) (GB/T 50500-2024 Section 8.10)
The all-in unit rate of additional works follows the dual path of 'contract unit rates first, negotiated rate build-up as fallback': (1) list and measure per the contract-agreed measurement and pricing rules, and price by combining contract unit rates and tender price levels; (2) where no applicable unit rate exists, the employer and contractor renegotiate the measurement and pricing rules. Conversion of contract unit rates must consider four factor groups: labour/material/machinery price differences, bulk-procurement effects, correction of under/over-priced items, and differences between competition-formed and negotiated rates; before implementation, submit the quotation for review and sign a supplementary agreement before proceeding; further variations to additional works are priced per Section 8.9, and Clauses 8.2.2/8.2.3 (BOQ errors/omissions) should not apply. Construction cost expert assessment (judicial appraisal) position: works outside the contract are not necessarily bound by the original contract; the contractor bears the burden of proof.
- ←
Charging boundary of material price differentials (construction-period adjustment): VAT only - no overheads or profit, and no participation in the charging bases of total-price preliminaries or statutory levies (GB/T 50500-2024 Article 3.3.5 paragraph 4, Article 8.7.6)
Differentials formed by construction-period material price settlement adjustments carry VAT only - no overheads or profit, and they do not join the charging bases of total-price preliminaries or statutory levies. Basis: GB/T 50500-2024 Article 3.3.5 paragraph 4 - differentials of labour, materials and the fuel-power element of plant within all-in unit rates carry VAT but not overheads or profit; Article 8.7.6 items 3 (preliminaries) and 7 (overheads and profit) are listed among fees not adjusted for cost fluctuation; and since total-price preliminaries charge on labour plus plant, and statutory levies on quota labour, material differentials - being material in nature - fall outside both bases anyway. Express contract terms prevail.
- ←
When bill and quota measurement units mismatch (m2 bill against m3 quota): no unit conversion - bill and quota quantities run on separate tracks, bridged by the all-in rate P = sum of item prices over Q
Bill units are locked - never rewrite a bill to m3 because the quota runs m3: GB/T 50500-2024 clauses 3.1.4 and 4.1.7 require units per the national and sector measurement standards, and GB 50861-2013 clause 4.2.6 (mandatory) "bill units shall follow the units in the appendix". The right handling is neither unit conversion nor a conversion factor on the quota rate, but: bill quantities on bill rules (keeping the appendix m2 unit), quota quantities converted on quota rules (m3), independent; then bridged per DBJ/T 15-145-2018 clause 6.1.4 - the all-in rate of a bill item equals the sum of the quota item prices under it divided by the bill item quantity.
- ←
Whether the all-in unit rate includes statutory levies and taxes: comparison and determination between BOQ-based pricing (non-fully-loaded) and the fully loaded all-in rate
Whether the all-in unit rate includes statutory levies and taxes depends on the pricing basis: under GB/T 50500-2024 BOQ-based pricing it excludes value added tax (VAT) (a price-exclusive tax listed separately) and no longer lists statutory levies and fees as a separate item (social insurance and housing fund contributions are amortized into labour cost and the overheads percentage rate); under the fully loaded all-in rate basis (GB/T 51095-2015 Clause 6.2.3, DB42/T 823-2021, DB14/T 1319-2021 highway) it includes statutory levies and fees and taxes. Confirm the applicable basis before pricing and review; the two sets must never be mixed.
- ←
The basis and cost attribution of the equipment-versus-material division in construction pricing (GB/T 50531-2009 general provisions, including process-type principal materials treated as equipment)
Per GB/T 50531-2009: divide equipment from material by supply scope, character and the standard's definitions - never by article name alone (clause 3.1.1); equipment-class costs enter permanent equipment procurement, material-class costs enter building-works or installation-works costs by discipline (clauses 1.0.3, 3.2.2). Equipment covers building services equipment, process equipment and process-type principal materials (long-distance pipelines, cables and the like special valves priced as equipment); the equipment scope = body + 5 items supplied with it (spares and fittings, companion piping and instruments, factory ladders platforms and railings, inspection and metering tackle, oils chemicals and packing). Fallback: not made on site counts as equipment, partly off-site with site assembly counts as equipment, catalogue products fabricated on site may count as material (clause 3.1.7).
