Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Railway 2024 quotas: budgeting self-built aggregate yards producing machine-made sand with combined plants (TB/T 10821-2024 Chapter 6 YY-70) and the unit-price composition of self-quarried aggregate

Machine-made sand uses Chapter 6 YY-70 of TB/T 10821-2024 (unit 100 m3 of finished aggregate; 2020 base 3,386.81 yuan/100 m3 — labor 270.66, plant 3,116.15, materials 0, raw feed separate). Chapter 6 is not a direct BOQ item: per the compilation measures 3.2.2 "material cost = sum of (quota consumption x material budget price)", it analyzes the self-quarried yard price (material original price) entering the material cost of concrete and other items. Self-quarried unit price: material budget price = (original price + freight-within-price) x (1 + procurement and custody rate) (TB 10801-2024 Clause 3.2.5); sand 4.47%, crushed stone (including ballast and medium/small cobbles) 3.45% (TB 10811-2024 Table 2.2.2); aggregate is Class A — base prices exclude freight, booked separately.

Applicable Codes

  • TB/T 10821-2024 铁路工程基本定额(Ch. 6 机制砂石)
  • TB 10801-2024 铁路基本建设工程设计概(预)算编制办法(第3.2节)
  • TB 10811-2024 铁路基本建设工程设计概(预)算费用定额(第2.2节、Table 2.2.2)
  • TB/T 10813-2024 铁路工程材料基期价格(第1.0.3~1.0.4条)
  • TB 10005-2010 铁路混凝土结构耐久性设计规范

Topic Positioning

Under the railway 2024 quotas: how to apply Chapter 6 of TB/T 10821-2024 when a self-built yard produces machine-made sand and other aggregate with a combined plant, and what the self-quarried aggregate unit price (material budget price) comprises — "which item, how it enters the budget, how the price is built".

Core Conclusions

1. The item (TB/T 10821-2024 Chapter 6 machine-made aggregate, Section 1 combined-plant production): machine-made sand uses YY-70, unit 100 m3 of finished aggregate. Also YY-69 machine-made stone chips, YY-71 crushed stone 5-10, YY-72 10-20, YY-73 20-31.5 — apply per size when the plant produces stone too. Work content: partial primary breaking, feeding, crushing, screening, discharge, stockpiling, waste clearing, watering. Base (2020, ex-deductible-VAT): YY-70 3,386.81 yuan/100 m3 — labor 270.66, plant 3,116.15, materials 0 (raw feed separate, see below).

2. Application logic (key): Chapter 6 is not applied directly as a BOQ item. Its use is to analyze the yard price (material original price) of self-quarried sand per the measures' 3.2.2 "material cost = sum of (quota consumption x material budget price)", which finally enters the material cost of items like concrete. Recompute the yard price at compilation-period labor and shift prices; the compilation-vs-base difference is booked as a material price difference (measures 3.2.3).

3. Cost boundaries: (1) the work content starts at "partial primary breaking" — raw-feed extraction excluded: feed from tunnel spoil or subgrade surplus needs only loading and haulage; dedicated extraction (blasting/mechanical) is booked per discipline quotas. (2) Where aggregate dirt exceeds the limits of TB 10005-2010 "Code for durability design of railway concrete structures" and washing is needed, apply this chapter's sand-washing and stone-washing items (Chapter 6 note as written).

4. Self-quarried unit price composition: per TB 10801-2024 Clauses 3.2.4 and 3.2.5, the material budget price has three blocks: budget price = (original price + freight-within-price) x (1 + procurement and custody rate). (1) Original price: for self-quarried material, the yard price — labor + plant from the Chapter 6 combined-plant items (compilation-period prices) plus raw-feed acquisition; where one material has several original prices by origin/channel, weight-average by supply shares (TB 10811-2024 Clause 2.2.1). (2) Freight-within-price: the costs of moving material from origin (plant or delivery point) to site that enter the material cost — transport, loading/unloading, and other related charges. (3) Procurement and custody: rates per TB 10811-2024 Table 2.2.2 — sand 4.47%, crushed stone (including ballast and medium/small cobbles) 3.45%, on the base (original price + freight-within-price).

5. Price caliber: sand and stone are Class A materials in TB/T 10813-2024 (base price = original price x (1 + procurement and custody rate)), excluding freight — freight booked separately; where the survey price is at a delivery point (not site), also compute freight-outside-price separately in the item estimate (budget) (TB 10811-2024 Clause 2.2.3). Base prices are 2020-level, ex-deductible-VAT (TB/T 10813-2024 Clause 1.0.3).

Applicable Boundaries

  • Only the railway 2024 system: TB/T 10821-2024, TB 10801-2024, TB 10811-2024, TB/T 10813-2024 (2020 base, ex-deductible-VAT).
  • Only the combined-plant process (integrated crushing-sand-screening); single equipment or other processes should not directly use YY-69~73.
  • The unit 100 m3 is finished aggregate volume, not raw feed or extraction volume.
  • Purchased aggregate does not use Chapter 6 — take base prices or compilation-period survey prices directly.
  • All base prices are 2020-level; recompute at compilation-period prices and book the difference.

Further Reading

  • TB/T 10821-2024 Chapter 6: Section 1 combined-plant items YY-69~73; washing items and conditions in the chapter notes (dirt limits per TB 10005-2010).
  • TB 10801-2024 Section 3.2 material cost (3.2.1-3.2.6).
  • TB 10811-2024 Section 2.2 (2.2.1 weighting; Table 2.2.2 procurement and custody rates; 2.2.2 price rules).
  • TB/T 10813-2024 Clauses 1.0.2-1.0.4 (scope, base level, Class A/B/C composition and formulas) and the aggregate price tables (for judging self-quarry economics against purchase).

Keywords