Definition and cost composition of the all-in unit rate (GB/T 50500-2024 Clause 2.0.9, GB/T 50875-2013 Clause 2.2.58)

All-in unit rate = labour cost + material cost (including engineering equipment) + plant and small tools cost + overheads (company and site) + profit + risk cost within the agreed scope and range, required to complete one specified unit of measurement of a billed (BOQ) item; VAT is excluded (a price-exclusive tax). Basis: GB/T 50500-2024 Clause 2.0.9 and GB/T 50875-2013 Clause 2.2.58; building works BOQ-based pricing uses the "incomplete-cost" caliber excluding statutory levies and fees and taxes, while highways and other industries may use the fully loaded caliber including statutory levies and fees and taxes — confirm the applicable industry standard before citing.

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准 第2.0.9条
  • GB/T 50875-2013 工程造价术语标准 第2.2.58条

Topic Positioning

The all-in unit rate is the core pricing unit of pricing on a bill of quantities basis. This card covers its standard definition, cost composition, and differences in industry caliber, applicable to tender pricing, contract valuation, interim payment, and settlement reconciliation.

Core Conclusions

Per GB/T 50500-2024, the China national pricing standard for BOQ (Clause 2.0.9), the all-in unit rate is the cost required to complete one unit quantity of a billed (BOQ) item, comprehensively considering influencing factors such as technical standards and codes, construction duration, construction sequence, construction conditions, geography and climate, plus risks within the agreed scope and range. Composition = labour cost + material cost (including engineering equipment) + plant and small tools cost + overheads (company and site) + profit + risk cost within the agreed scope and range; VAT is a price-exclusive tax and is not included in the all-in unit rate. GB/T 50875-2013, the Standard for construction cost terminology, Clause 2.2.58, uses the same caliber. Along the pricing chain: quantity x all-in unit rate = item price; tender pricing, interim payment, and settlement all take the all-in unit rate as the benchmark.

Applicable Boundaries

This is the BOQ-based pricing caliber for building and general installation works (an "incomplete-cost all-in unit rate"), excluding statutory levies and fees and taxes — the 2024 edition removed the separate statutory-levy item, with social insurance and housing fund measured by bidders and apportioned into the labour unit price and the overheads percentage rate. In highways and other industries the all-in unit rate may include permanent equipment procurement cost, preliminaries, statutory levies and fees, and taxes (a "fully loaded all-in rate"); confirm the industry/local standard's pricing caliber before citing, and never mix the two directly.

Further Reading

See GB/T 50500-2024 Clause 2.0.9 (all-in unit rate term), Clause 3.1.6 (fully inclusive price excluding VAT tender caliber), and Clause 3.2.11 (VAT listed separately and its taxable base); GB/T 50875-2013 Clause 2.2.58. Application of the all-in unit rate in adjustment of provisional prices after procurement, adjustment for cost fluctuation, and quantity deviation: 2024 edition Sections 8.4, 8.7, and 8.9.