- ←
May quantities cut by design variation be listed as negative BOQ items: the contract BOQ itself never goes negative - increases and decreases fall to the "variation increase-and-decrease price" item at final account; under lump-sum (fixed-price) contracts BOQ defects do not adjust, only differences between as-built and contract drawings form priceable variations (GB/T 50500-2024)
Quantity cuts from design variations must never be written as negative quantities in the original contract BOQ - BOQ quantities compute on design-shown dimensions and, under lump-sum contracts, divisional BOQ quantities need no re-measurement (clause 7.2.2); the cuts land at the settlement adjustment layer, item 9 of GB/T 50500-2024 clause 10.3.2, "variation increase-and-decrease price" (which may be negative), the contract-BOQ-total line standing unchanged. Under lump-sum contracts only the difference between as-built and contract drawings constitutes a priceable variation (clause 7.4.3); contract-drawing versus contract-BOQ differences are BOQ defects and never adjust (7.4.2, 8.2.3). Variation pricing splits on whether contract rates apply: applying, adjust under 8.9.1 (quantity change within 15%, inclusive) or 8.9.2 (over 15%, exclusive - cuts reasonably raise rates); not applying, the parties negotiate the all-in rates (8.9.3).
- ←
How to build up rates for additional works with no applicable quota norms: the progressive path of apply → convert → cost-plus-profit → market price enquiry
For additional works or variation items with no quota norms to apply, rate build-up follows the progression "identical items use the contract unit rate → similar items are converted and adjusted → quota norms for similar technology are adjusted in applying quota items, or supplementary quota items are compiled → rates are re-derived on a cost-plus-profit basis → confirmed by market price enquiry → a supplementary agreement is negotiated and signed by both parties"; the order of price sources is contract-agreed information sources → published price information (government guidance prices) issued by the construction cost administration or industry bodies (tax-exclusive) → contractor procurement unit prices confirmed by both parties; additional works are works outside the contract and are not necessarily bound by the original contract unit rates — submit for review before implementation, with the contractor bearing the burden of proof.
- ←
GB/T 50500-2024 VAT pricing basis: all-in unit rates are fully inclusive prices excluding VAT, with VAT listed and assessed separately
BOQ item all-in unit rates and their totals are fully inclusive prices excluding VAT (labour cost + material cost + plant and small tools cost + management fee + profit + agreed risk costs + indispensable auxiliary work costs), with taxes and duties listed separately under VAT; the VAT base = the combined amounts of the bill of quantities for divisional and sub-divisional works + the bill of preliminaries + the bill of provisional sums and other charges (less provisional sums for nominated specialist subcontract works) x the prescribed rate; provisional sums for nominated specialist subcontract works are tax-inclusive provisional amounts, on which VAT is no longer assessed.
- ←
Definitions, cost composition and applicable conventions of the direct-cost rate, the all-in unit rate and the fully loaded all-in rate compared (Order No. 107 of the Ministry of Construction, GB/T 50500-2024, GB/T 51095-2015, etc.)
The three rate conventions widen in scope in turn: the direct-cost rate (labour plus materials plus plant only, with on-costs, profit and taxes computed separately) is contained in the all-in unit rate (labour plus materials plus plant and small tools plus overheads plus profit plus risk fees within the agreed band; GB/T 50500-2024 clause 2.0.9 expressly excludes VAT, which is carried separately), which is contained in the fully loaded all-in rate (further including statutory levies and taxes, tax-inclusive; GB/T 51095-2015 clause 6.2.3 requires its use for the tender price ceiling and tenders). Note that the "all-in rate method" defined in Order No. 107 of the Ministry of Construction is a fully loaded unit rate - the same name as, but different content from, the "all-in unit rate" of current BOQ pricing; the "all-in rate" of highway works is likewise a wide convention including statutory levies and taxes (and additionally equipment procurement cost and preliminaries).
- ←
Overview of bills of quantities: composition, compilation, item descriptions and handling of errors/omissions (GB/T 50500-2024)
A bill of quantities comprises four sections — trade items, preliminaries, other items and VAT; the five BOQ elements (code/name/item description/unit of measurement/quantity) are compiled per the national and industry measurement standards. Division of responsibility: under unit-rate contracts the trade-items BOQ is the employer's responsibility, under lump-sum contracts the contractor's, and the bill of preliminaries is always the contractor's. BOQ defects are per definition 2.0.27; unit-rate contracts re-measure under section 8.2 with price adjustment at the 15% boundary; lump-sum contracts are generally not adjusted except provisional-quantity items.
