Handling amortization of temporary constructions/turnover materials when the period mismatches the project duration: quotas adapt automatically via amortization counts and quarterly annual rates; accounting uses shorter-of plus period-end net-value carryover
At the quota-pricing level the amortization mechanism has duration adaptation built in, needing no manual adjustment: count-based materials (formwork, timber, scaffolding) directly apply quota contents in budgets, amortization counts do not vary with duration; rate-based equipment (rails and turnouts, metal members, etc.) bills quarterly with fractions of a quarter counted as a full quarter (TB 10811-2024 Table 2.8.2), so longer duration costs more; optical cables and catenary concrete poles amortize 100% regardless of years. At the accounting level, use the shorter of amortization period vs duration; when the amortization period exceeds duration, carry over the remaining net value once into project cost at period end; multi-section shared items are allocated as overheads by criteria.
Applicable Codes
- TB/T 10821-2024 铁路工程基本定额
- TB 10811-2024 铁路基本建设工程设计概(预)算费用定额
- TB 10801-2024 铁路基本建设工程设计概(预)算编制办法
- 企业会计准则(财政部令第5号)第四十八条
Topic Positioning
Rules for handling the mismatch between the amortization period of temporary works and turnover materials and the project duration (project extension, early completion, cross-project transfers): external quota pricing and internal accounting follow two separate logics, and neither needs to be forcibly aligned.
Core Conclusions
At the quota-pricing level (external), the amortization mechanism already has duration adaptation built in: (1) calculation by number of reuses (amortization cycles) (timber, formwork, scaffolding, etc., TB/T 10821-2024 Chapter 9): amortization per use = one-time usage ÷ number of reuses (amortization cycles), and the number of reuses is a value fixed by the quota; budget preparation applies the content directly without duration adjustment, and only cost estimation recalculates by the actual number of turnover cycles; (2) calculation by annual usage rate (rails and turnouts, metal members, piping, poles, etc.): amortization = total weight used × wastage rate per one erection/dismantling + total weight used × annual usage rate × years of use, with the billing unit being the quarter, and any part of a quarter counted as a full quarter (TB 10811-2024 Table 2.8.2) — the longer the duration, the higher the cost, and shortening it reduces the cost automatically; optical cables, catenary concrete poles, and reinforced concrete poles in difficult mountainous areas are amortized at 100% regardless of the number of service years, independent of duration. At the accounting level (internal): when the amortization period exceeds the duration, the remaining net value is carried over once into the project's works cost at the end of the period (or offset against the demolition residual value), keeping the single-project cost complete; when the amortization period is shorter than the duration, no further accrual is made once amortization is complete; temporary works shared across multiple contract sections are treated as on-costs (indirect costs) and allocated to each section's cost according to a certain standard (Accounting Standards for Business Enterprises, Article 48). Cross-project transfers are carried over at book net value, with the receiving project bearing the remaining amortization, so as to avoid understated costs in the transferring project and double charging in the receiving project.
Applicable Boundaries
Applies to the railway pricing calibers (TB 10801/TB 10811/TB/T 10821-2024); that the number of reuses does not vary with duration is a budget-preparation rule, not a cost-accounting rule; accounting amortization years are determined under the enterprise's own policy; it does not apply to the employer's temporary works and site establishment costs (by proportion of works cost or as actually incurred).
Further Reading
TB/T 10821-2024 "Railway Basic (Fundamental) Quota Manual", Chapter 9 Amortization of Auxiliary Structural Materials and Semi-finished Products (including the table of numbers of reuses for timber and the tables of erection/dismantling wastage rates and annual usage rates for metal members and piping); TB 10811-2024 Table 2.8.2 Annual Usage Rates for Construction Equipment (quarterly rounding-up, 100% amortization cases); TB 10801-2024 Section 3.6 Preliminaries, Section 3.8 Heavy Temporary Works and Transitional Works Costs; Accounting Standards for Business Enterprises, Article 48 Allocation of On-costs (Indirect Costs).
Keywords
- 临建摊销
- 周转材料摊销
- 年使用费率
- number of reuses (amortization cycles)
- heavy temporary works
- 工期
- 净值结转
- 施工器材摊销