TB/T 10821-2024 basic quota Chapter 2 formwork pricing: steel/plastic/timber formwork selection, the timber fabrication/erection split (YY-23 + YY-24), amortization conversion, and falsework listed separately
In TB/T 10821-2024 Chapter 2, formwork fabrication-erection and removal units are all 10 m2 (formwork-to-concrete contact area); timber formwork "fabricication" and "erection/removal" are two items — YY-23 bamboo-plywood fabrication + YY-24 timber formwork erection/removal — both must be applied, and YY-23 must be converted to amortized quantity per Chapter 9 (per-use quantity = one-time quantity / amortization count; bamboo plywood 5 uses); the falsework under the formwork is not in Sections 1-3's work content — apply Section 4 auxiliary structures separately (YY-25 timber-structure fabrication with amortization conversion / YY-26 timber-structure erection/removal direct); large steel formwork items apply only to pile caps and spread footings.
Applicable Codes
- TB/T 10821-2024 · Basic Quota of Railway Engineering Ch. 2 模板与辅助结构
- TB/T 10821-2024 Ch. 9 辅助结构材料及半成品摊销
Topic Positioning
The pricing-selection rules for the formwork items of Chapter 2 "formwork and auxiliary structures" of TB/T 10821-2024 "Basic quotas for railway works": how the steel, plastic, and timber formwork families are chosen per actual site use; why timber formwork splits into fabrication and erection/removal (YY-23 + YY-24 — both applied); the fabrication item's mandatory amortization conversion per Chapter 9; and falsework listed separately in Section 4.
Core Conclusions
- Chapter composition (note 1): four families — steel formwork erection/removal, plastic formwork erection/removal, timber formwork fabrication and erection/removal, auxiliary-structure fabrication and erection/removal. Select per the formwork type actually used — not any one of the three.
- Unit (note 2): all formwork fabrication-erection and removal items are per 10 m2 of formwork-to-concrete contact area.
- Falsework separate (note 3): Sections 1-3's work content excludes the falsework under the formwork — apply Section 4 auxiliary structures: YY-25 timber-structure fabrication (per m3) and YY-26 timber-structure erection/removal.
- Large steel formwork (note 4): the large steel formwork items apply to pile caps and spread footings.
- Timber formwork is two items (Section 3): (1) YY-23 bamboo-plywood fabrication, 1,267.81 yuan/10 m2 (labor 395.04, materials 858.32, plant 14.45), content: making boards and backing battens, nailing, trimming, stacking finished product; (2) YY-24 timber formwork erection/removal, 143.70 yuan/10 m2 (labor 142.56, materials 1.14), content: erecting, removing, trimming. Both must be applied.
- Fabrication requires amortization conversion (note 5 as written): "When citing the 'timber formwork fabrication' quota in compiling discipline quotas, compute the amortized quantity from YY-23 per the amortization count; the count and formula are in Chapter 9; YY-24 is cited directly." Likewise (note 6): "for 'timber-structure fabrication', compute from YY-25 per the amortization count... YY-26 is cited directly."
- Amortization formulas (Chapter 9 notes 2 and 3 as written): steel formwork, timber, and other track materials — per-use quantity = one-time quantity / amortization count; assembled steel-formwork accessories and supports, plastic formwork, metal materials — per-use quantity = one-time quantity / count + one-time quantity x site handling and operating wastage rate (rates in Chapter 10); metal parts and piping, rails and turnouts — amortized quantity = total weight x per-erection wastage rate + total weight x annual use rate x years (by quarter, part quarters as whole).
- Timber amortization counts (Chapter 9 Section 3 table): cast-in-place concrete — small-member formwork 5, formwork supports 8, scaffolding 12, bamboo plywood 5; precast small-member formwork 20; sleeper stacks and girder-dragging slides 16; auxiliary packing timber 4. Example: bamboo plywood 10 m2 one-time cost 1,267.81 yuan / 5 uses = about 253.56 yuan per use — convert thus; never book YY-23's base price in full.
Applicable Boundaries
- For the "citing the basic quotas to compile railway discipline quotas" stage; discipline budget quotas usually have the amortization already converted — direct application needs no re-conversion.
- Steel and plastic formwork items exclude fabrication (steel formwork is a turnover material, amortization inside the material cost); only timber formwork has a separate fabrication item (YY-23).
- Falsework is not in Sections 1-3 — apply Section 4 separately; avoid omissions.
- Base prices are 2024 base-period; adjust per the difference rules — not market prices.
- Wastage rates for plastic formwork and steel-formwork accessories/supports are in Chapter 10 (values not in this card's evidence) — consult the original text.
Further Reading
- TB/T 10821-2024 Chapter 2 notes 1-6; Section 3 (YY-23, YY-24); Section 4 (YY-25, YY-26).
- Chapter 9 "amortization of auxiliary-structure materials and semi-finished products", notes 2-3 (formulas) and Section 3 (timber amortization counts); Chapter 10 (metal handling and operating wastage rates).
- General amortization mechanism: the cards "determining turnover-material amortization counts and per-use cost" and "handling mismatches between temporary works/turnover-material amortization and project duration"; applied example: "railway 2024 quota pricing rules for bored-pile steel casings" (the same amortization caliber landed in a discipline volume).