- ←
Should the construction-installation cost in a design estimate carry provisional sums? — the stage division of provisional sums (BOQ/contract level) vs reserve funds (estimate level)
No. The construction-installation cost (works cost) in a design estimate must not carry provisional sums. Provisional sums are a contract-price account of BOQ pricing (construction tendering and implementation) (defined in GB/T 50500-2024, 2.0.13; scope limited by 1.0.2; employer-controlled, unused portions revert, 8.3.1); the estimate's uncertain/unforeseeable costs are carried by the reserve funds (basic + price-difference) in the total estimate, whose composition — works costs + other construction costs + reserves + construction-period loan interest + VAT (T/ZBD 100.3-2022, 4.1.1 and Annex A) — has no "provisional sum" account.
- ←
The FIDIC Clause 1 term "Cost" (1999 Red Book 1.1.4.3 vs 2017 1.1.19/1.1.20) and the three payment calibers: Cost / Cost Plus Profit / 12.3 "reasonable cost plus reasonable profit"
Capitalized "Cost" is a Clause 1 defined term: all expenditure reasonably incurred (or to be incurred) by the Contractor, on or off Site, including overheads but excluding profit — a chargeable "payment unit" entering the Contract Price; the 2017 edition narrows it to "in performing the Contract" and defines Cost Plus Profit as Cost + the profit rate in the Contract Data (default 5%). It is not the domestic norm-based "engineering cost"; claims and accounts must first identify whether a clause gives Cost, Cost Plus Profit, or a 12.3 new rate built from "reasonable cost plus reasonable profit".
- ←
Why the all-in unit rate under GB/T 50500-2024 excludes VAT: price-exclusive tax character, separation of net price and VAT, the rationale for listing taxes and duties (VAT under the current standard) separately, and practical reasons
Under GB/T 50500-2024, the all-in unit rate = labour cost + material cost + plant and small tools cost + management fee + profit + risk costs within the agreed scope and risk band (no-adjustment tolerance, e.g. ±5%) (incl. auxiliary work costs), excluding VAT. Four reasons: (1) VAT is a price-exclusive tax (2.0.9), not a production-factor cost of completing the billed (BOQ) item; (2) separation of net price and VAT — unit rates and totals are fully inclusive prices excluding VAT, with taxes and duties (VAT under the current standard) reflected in VAT (3.1.6); (3) taxes and duties listed separately and calculated uniformly — VAT = (bills of work items + bill of preliminaries + bill of provisional sums and other charges, except provisional sums for nominated specialist subcontract works) × the prescribed VAT rate (3.2.11); (4) practically, avoiding "tax on tax" and interfacing with the input VAT credit chain.
- ←
GB/T 50500-2024: definitions of the three pricing methods (unit rate / lump sum / rate-based) and their applicability to each BOQ category
GB/T 50500-2024 provides: work-section BOQ items and day-work items should use unit-rate pricing (quantity x comprehensive rate); measures items should use lump-sum or rate-based pricing; provisional sums and specialist-work provisional amounts should use lump-sum pricing; main-contract services should use rate-based or lump-sum pricing (shared passage of Clauses 2.0.10-2.0.12). Clause 3.1.5 is the catch-all: where unit-rate or lump-sum pricing is unsuitable, rate-based or other methods may be used, with pricing requirements and price-adjustment rules stated in the tender and contract documents.
- ←
GB/T 50500-2024 comparison of specialist-work provisional amounts (VAT-inclusive) and material provisional prices (VAT-exclusive): listing, taxation, and adjustment rules
Under GB/T 50500-2024 "Standard for BOQ pricing of construction works": the specialist-work provisional amount is a VAT-inclusive price (listed in other items, deducted from the VAT computation base to avoid double taxation, replaced wholesale by the successful VAT-inclusive subcontract price at adjustment); the material provisional price is a VAT-exclusive pre-tax unit price (entered into the comprehensive rate of a work-section item, VAT charged normally on the VAT line, adjustment limited to the pre-tax material difference within the comprehensive rate). The two have opposite tax calibers and differ in listing, taxation, and adjustment — mixing them double-counts or omits VAT.
