purchasing and custody charges
- 01
Reading published price information as tax-inclusive or net, and the de-taxing conversion: de-tax by element (goods 13%, transport 9%, levy rate 3%), then custody, then into the all-in unit rate - with the order-bias test and double-tax prevention
Published prices are often tax-inclusive or freight-inclusive: read the…
GB/T 50500-2024 建设工程工程量清单计价标准 第2.0.9、3.1.6、3.2.11、8.4.1条JTG 3830-2018 公路工程建设项目概算预算编制办法 第3.1.1、3.1.2条TB 10801-2024 铁路基本建设工程设计概(预)算编制办法 第3.2节2026-10-25 - 02
Where material wastage is booked, and the double counting and omission tests: off-site transport and storage losses into the material unit price (price factor) versus site haulage and operation losses into the quota consumption (quantity factor), with the site warehouse / designated stockpile point as the boundary, plus a comparison of booking positions for typical work items and settlement audit checkpoints
Material wastage may enter only one of the material unit price (price fa…
TB 10801-2024 · Measures for Compilation of Design Estimates and Budgets of Railway Capital Construction Projects 第3.2.1~3.2.6条、第4.1.2条TB/T 10821-2024 · Basic Quota of Railway Engineering 总说明第四条、Ch. 5砌筑说明、附录《材料工地搬运及操作损耗率》TB 10811-2024 · Fee schedule for design estimates and budgets of capital railway works 第2.2节 Table 2.2.22026-10-25 - 03
Four cost components of the material price (norm-based material price for estimating) and the step-by-step computation: the formula, the charging base of purchasing and custody, the double pass of transport wastage and the placement of inspection and testing costs
Material price (norm-based material price for estimating) = (material pr…
材料价格信息管理办法 第九条、第十条(材料价格四项构成与计算公式)湖北省建筑安装工程费用定额(2024)材料费内容陕西省建设工程费用规则(2025)材料费内容2026-10-18 - 04
Railway 2024 quota system equipment purchase cost: composition and booking — equipment price + equipment freight and handling charges, rate standards, and the nature boundary against installation works cost (TB 10801-2024 Section 3.10 / TB 10811-2024 Section 2.10)
Equipment purchase cost = equipment price + equipment freight and handli…
TB 10801-2024 · Measures for Compilation of Design Estimates and Budgets of Railway Capital Construction ProjectsTB 10811-2024 · Fee schedule for design estimates and budgets of capital railway worksGB/T 50531-2009 · Standard for Classification of Equipment and Materials for Construction Cost Pricing2026-09-25 - 05
Scope of the "delivered price" basis of published material price information: the mainstream basis includes the material price at source, freight and handling charges, transport wastage and purchasing and custody charges, but exceptions exist by region and category; read the notes of the current issue before use, and never count twice charges already included
The mainstream basis of published price information is the "delivered pr…
GB/T 50875-2013 工程造价术语标准(第2.2.14、2.2.16条)TB 10801-2024 铁路基本建设工程设计概(预)算编制办法(第3.2节)TB 10811 铁路基本建设工程设计概(预)算费用定额2026-09-25 - 06
Pricing rules for cross-region material procurement: purchase-origin price + freight compose the delivered price; adjustment per contract and the price-confirmation procedure
Budget compilation does not force a binary "project location vs purchase…
GB/T 50875-2013 工程造价术语标准TB 10801-2024 铁路基本建设工程设计概(预)算编制办法TB 10811-2024 铁路基本建设工程设计概(预)算费用定额2026-09-25 - 07
Highway JTG 3830-2018 purchasing and custody charge rates for materials: steel 0.75%, fuel and explosives 3.26%, other materials 2.06%, purchased components 0.42%, commercial mixes exempt — and the basis for the norm-based material price for estimating
Per clause 3.1.2 of JTG 3830-2018 "Administrative compilation rules for…
JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第 3.1.2 条JTG/T 3833 · Quota for Shift Costs of Highway Engineering Machinery2026-09-25 - 08
Whether published price information / base-period prices include freight and miscellaneous charges: price-caliber determination (ex-factory caliber excludes, delivered-to-site caliber includes) and the A/B/C classification of railway base-period prices
Whether price information includes transport charges depends on the publ…
GB/T 50875-2013TB 10801-2024TB 10813-20242026-09-25 - 09
Whether published price information / base-period prices include the procurement and keeping fee: caliber determination (railway base-period prices fully include, most provincial price information excludes, highway adds separately)
The procurement and keeping fee is added by rate and not merged into the…
GB/T 50875-2013TB 10801-2024TB 10811-20242026-09-25 - 10
Highway estimate/budget equipment purchase costs: four components — original price, freight, transport insurance, procurement and storage (JTG 3830-2018 clause 3.1.3)
Per clause 3.1.3 of JTG 3830-2018 "Measures for compiling estimates and…
JTG 3830-2018 公路工程建设项目概算预算编制办法(第3.1.3条、第3.1.1条、第3.1.2条、App. C)2026-09-25 - 11
Determining material cost within the all-in unit rate: the two-step norm resource consumption × material unit price method, special situations, and the tax-exclusive boundary
Material cost = norm material consumption × norm-based material price fo…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 50875-2013 工程造价术语标准GB/T 51095-2015 建设工程造价咨询规范2026-09-25 - 12
Overview of the full-chain use rules for construction cost published price information: nature, price calibers, stage-by-stage pricing, and frequent misconceptions
Published price information means reference guide prices issued by cost…
GB/T 50875-2013 工程造价术语标准GB/T 50500-2024 建设工程工程量清单计价标准TB 10801-2024 铁路基本建设工程设计概(预)算编制办法2026-09-25