GB/T 50484-2019 temporary power on petrochemical sites: TN-S earthing system and four/three/two-tier distribution with "residual-current protection at every tier" (Clause 4.1.1)
Per GB/T 50484-2019 Clause 4.1.1: (1) low-voltage three-phase four-wire systems with directly earthed neutral shall use the TN-S system (protective nulling; five-wire L1/L2/L3+N+PE); (2) distribution tiers by project scale - four-tier (distribution board -> main distribution box -> sub distribution box -> switch box) or three-tier (main -> sub -> switch), two-tier also allowed for small projects; (3) "residual-current protection at every tier". With on-site generator sets: neutral directly earthed with an independent TN-S nulling system (GB 50484-2008 Clause 4.2.15).
Applicable Codes
- GB/T 50484-2019 · Standard for Construction Safety Technology of Petrochemical Engineering Projects 第 4.1.1 条
- GB 50484-2008 · Code for Construction Safety Technology of Petrochemical Engineering Projects 第 4.2.15 条
- JGJ 46 · Technical Code for Safety of Temporary Electrification on Construction Sites
- GB 50194 · Code for Safety of Electric Power Supply and Consumption at Construction Sites
- GB 14050 · Types and Safety Technical Requirements of System Earthing
Topic Positioning
Core provisions of GB/T 50484-2019 "Standard for construction safety technology of petrochemical engineering construction" on site temporary power: TN-S earthing (protective nulling), distribution tiers by project scale (four/three/two), and residual-current protection at every tier, plus the independent TN-S requirement for on-site generators - for temporary-power plans, safety checks, and compliance review on petrochemical sites.
Core Conclusions
Clause 4.1.1 ("temporary power and temporary works" chapter), key sentences: "In temporary power works on site, low-voltage three-phase four-wire systems with directly earthed neutral shall adopt the TN-S system. Temporary power should, per project scale, adopt a four-tier or three-tier distribution system with 'residual-current protection at every tier'."
Commentary points (numbers and terms as in the original):
- Earthing type: TN-S = protective nulling - bonding equipment enclosures to the protective null conductor with overcurrent protection on the supply side. On a frame-to-enclosure fault, a large line-to-PE single-phase short circuit rapidly trips the protection - converting a "frame fault" into a "single-phase short circuit". Safer and more reliable than TT; consistent with JGJ 46 "Code for safety of temporary electrification on construction site". Wiring is five-wire (L1/L2/L3 + N + PE).
- Tiers: given petrochemical site power loads, most sites use four tiers - distribution board (from an independent substation or kiosk) -> main distribution box -> sub distribution box -> switch box - with equipment fed from tier-3 sub boxes or tier-4 switch boxes; smaller projects use three tiers (main -> sub -> switch); two tiers are allowed for small projects. Too many tiers complicate selective relay settings; too few cannot meet supply needs - configure per actual demand.
- "Residual-current protection at every tier": site faults often produce small earth-fault residual currents (damp equipment, overload, long lines, aging insulation) too small to trip overcurrent protection quickly; such persistent faults seriously threaten workers, so every tier needs residual-current devices more sensitive than nulling protection. Nulling plus residual-current protection together greatly improves safety over the older earthing-only approach.
On-site generator supply (GB 50484-2008 Clause 4.2.15, carried forward; clause number per current edition): "The generator set shall directly earth its neutral and set up an independent TN-S nulling protection system" - to prevent unbalanced neutral currents affecting the external grid; the earthing system shall be independent.
Version note: current is GB/T 50484-2019 (recommended); the old GB 50484-2008 (mandatory) said temporary power "should use a four-tier distribution system"; the 2019 edition relaxes to tier choice by project scale - plans and checklists must follow the current edition.
Applicable Boundaries
- Scope: temporary power on petrochemical construction sites (Chapter 4), covering open-air, damp, high-turnover high-risk environments.
- Difference vs. building-sector rules: JGJ 46 prescribes "three-tier distribution + two-tier residual-current protection"; GB/T 50484-2019 requires protection at every tier (stricter) and allows a fourth tier (distribution board) for large projects.
- Covers earthing type and tier count only; transformer capacity, load calculations, and temporary water are in the cited cards.
- Actual configurations should also follow GB 50194 "Code for safety of power supply and consumption at construction site" and site demand.
Further Reading
- GB/T 50484-2019 Chapter 4, Clause 4.1.1 and commentary (TN-S, tier configuration, principle of per-tier residual-current protection).
- GB 50484-2008 Clause 4.2.15 (generator neutral earthing and independent TN-S; commentary cites GB 14050 "Types and safety requirements of system earthing").
- Related clauses (numbers per current edition): PE conductors of equipment shall not be chained; tower cranes, gantry cranes, and hoists shall re-earth their PE conductors.
- Comparison: JGJ 46 (three-tier, two-tier protection); GB 50194 (tier principles).