Four-step method for selecting temporary power transformer capacity on site: load calculation -> apparent power -> load-rate amplification -> nearest standard capacity step
Four selection steps: (1) compute P-calc by the demand-coefficient method; (2) S-calc = P-calc / cos-phi-overall (cos-phi 0.7~0.85); (3) S-transformer = S-calc / Kf (Kf 0.80~0.90); (4) take the next step up in the standard series 100/125/160/200/250/315/400/500/630 kVA. Post-selection checks: > 100 kVA working grounding resistance <= 4 ohm, <= 100 kVA <= 10 ohm; TN-S three-level distribution with two-level residual current protection; three-phase loads preferably balanced; effective supply radius preferably <= 500 m; transformer placed at the load center.
Applicable Codes
- JGJ/T 46-2024 建筑与市政工程施工现场临时用电安全技术标准
- GB/T 50481-2019
- GB/T 50484-2019
Topic Positioning
The general four-step calculation method for selecting temporary power transformer capacity on construction sites, and the post-selection checks — applicable to the transformer selection step of temporary power organization design for building, municipal, railway, and other works.
Core Conclusions
Four selection steps: (1) Load calculation — compute the calculated active power P-calc by the demand-coefficient method (JGJ/T 46-2024, Clause 10.1.2 explicitly allows this method); (2) Convert to apparent power — S-calc = P-calc / cos-phi-overall, the composite power factor generally 0.7~0.85 (lower with high motor and welder shares; above 0.9 after centralized reactive compensation); (3) Amplify by load rate — S-transformer = S-calc / Kf, where Kf is the transformer economic load rate, generally 0.80~0.90; (4) Take the next step up in the standard capacity series: 100/125/160/200/250/315/400/500/630 kVA..., stepping one further up if capacity expansion is possible during construction. Hard post-selection checks: for a single unit (or total of parallel units) > 100 kVA, working grounding resistance <= 4 ohm; <= 100 kVA, <= 10 ohm; TN-S system three-level distribution, two-level residual-current protection; three-phase loads preferably balanced; effective supply radius preferably <= 500 m (petrochemical industry standard, generally referenced by sites); the transformer should sit at the load center of the supply area or near large loads. Where peak load is large or power points are scattered, multiple transformers with staged commissioning are preferable to reduce no-load losses.
Applicable Boundaries
Applies to initial transformer selection by peak construction load. Demand coefficients, power factors, and load rates are common engineering calibers — JGJ/T 46-2024 prescribes the method without coefficient tables; the equipment nameplate list and site conditions ultimately govern. Not applicable to permanent power distribution or substation design. Sites with >= 5 powered equipment items or total capacity >= 50 kW must compile a temporary power organization design (Clause 10.1.1), where transformer selection is step 5 — capacity statistics and load calculation must be completed first.
Further Reading
JGJ/T 46-2024 "Standard for safety of temporary electric power on construction sites of buildings and municipal works" Clauses 10.1.1, 10.1.2 (organization design conditions and content), Clause 3.1.1 (distribution system), Clause 3.5.1 (working grounding resistance); transformer apparent power as calculated load divided by load rate see GB/T 50481-2019 Appendix H; supply-radius limits see GB/T 50484-2019 Clause 4.2.1.
Keywords
- temporary site power supply
- 变压器容量
- 变压器选型
- 需要系数法
- 负荷计算
- 视在功率
- 功率因数
- 临时用电工程组织设计