- ←
Full-process handling rules for prime cost (PC) sums for materials included in the all-in unit rate across tender, performance and settlement (GB/T 50500-2024)
For prime cost (PC) sums for materials (tax-exclusive unit prices), tenderers must include them in the all-in unit rate as stated in the BOQ without unilateral alteration, and separately include safekeeping, secondary handling and loss costs and list them in Table E.2.3; during performance, after the winning tender price or the employer's approval of material prices, only the material PC sum item within the all-in unit rate is replaced, with other costs not adjusted; such items are not subject to the general adjustment for cost fluctuation under Clauses 8.7.2–8.7.4; for settlement and construction cost expert assessment (judicial appraisal), the material price confirmation sheet / winning tender basis serves as the price-adjustment voucher.
- ←
Correction windows and settlement handling for obviously abnormal (over-high/over-low) tendered all-in unit rates: tender-stage clarification/rejection vs settlement-stage contract price lock-in
The correction window for abnormal unit prices (incl. unbalanced bidding) is at tender stage: bidders may be required to clarify and, without changing the tender total, provide corrected unit prices for evaluation reference (GB/T 50500-2024 3.5.3); offers obviously below cost that cannot be proven reasonable are deemed below-cost bidding and rejected (MOT Decree 2018 No. 13 Article 32; MOHURD Decree No. 47 Article 42). At settlement, contract prices are locked: bidders are responsible for consistency and rationality of priced-list entries and bear irrational-pricing risk (6.1.2); settlement review may not adjust unit prices except as contractually agreed (T/ZBD 100.5-2023 3.1.6); the only legitimate repricing path is contractual adjustment events — the 15% quantity deviation boundary (8.9.1/8.9.2) — which corrects price changes induced by quantity changes, not tender-time anomalies.
- ←
Derivation of new (built-up) rates when a design change changes the construction process (construction method): qualifying the source + the three-tier path of GB/T 50500-2024 clause 8.9.1
"Change of construction method" is a price-impact factor of "item description change" expressly listed in GB/T 50500-2024 8.9.1: process changes caused by design changes or employer requirements are variations requiring derivation of new (built-up) rates; a contractor's autonomous process switch is construction method statement optimization, generally not adjusting the contract price, costs borne by the contractor itself. Pricing follows three tiers: identical conditions + identical item descriptions retain the contract unit rate; similar item descriptions/conditions convert via the original all-in unit rate analysis, replacing only differing elements; different item descriptions/conditions (complete method change) negotiate at "reasonable cost + profit" with a new all-in unit rate analysis. Confirm the pricing path in writing before implementation and keep evidence; accompanying quantity changes beyond 15% (exclusive) follow 8.9.2 — for increases, reasonably reduce; for decreases, reasonably increase.
- ←
Six-step labour-material-plant analysis for the all-in unit rate: apply quota line items -> take consumption and compilation-period unit prices -> add management fee and profit -> fill the all-in unit rate analysis sheet
Labour-material-plant analysis splits the all-in unit rate by "consumption x unit price" into three direct costs — labour cost, material cost, and plant and small tools cost — then superimposes management fee, profit, and the agreed risk cost; consumption is taken from quota line item factor values, unit prices from the report compilation-period market prices / published price information (government guidance prices), and fees per the matching norms for on-costs and expenses (GB/T 51095-2015 Clause 5.3.9). The analysis sheet must be fully consistent with the BOQ all-in unit rate (GB/T 50500-2024 Clause 3.1.7), in the form of Appendix E.2.2.
- ←
Disallowance grounds on final-account review for double counting of earthwork haul distance: the all-in unit rate cost envelope under GB/T 50500-2024 + the "disposal of surplus (excavated) material" itemisation basis in the measurement standards
Earthwork loading and haulage costs are already included in the corresponding billed (BOQ) items' all-in unit rates (GB/T 50500-2024 2.0.9, 3.1.6); haul distance is an item description (work item specification) — where the description states a distance, the contract unit rate has locked the corresponding transport cost, and without a variation or BOQ error no separate charge is allowed (8.9.1 item 1, 7.2.1); duplicated haul costs fall within none of the 13 final-account adjustment categories (10.3.2) and shall be disallowed. Off-site haulage can only be itemised as "disposal of surplus (excavated) material" (GB/T 50854-2024 A.4.13, GB/T 50857-2024 A.4.6); excavation work content covers on-site haulage only.
