heavy temporary works
- 01
Handling amortization of temporary constructions/turnover materials when the period mismatches the project duration: quotas adapt automatically via amortization counts and quarterly annual rates; accounting uses shorter-of plus period-end net-value carryover
At the quota-pricing level the amortization mechanism has duration adapt…
TB/T 10821-2024 铁路工程基本定额TB 10811-2024 铁路基本建设工程设计概(预)算费用定额TB 10801-2024 铁路基本建设工程设计概(预)算编制办法2026-09-25 - 02
Compiling railway heavy temporary works and transition works costs: definition, compilation depth, and calculation methods (TB 10801-2024 Section 3.8, TB 10811-2024 Section 2.8)
Heavy temporary works comprise 10 categories (railway diversion lines, t…
TB 10801-2024 铁路基本建设工程设计概(预)算编制办法TB 10811-2024 铁路基本建设工程设计概(预)算费用定额TB 10504-2018 铁路建设项目预可行性研究、可行性研究和设计文件编制办法2026-09-25 - 03
Sizing and cost estimating of project temporary works: the three-way split of minor temporary works / heavy temporary works / employer's temporary works, plus the headcount-index method, capacity back-calculation, and itemized listing
First split temporary works by cost category: minor temporary works are…
TB 10801-2024 铁路基本建设工程设计概(预)算编制办法TB 10811-2024 铁路基本建设工程设计概(预)算费用定额GB 51114-2015 露天煤矿施工组织设计规范2026-09-25 - 04
Pooling and allocating temporary works costs of office/living/production zones: externally merged into preliminaries percentage rates, internally allocated by drivers
External pricing does not "allocate": office, living and small productio…
TB 10801-2024 第3.6节、第3.8节TB 10811-2024 第2.8节SJG 86-2020 第4.4.2条2026-09-25