Sizing and cost estimating of project temporary works: the three-way split of minor temporary works / heavy temporary works / employer's temporary works, plus the headcount-index method, capacity back-calculation, and itemized listing
First split temporary works by cost category: minor temporary works are absorbed into preliminaries (railway = (base-period labour cost + base-period plant and small tools cost) x percentage rate, not listed separately); heavy temporary works are sized and measured item by item applying quota items in line with the project execution plan (construction methodology and site organization) (railway: 10 categories); employer's temporary works are estimated from actual quantities, or at about 1% of works costs where estimation is impracticable. Physical sizing: living and office facilities = peak average headcount x 5~7 m2/person (GB 51114-2015 6.3.8); production facilities by back-calculation from construction intensity or by analogy with experience (6.3.7); railway heavy temporary works itemized (TB 10801-2024 3.8, TB 10811-2024 2.8).
Applicable Codes
- TB 10801-2024 铁路基本建设工程设计概(预)算编制办法
- TB 10811-2024 铁路基本建设工程设计概(预)算费用定额
- GB 51114-2015 露天煤矿施工组织设计规范
- SJG 86-2020 建筑和市政工程估算编制规程
- DB23/T 1318-2020 黑龙江省建设施工现场安全生产标准化实施标准
Topic Positioning
A general framework for estimating temporary works "size + cost": first determine the charging path by the three-way split of minor temporary works / heavy temporary works / employer's temporary works, then choose the sizing algorithm by facility type — headcount-index method (living and office facilities), capacity back-calculation (production facilities), itemized listing (railway heavy temporary works).
Core Conclusions
- Three-way split: minor temporary works costs are included in preliminaries and not listed separately — under the railway regime, preliminaries = (base-period labour cost + base-period plant and small tools cost) x percentage rate, taken by work category x region from the norms for on-costs and expenses (TB 10801-2024, Section 3.6); heavy temporary works have their items, scale and quantities fixed by the project execution plan (construction methodology and site organization) and are priced item by item applying quota items through the single-item estimate (budget) procedure (Section 3.8); employer's temporary works are estimated from actual quantities, or at about 1% of works costs where estimation is impracticable (SJG 86-2020, Clause 4.4.2).
- Living and office facilities: gross floor area (GFA) = average headcount at the construction peak year x per-capita composite index of 5~7 m2/person (GB 51114-2015, Clause 6.3.8), adjustable by construction scale and regional conditions.
- Production facilities (batching plants, rebar processing yards, warehouses, etc.): determined by the project execution plan (construction methodology and site organization) or by analogy with similar works; the core is "first compute construction intensity -> set facility capacity -> convert to land area", with no unified per-capita index (GB 51114-2015, Clause 6.3.7).
- The 10 categories of railway heavy temporary works (railway diversion lines, truck haul roads, girder-transport roads, temporary water supply, power lines >= 6 kV, centralized generation/substations, temporary communication base stations, temporary yards/stations, tunnel wastewater treatment stations, ferry crossings/wharves, etc.), computed item by item from the quantities in the project execution plan (construction methodology and site organization).
Applicable Boundaries
The headcount-index method applies only to estimating living and office facilities; refined checks may reference local-standard floors (offices >= 4 m2/person, dormitories >= 2.5 m2/person and <= 16 persons per room, canteens >= 18 m2, temporary buildings preferably <= 2 storeys). Production facilities must not use the headcount method — they must be back-calculated from construction intensity. The railway 10-category list applies only to the railway regime; building and municipal works have no "heavy temporary works" heading, and minor temporary works follow the local preliminaries regime. Materials borrowed from the permanent works for heavy temporary works are charged with construction wastage, and construction plant and equipment is charged at annual usage rates (rails/turnouts 10%, steel members 16%, etc.).
Further Reading
Railway: TB 10801-2024 "Measures for compiling design estimates (budgets) of railway capital construction projects" Sections 3.6, 3.8; TB 10811-2024 "Norms for on-costs and expenses for design estimates (budgets) of railway capital construction projects" Section 2.8 and Table 2.8.2 (annual usage rates), Tables 2.8.3/2.8.4 (diversion line / haul road maintenance quotas). General: GB 51114-2015 "Code for construction methodology and site organization of open-pit coal mines" Clauses 6.3.7, 6.3.8; SJG 86-2020 "Rules for compiling building and municipal estimates" Clause 4.4.2; refined temporary-building indicators may reference DB23/T 1318-2020 Clause 5.6.4.