- ←
Mechanism for material price changes under fixed unit-price contracts: unit price locked + quantities at actuals + beyond-band adjustment (GB/T 50500-2024)
Under unit-price contracts the all-in unit rate is fixed within the contract-agreed risk conditions and quantities are determined at what is actually completed and should be measured (2.0.6); material prices follow "contract agreement first, statutory fallback": an express adjustment clause adjusts per the agreement -> agreement of adjustability without method follows industry pricing documents -> express non-adjustment is executed (unless the clause is invalid) -> no agreed band: fluctuation beyond 5% adjusts per Appendix A (8.7.2); the difference carries VAT only, no management fee or profit (3.3.5).
- ←
Distinguishing the basis of the all-in unit rate from that of the fully loaded all-in rate (incl. taxes and specified on-costs): composition differences, applicable scenarios, and risks of mixed use
Narrow-sense all-in unit rate = labour cost + material cost (including engineering equipment) + plant and small tools cost + overheads (company and site) + profit + risk cost within the agreed scope and risk band (no-adjustment tolerance, e.g. ±5%), excluding statutory levies and fees and value added tax (VAT) (GB/T 50500-2024 Clause 2.0.9, VAT being a price-exclusive tax listed separately); the fully loaded all-in rate (incl. taxes and specified on-costs) = the above + statutory levies and fees + taxes and duties (VAT under the current standard), tax-inclusive (GB/T 51095-2015 and other consultancy/local bases). Note that the 2024 edition's "fully inclusive price excluding VAT" means all costs are included but VAT is still excluded — different from the industry-conventional fully loaded all-in rate (incl. taxes and specified on-costs). A single project must adopt a consistent basis; mixing the two leads to total-price miscalculation.
- ←
Three bases for the composition of the construction price: cost elements, BOQ-based pricing, and final-account listing
The construction price (cost of works (construction and installation)) has three composition bases: (1) by cost elements (GB/T 50875-2013 Clause 2.2.10) = labour cost + material cost + construction machinery usage cost + management fee + profit + statutory levies and fees + taxes and duties (VAT under the current standard); (2) by BOQ-based pricing (GB/T 50500-2024) = divisional/sub-divisional works cost + preliminaries + other-item cost + VAT — the 2024 edition abolishes the separate statutory-levies item, the all-in unit rate being a fully inclusive price excluding VAT, and the VAT base deducting provisional sums for nominated specialist subcontract works; (3) by final-account listing (Clause 10.3.2) — 13 items. Mind the differences between the 2013 and 2024 bases when comparing.
- ←
GB/T 50500-2024 vs GB 50500-2013 edition change: all-in unit rate composition changes and the repositioning of statutory levies and fees and taxes and duties in the BOQ-based pricing system
The 2024 edition removes "statutory levies and fees" entirely from the BOQ system (no longer listed; the mandatory "shall not be competitive" clause canceled); taxes and duties become value added tax (VAT) listed separately at the summary level (= total of summarized list prices x VAT rate); the all-in unit rate is explicitly a fully inclusive price excluding VAT (labour cost + materials + plant and small tools cost + management fee + profit + agreed-scope risk + indispensable auxiliary work costs); "overheads (company and site)" is renamed "management fee". The 2013 edition excluded statutory levies and fees and taxes and duties indirectly via mandatory provisions of codes; 2024 declares "excluding VAT" directly in the term definition. The standard changed from mandatory GB to recommended GB/T, effective 2025-09-01 with the 2013 edition abolished.
