Reading published price information as tax-inclusive or net, and the de-taxing conversion: de-tax by element (goods 13%, transport 9%, levy rate 3%), then custody, then into the all-in unit rate - with the order-bias test and double-tax prevention

Published prices are often tax-inclusive or freight-inclusive: read the release notes first. Tax-inclusive prices de-tax by each element's own rate (goods 13%, transport services 9%, simplified levy 3%) before purchasing and custody; a tax-inclusive delivered price divided once by 1.13 never adds freight or custody again. 'Add freight then divide the whole by 13%' differs algebraically from 'divide first, add later' only in form - both de-tax freight at 13%; the bias test is delta = F x (1/1.09 - 1/1.13) x (1+k). Net prices enter the all-in unit rate with VAT listed separately - one VAT only, throughout (GB/T 50500-2024 clauses 2.0.9, 3.1.6, 3.2.11).

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准 第2.0.9、3.1.6、3.2.11、8.4.1条
  • JTG 3830-2018 公路工程建设项目概算预算编制办法 第3.1.1、3.1.2条
  • TB 10801-2024 铁路基本建设工程设计概(预)算编制办法 第3.2节
  • TB/T 10813-2024 铁路工程材料基期价格 第1.0.3、1.0.4、1.0.5条
  • TB 10811-2024 铁路基本建设工程设计概(预)算费用定额 第2.12节及Table 2.12.1
  • 中华人民共和国增值税暂行条例 第十二条(征收率3%)
  • 湖北省建筑安装工程费用定额(2024)除税价/含税价与一般计税、简易计税条款

Positioning

Published cost information (and railway price information, highway / railway base-period prices) is often 'tax-inclusive' or 'freight-inclusive', while BOQ all-in rates and estimates need net-of-deductible-input prices. This card gives: (1) reading the basis; (2) de-taxing formulas under general and simplified taxation; (3) the order bias and its test; (4) the net-price / separate-VAT junction that prevents double taxation.

Core conclusions

1. Read the basis first - never assume Order: release notes -> column headings -> delivery point (ex-works versus delivered).

  • 'Tax-inclusive': de-tax before rate build-up.
  • 'Net / excluding deductible input VAT': already net - straight into rates, never de-tax again. Railway base-period prices are of this class - TB/T 10813-2024 clause 1.0.3: '2020 price level, excluding deductible input VAT.'
  • 'Composite ex-works / ex-works': excludes freight to site - add freight, then de-tax.
  • 'Delivered / site price': freight included - never add freight again, nor duplicate the included custody.
  • Unmarked: never assume; confirm with the publisher or contract, or take the adverse basis and record it. Railway evidence: cement, timber, steel, pipes, geosynthetics, rail fastenings, poles, masts, towers, catenary and power wire, optical cables and relays publish composite ex-works (class B) - the price at the named delivery point, with freight to site (plus custody on carriage, loading and related costs) computed separately by the designer; rails, turnouts, sleepers, steel girders, bridge bearings and catenary masts publish ex-works (class A); fuels and explosives publish delivered prices including all freight and custody (class C); 'composite ex-works and ex-works already include custody on the ex-works part'. Clause 1.0.4: A = origin price x (1 + custody rate); B = composite ex-works x (1 + custody rate); C = (origin + freight-in-price) x (1 + custody rate). Sector compositions: highway JTG 3830-2018 clause 3.1.2: budget price = (origin + freight) x (1 + off-site wastage) x (1 + custody) - packaging recovery; railway TB 10801-2024 clauses 3.2.4-3.2.5: (origin + freight-in-price) x (1 + custody), no separate wastage term. Published 'delivered' prices usually already hold wastage and custody.

2. The object of de-taxing is the deductible input - not one uniform rate Per element, factor = 1 / (1 + rate): goods 13% -> 0.88496; transport / construction services 9% -> 0.91743; simplified levy 3% -> 0.97087 (VAT Regulations Article 12); survey, design, consultancy and IT services 6%. TB 10811-2024 Table 2.12.1 maps rates: goods 13%; construction services 9% (works, equipment, safety funds); transport 9%; R&D and technical 6% (survey-design, coordination, research); certification 6% (land-agency fees, supervision, document review, monitoring, whole-process consulting); IT 6%. Land compensation, relocation, temporary land, crop and mineral overlays, staff training and stamp duties carry no VAT; construction-management fees carry VAT only under agency construction. Correct forms (general taxation; k custody, L wastage):

  • railway / general: net budget price = (tax-inclusive origin / 1.13 + tax-inclusive freight / 1.09) x (1 + k);
  • highway: = (origin / 1.13 + freight / 1.09) x (1 + L) x (1 + k);
  • single tax-inclusive delivered price: net price = price / 1.13, no further freight or custody (already inside).

3. The order question is really 'de-tax per element or not' (A + F) / 1.13 and (A + F) x (1 + k) / 1.13 are algebraically identical (multiplication commutes); the shared error is de-taxing transport services at 13% instead of 9%. The bias: delta = F x (1/1.09 - 1/1.13) x (1 + k) = about 0.0325 x F x (1 + k), F being tax-inclusive freight - wholesale de-taxing systematically understates the net delivered price, growing with freight share and distance; negligible for local materials without freight. The one correct course: split elements, de-tax each at its own rate, apply wastage and custody last.

4. Net into rates + VAT separate = one VAT only

  • All-in rate (term 2.0.9): 'labour, materials, plant, overheads, profit and in-band risk - excluding VAT; VAT is price-exclusive.'
  • Price-tax separation (3.1.6): rates and sums are pre-tax fully loaded; item tax sits in VAT; specialist provisional sums already hold VAT - never taxed again.
  • Base (3.2.11): VAT = (work items + preliminaries + other items less specialist provisional sums) x the rate.
  • Provisional prices never mix (8.4.1): material provisional sums are pre-tax (net); specialist provisional sums tax-inclusive - replacements follow the same characters.
  • Highway parallel: JTG 3830-2018 clause 3.1.1 - all items priced net of deductible input VAT.
  • Methods: general taxation uses net prices (output - input, 9% on construction); simplified uses tax-inclusive prices at the 3% levy (sales net of subcontract payments).
  • Express prohibition: never fill tax-inclusive material prices into rates and then charge 9% VAT - that counts the embedded input again as output. The one path: de-tax at 13/9/3/6% into pre-tax rates -> total net cost -> 9% VAT listed once (or 3% levy under the simplified scheme, likewise once).

Applicable boundaries

  • The bias formula holds where the published price is tax-inclusive delivered carrying both goods-13% and transport-9% inputs; single goods-inclusive prices (self-collection, no freight) show no bias.
  • 'Tax-inclusive or not' and 'freight-inclusive or not' are independent - read both.
  • Simplified (3%) projects de-tax and price at 3%; 1/1.03 matches 3% levy invoices only.
  • Sector compositions never cross: railway has no separate wastage term, highway does; highway cost-of-works runs 8 items with separate levies and tax; building works follow the BOQ standard.
  • Rates are current; follow the tax files of the day. No price values here; custody, wastage and packaging recovery follow their own norms.

Further reading

  • GB/T 50500-2024 clauses 2.0.9, 3.1.6, 3.2.11, 8.4.1; JTG 3830-2018 clauses 3.1.1-3.1.2; TB 10801-2024 clause 3.2; TB/T 10813-2024 clauses 1.0.3-1.0.5 (classes A / B / C); TB 10811-2024 clause 2.12 (VAT plan); the current railway material information 'notes'; Hubei 2024 fee norms (net / tax-inclusive definitions, computation); VAT Regulations Article 12; provincial release notes - most conversion errors come from unread notes.