Calculating temporary power capacity and temporary water demand on site (demand-coefficient load calculation + itemized water formulas + fire-flow values + pipe diameter)
Temporary power per the demand-coefficient method P-calc = 1.05~1.1 x (K1 x sum-P1/cos-phi + K2 x sum-P2 + K3 x sum-P3 + K4 x sum-P4); with >= 5 equipment items or capacity >= 50 kW a temporary power organization design must be compiled (JGJ/T 46-2024); temporary water Q-total = max(construction + domestic, fire) x 1.10, fire flow per GB 50720-2011 Tables 5.3.5/5.3.6 (mandatory); pipe diameter d = sqrt(4Q/(pi x v x 1000)). Railway caliber: power lines >= 6 kV and water pipes >= 100 mm or >= 2 km go to large temps, otherwise to small temps merged into construction measure fees.
Applicable Codes
- JGJ/T 46-2024
- GBJ 213-90
- GB 50842-2013
- GB 50653-2011
- GB 50720-2011
- TB 10801-2024
- TB 10811-2024
Topic Positioning
Methods for calculating temporary site power supply capacity and temporary water demand on construction sites: demand-coefficient load calculation, transformer capacity selection, itemized water determination and fire-flow values, pipe diameter calculation, and the railway heavy/minor temporary works pricing basis for temporary power lines and water supply pipes.
Core Conclusions
Temporary site power supply: with >= 5 powered equipment items or total capacity >= 50 kW, a temporary site power supply works organization design must be compiled (JGJ/T 46-2024, Clause 10.1.1); load calculation may use the demand-coefficient method (Clause 10.1.2): P-calc = 1.05~1.1 x (K1 x sum-P1/cos-phi + K2 x sum-P2 + K3 x sum-P3 + K4 x sum-P4). Motors K = 0.5~0.7, cos-phi = 0.65~0.75; welders K = 0.5~0.6; indoor lighting K = 0.8; outdoor lighting K = 1.0. Transformer capacity S >= P-calc, plus 10%~20% margin. Temporary water: Q-total = max(construction water + domestic water, fire water) x 1.10 (10% reserve, GBJ 213-90 Clause 2.1.3, GB 50842-2013 Clause 4.1.4, GB 50653-2011 Clause 3.0.7); fire flow is read from mandatory provisions of codes GB 50720-2011 Table 5.3.5 (temporary buildings), Table 5.3.6 (works in progress). Pipe diameter d = sqrt(4Q/(pi x v x 1000)) (m), economic flow velocity 1.5~2.5 m/s. Railway pricing basis: temporary power lines with supply voltage >= 6 kV and water pipes with diameter >= 100 mm or length >= 2 km go into heavy temporary works costs; those below go to minor temporary works, charged in bulk with preliminaries at (base-period labour cost + base-period plant and small tools cost) x rate (TB 10801-2024, Clause 3.8.3, Section 3.6).
Applicable Boundaries
K and cos-phi values are common industry practices (construction handbooks/organization textbooks); standards prescribe the method only, without coefficient tables — in practice the equipment nameplate list governs; specific fire-flow values must be read from the current code edition; the railway heavy/minor temporary works treatment applies only to railway estimates and budgets compilation, not to general building, municipal, or mining projects.
Further Reading
JGJ/T 46-2024 Clauses 10.1.1, 10.1.2; GBJ 213-90 Clause 2.1.3, GB 50842-2013 Clause 4.1.4, GB 50653-2011 Clause 3.0.7; GB 50720-2011 Clauses 5.3.5, 5.3.6 (mandatory provisions of codes); railway basis see TB 10801-2024 Section 3.8, TB 10811-2024 Section 2.8.
Keywords
- temporary site power supply
- 需要系数法
- 负荷计算
- 临时用水
- 施工用水量
- 消防用水量
- 管径计算
- 临时电力线
- 给水管路