- ←
Overheads (company and site) within the all-in unit rate vs. site management fee within lump-sum preliminaries: distinction and prevention of duplicate charging
Overheads (company and site) are on-costs (indirect costs) in nature and enter the all-in unit rate (labour cost + materials cost + plant and small tools cost + overheads (company and site) + profit + agreed risk, excluding value added tax (VAT)), and are settled with the quantities; the legacy 'site management fee' belonged to preliminaries and was lump-summed per item. Since Jian Biao [2003] No. 206, the site management fee has been merged into overheads (company and site), and most provinces no longer list it separately within lump-sum preliminaries; the same management outlay can be charged only once — in preparation and audit review, check that the local quota norm percentage rate basis and the item listing are consistent with each other.
- ←
Item description vs method of measurement in the BOQ: the item description column must not stipulate the method of measurement; supplementary rules belong in the BOQ calculation-rules statement and apply as contractual agreement
Item description and method of measurement are two parallel, independent elements of the bill of quantities (BOQ): the item description must be drafted in accordance with the annexes to the measurement standard and the actual works, its function being to fix the all-in unit rate; quantities must be computed under the method of measurement prescribed in the annexes (mandatory provisions of codes) — the item description column must not stipulate the method of measurement. Where supplementary rules are genuinely required, they must be set out in the BOQ calculation-rules statement (naming the national and industry standards adopted, with their titles and numbers, or setting out the detailed supplementary rules) and made part of the tender documents/contract documents, applying as "contractual agreement". Hierarchy of measurement bases: contractual agreement -> national standard matching the contract type -> industry/local standard.
- ←
GB/T 50500-2024 Appendix E pricing cost summary: Table E.1.1 summary hierarchy (project → single project → unit work) and aggregation rules for billed items, preliminary items, other charges and VAT
GB/T 50500-2024 Appendix E contains a single general summary table — Table E.1.1 "Project summary table" — using three-level numbering (1 → 1.1 → 1.1.1) to express the project → single project → unit work hierarchy; Note 2: "This table is preferably used for the summary calculation of works where the contract subject is the object of preparation of the bill of quantities; works where a single project or unit work is the object of preparation of the bill of quantities may also be summarised using this table." Aggregation rules: billed (BOQ) item costs (the only level expanded down to unit-work detail) roll up level by level; preliminary items (with 2.1 safety-production preliminary items listed separately) and other charges (broken out into provisional sums / provisional sum for nominated specialist subcontract works / dayworks / main contractor's attendance and coordination provisions / other items agreed in the contract) are summarised at whole-project level; VAT is listed separately and its calculation base excludes the provisional sum for nominated specialist subcontract works (Note 1); total = 1+2+3+4. All-in unit rates are fully inclusive prices excluding VAT (Clause 3.1.6, term 2.0.9); statutory levies and fees are no longer listed separately in the 2024 edition, having been merged into management fee; settlement follows Table E.6.1, with amounts adjusting for errors and omissions in the BOQ entered respectively under "contract price adjustment amount" of billed items and preliminary items.
- ←
Calculation of progress payments (GB/T 50500-2024 §9.1/§9.4): the cumulative-difference method, the 11-item composition of cumulative completed value, and payment/deduction rules
Current payable progress payment = cumulative completed value to date − cumulative paid price − current deductions (GB/T 50500-2024 Clauses 9.1.6, 9.4.9); absent an agreed ratio, payment should be no less than 80% of cumulative completed value (9.1.7); the cumulative value comprises 11 items — contract BOQ price, BOQ errors/omissions adjustments, provisional sums, adjustments of provisional prices after procurement, main contractor's attendance and coordination provisions, dayworks, changes in costs, regulation/policy changes, variations, additional works, claims; the statutory safety provisions advance may not be recovered from progress payments (9.1.7, 9.3.2), advances recovered per the agreement (9.2.6); disputed items certified and paid first on undisputed parts (9.4.11); payment applications must list construction workers' wages separately (9.4.9).
- ←
Six-step method for reviewing the reasonableness of all-in unit rates: rate build-up basis -> labour/materials/plant -> on-costs -> special items -> horizontal comparison -> arithmetic
Reviewing an all-in unit rate means breaking down and verifying the three pricing elements (labour/material/plant consumption x unit price + on-costs) layer by layer, plus horizontal comparison against market benchmarks. Six steps: (1) compliance of the rate build-up basis; (2) labour/material/plant consumption at quota norm values, unit prices at compilation-period market/published price information (government guidance prices); (3) compliance of on-cost rates and bases (in the 2024 edition, check for double-counting after statutory levies and fees are rolled in); (4) special items (provisional sums for specified materials adjust material price only; employer-supplied (free-issue) materials; attribution of risk allowances); (5) horizontal comparison against tender price ceilings/similar works/analogous projects and identification of unbalanced rates / rate loading; (6) arithmetic check (unit price x quantity = extended amount; analysis sheet consistent with the BOQ).
