Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Calculation rules for railway material transport costs (out-of-price freight and miscellaneous charges) and secondary haulage (TB 10801/10811/10821)

Out-of-price freight and miscellaneous charges = sum(freight + loading/unloading + other transport charges) x (1 + procurement-and-keeping rate); train tariffs split by business line/temporary line/work trains into formulas multiplied by K1/K2 composite coefficients; truck tariffs computed as highway x 1.05, haul road x 1.2; on-site small hauling within 50 m is already in quota labor and not charged again; short-haul beyond 50 m is charged per TB/T 10821 short-haul transport quotas.

Applicable Codes

  • TB 10801-2024 铁路基本建设工程设计概(预)算编制办法
  • TB 10811-2024 铁路基本建设工程设计概(预)算费用定额
  • TB/T 10821-2024 铁路工程基本定额

Topic Positioning

The calculation rules for "material transport costs (out-of-price freight and miscellaneous charges)" and "secondary haulage (on-site small hauling/short-haul connection)" in railway estimates (budgets): the former is listed separately outside material costs per TB 10801-2024 Section 3.4 and TB 10811-2024 Section 2.4; the latter has no independent item and is handled by TB/T 10821-2024 as quota-included or by short-haul transport quotas.

Core Conclusions

  1. Out-of-price freight and miscellaneous charges = sum(freight + loading/unloading + other related transport charges) x (1 + procurement-and-keeping rate); the rate per TB 10811 Table 2.2.2 (cement 3.78%, sand 4.47%, crushed stone ballast 3.45%, bricks/tiles/lime 4.98%, rails/turnouts/sleepers/steel girders/bearings etc. 1.10%, other materials 2.65%).
  2. Train tariffs fall into four types — business lines, temporary lines, work trains, other railways: business line = K1 x (base price 1 + base price 2 x mileage) + K2 x (new-road price amortization + construction fund) x mileage; work train = 1.4 x K2 x (base price 1 + base price 2 x mileage). K1/K2 per Table 2.4.1: bricks/tiles/lime/sand/stone 1.00, ballast 1.20, rails (<= 25 m)/turnouts/sleepers 1.08, 100 m long-rail 1.80, 500 m long rails and 25 m track panels 1.43, single pieces >= 120 t 32 m T-girders 3.01/1.47, other T-girders 3.48/1.64, catenary poles/towers/rigid cross beams 2.35, wire materials 2.00, others 1.05. Loading/unloading per Table 2.4.2 unit prices (loading 60%, unloading 40%).
  3. Truck tariff = highway composite rate x highway distance + haul-road composite rate x haul-road distance, the two rates being local tax-exclusive unit prices x 1.05 and x 1.2 respectively; distances under 1 km are rounded.
  4. Secondary haulage: on-site small hauling within 50 m is already included in quota labor consumption (basic + auxiliary + small-haul labor) and material loss, and must not be double charged; short-haul connection beyond 50 m is charged per TB/T 10821 Chapter 7 labor, wheelbarrow, and small-vehicle quotas, with slopes converted to horizontal distance by actual slope length x gradient conversion coefficients.

Applicable Boundaries

Applies to railway works (except housing works) estimate/budget compilation, at prices excluding deductible input VAT; the compilation scope of out-of-price charges must correspond to the composite-estimate compilation unit (bridges/tunnels by work-point supply schemes; culverts/track by equal per-kilometer material usage of the main line averaged into mean haul distance); actual prices in the implementation stage are market-determined; rate values per the current TB 10811-2024.

Further Reading

TB 10801-2024 Section 3.2 material costs, Section 3.4 out-of-price freight and miscellaneous charges; TB 10811-2024 Section 2.2 material costs (Table 2.2.2 procurement-and-keeping rates), Section 2.4 out-of-price charges (Table 2.4.1 train composite coefficients, Table 2.4.2 loading/unloading prices); TB/T 10821-2024 general notes (50 m small-haul scope) and Chapter 7 material short-haul transport (labor/wheelbarrow gradient conversion coefficient table).

Keywords

Cited By