Railway 2024 quota system equipment purchase cost: composition and booking — equipment price + equipment freight and handling charges, rate standards, and the nature boundary against installation works cost (TB 10801-2024 Section 3.10 / TB 10811-2024 Section 2.10)
Equipment purchase cost = equipment price + equipment freight and handling charges (TB 10801-2024 Section 3.10, these two items only). Equipment price = sum of (equipment quantity x original equipment price) (the original price excludes deductible input VAT and is determined per TB 10811-2024 Clause 2.10.1); equipment freight and handling charges = equipment price x rate, 6.5% for ordinary regions and 8.4% for Xinjiang/Tibet/Qinghai (Clause 2.10.2), with purchasing and custody charges already inside the composite rate and not booked separately. The installation cost of equipment requiring installation belongs to installation works cost (assembly, setting, and commissioning work) and appears as a parallel column beside equipment purchase cost in the composite estimate (budget) chapter table — it is not booked under this section.
Applicable Codes
- TB 10801-2024 · Measures for Compilation of Design Estimates and Budgets of Railway Capital Construction Projects
- TB 10811-2024 · Fee schedule for design estimates and budgets of capital railway works
- GB/T 50531-2009 · Standard for Classification of Equipment and Materials for Construction Cost Pricing
Topic Positioning
Under the railway 2024 quota system: the composition, formulas, and rate standards of the equipment purchase cost, and the cost-nature basis for "why the installation cost of equipment requiring installation is not under the equipment purchase cost section". Based on Section 3.10 of TB 10801-2024 "Measures for compiling design estimates (budgets) of railway capital construction projects" and Section 2.10 of TB 10811-2024 "Fee quotas for design estimates (budgets) of railway capital construction projects".
Core Conclusions
1. Composition: equipment purchase cost = equipment price + equipment freight and handling charges (TB 10801-2024 Clause 3.10.1, these two items only). It covers the cost of purchasing equipment, tools and instruments, and production furniture meeting the fixed-asset criterion, and equipment below that criterion but expressly listed in the equipment schedule by the design; where software bundled with purchased computer hardware is not separately priced, its cost is included in the equipment purchase cost together with the hardware. Under the cost-division caliber (Clause 2.5.2, item 3), the purchase costs of equipment requiring or not requiring installation (with spares), tools and instruments forming fixed assets (with spares), and special tools (with spares) are all booked here.
2. Equipment price = sum of (equipment quantity x original equipment price) (Clause 3.10.2). The original price of standard equipment = ex-factory price (including general packing to guarantee undamaged transport per the discipline standard, and the cost of tools, attachments, and wearing parts supplied with the product per its design); the original price of non-standard equipment = fabrication-order price (including material cost, fabrication cost, and the fabricator's management fee). Per TB 10811-2024 Clause 2.10.1: the original equipment price adopts a price excluding deductible input VAT; standard-equipment original prices are determined by comprehensive analysis of manufacturer ex-factory prices, the national mechanical-and-electrical product market price catalogue, and published price information (government guidance prices); non-standard equipment original prices are determined by analysis and verification of fabrication-order price data combined with published price information (government guidance prices).
3. Equipment freight and handling charges = equipment price x freight-and-handling rate (TB 10801-2024 Clause 3.10.3). The charge is "the general term for the transport, loading/unloading, agency, purchasing, and custody charges incurred in moving equipment from the manufacturer (origin) to the construction and installation site" — purchasing and custody charges are already inside the rate and are not booked separately. Rates per TB 10811-2024 Clause 2.10.2: 6.5% for ordinary regions; 8.4% for Xinjiang, Tibet, and Qinghai. Distinguish from the materials caliber: the material purchasing and custody charge is a separate rate (TB 10811-2024 Table 2.2.2), and the norm-based material price for estimating = (material price at source + freight and handling included in the material price) x (1 + purchasing and custody rate); equipment has a single composite rate (6.5%/8.4%) bundling transport, loading/unloading, agency, purchasing, and custody — the material formula must not be applied to it.
4. Why installation cost is not in this section: equipment purchase cost and installation works cost are cost categories of different natures listed in parallel (items 2 and 3 of the six-way static-investment cost division, TB 10801-2024 Clause 2.5.2). Installation works cost means "the cost of assembling and setting the various mechanical and electrical equipment requiring installation, erecting work platforms and ladders connected to the equipment, laying pipes and lines attached to the installed equipment, and insulating, painting, lagging, and commissioning the installed equipment" — a construction-operation cost with labour, materials, plant, and fees, priced by the installation quotas; equipment purchase cost covers only "the purchase act + delivery to the installation site", with no construction consumption. In the composite estimate (budget) chapter table (Appendix A), every chapter (e.g., electric power and electric traction power supply) carries the two parallel columns "II. Installation works cost / III. Equipment purchase cost", each on its own account.
Applicable Boundaries
- Applies to compiling design estimates (budgets) of railway capital construction projects (2024 quota system: TB 10801-2024 + TB 10811-2024).
- The original equipment price excludes deductible input VAT (general taxation caliber); when compiling, distinguish it from tax-inclusive prices — input VAT does not enter the equipment purchase cost.
- 6.5%/8.4% is the composite freight and handling rate for railway equipment only; the material purchasing and custody charge has its own rate table (Table 2.2.2) — the two must not be mixed.
- The installation cost of equipment requiring installation (assembly, setting, commissioning) is booked by the discipline installation quotas, not in the equipment purchase cost; the attribution of single-machine commissioning is bounded by the installation-works-cost definition.
- This card does not cover the chapter placement of equipment purchase cost within the four-part seventeen-chapter structure, or settlement matters such as claw-back of employer-supplied equipment.
Further Reading
- TB 10801-2024 "Measures for compiling design estimates (budgets) of railway capital construction projects": Clause 2.5.2 (six-way static-investment division), Section 3.10 (equipment purchase cost), Appendix A (composite estimate/budget chapter table, "II. Installation works cost / III. Equipment purchase cost" parallel per chapter).
- TB 10811-2024 "Fee quotas for design estimates (budgets) of railway capital construction projects": Section 2.10 (equipment purchase cost fee quotas), Table 2.2.2 (material purchasing and custody rates, for the materials contrast).
- National standard GB/T 50531-2009 "Standard for the division of equipment and materials in construction pricing": all costs within the equipment category (equipment price, equipment freight and handling charges, and subordinate charges) go to equipment purchase cost, installation-operation costs go to installation works cost by discipline — the same logic as the railway caliber.
Keywords
- permanent equipment procurement cost
- 设备运杂费
- 设备原价
- purchasing and custody charges
- 安装工程费
- TB 10801-2024
- TB 10811-2024
- railway estimates and budgets (China Railway system)