- ←
GB 50500-2013 -> GB/T 50500-2024: changes to the clauses on statutory levies and fees, taxes and the mandatory health, safety and environmental (HSE) provisions — mandatory provisions withdrawn, the bills restructured into four parts, and the item renamed statutory safety provisions
2013 Clause 3.1.6, “statutory levies and fees and taxes must be calculated in accordance with the provisions of the state, provincial or industry construction authorities and shall not be treated as competitive costs” (a mandatory provision), disappears entirely from GB/T 50500-2024: the 2024 edition is a recommended GB/T standard with no mandatory provisions anywhere; under Clause 3.1.2 the bills become four parts (work items / preliminaries / provisional sums and other charges / VAT), statutory levies and fees are no longer a separate billed item, and taxes are renamed VAT (Clause 3.2.11: the tax base is the total of work items + preliminaries + other items, less the provisional sum for nominated specialist subcontract works, multiplied by the tax rate). The mandatory health, safety and environmental (HSE) provisions are renamed “statutory safety provisions” (Clause 3.2.5), and their “non-competitive” character is expressly retained (“is a non-competitive item”), but the wording is softened from “must ... shall not be treated as competitive costs” to “shall be priced in accordance with the relevant provisions of the state and provincial or industry authorities”. GB/T 50500-2024 takes effect on 1 September 2025, and GB 50500-2013 is repealed at the same time.
- ←
Determining the pricing risk scope within the all-in unit rate: contract agreement first + statutory fallback of GB/T 50500-2024 Sections 3.3/8.7
Risk-scope determination follows 'contract agreement first, statutory fallback second': the employer and contractor must specify the content, scope and risk band (no-adjustment tolerance, e.g. ±5%) of measurement and pricing risks in the tender documents/contract, and clauses providing for uncapped risk allocation to one party and 'all risks' are prohibited; where not agreed or unclear, the risks are statically divided per GB/T 50500-2024 Clauses 3.3.2/3.3.3 (employer: BOQ errors / omissions, errors in raw data, approved changes, acceleration/stoppage, changes in laws and policies, cost fluctuations beyond the risk band; contractor: accuracy of the bill of preliminaries, BOQ errors / omissions in lump-sum contracts, own scheme/machinery/management, cost fluctuations within the risk band), with Section 8.7 as the dynamic quantitative fallback (where no risk band is agreed, the portion exceeding 5% is adjusted per Appendix A; the price difference carries value added tax (VAT) only, with no management fee or profit).
- ←
GB/T 50500-2024, China's BOQ pricing standard: positioning, 2024-vs-2013 changes, chapter map and card-group navigation
GB/T 50500-2024, the China national pricing standard for BOQ-based pricing (MOHURD Announcement No. 212 of 2024, approved 26 November 2024), came into force on 1 September 2025 and repealed GB 50500-2013. Its status shifted from a partly mandatory code to a recommended national standard (GB to GB/T), aiming to regularise pricing rules and let the market form construction costs. It governs pricing activity in tendering, contracting and execution for construction works; EPC and other general-contracting models apply it by reference, and the requirement that state-funded projects use BOQ pricing is carried by a MOHURD ministerial order. Nine headline revisions (per the foreword): risk scope and allocation rules by contract form; a new bid clarification mechanism; revised pricing of preliminaries; the 'contract price agreement' chapter replaced by contract selection and requirements; revised measurement and adjustment rules; site visas abolished and additional-works pricing introduced; interim settlement by construction stage added; dispute resolution revised; the cost-expert-assessment chapter deleted. The structure was rebuilt from 16 chapters into 12 chapters plus annexes: 'tender control price' renamed tender price ceiling; completion settlement and contract-termination settlement merged into 'works settlement and payment' (absorbing stage settlement); dispute resolution and expert assessment merged; pricing tables moved to annexes (with a new Annex G, schedule of price-adjustable key materials).