GB/T 50484-2019 Clause 3.3.4: distance limits (30m / 15m / 10m) on flammable gas / liquid venting and cross operations around hot-work points

Before hot work in petrochemical construction: no flammable gas may be vented within 30m of the hot-work point, no flammable liquid discharged within 15m, and no simultaneous cross operations such as flammable-solvent cleaning or spray painting within 10m; combustible and flammable materials shall be cleared from the site before hot work (GB/T 50484-2019 Clause 3.3.4).

Applicable Codes

  • GB/T 50484-2019 石油化工建设工程施工安全技术标准
  • GB/T 51474-2025 城镇燃气设施抢修技术标准

Topic Positioning

This card explains the quantified distance limits (30m / 15m / 10m) of Clause 3.3.4 of GB/T 50484-2019 "Standard for construction safety technology of petrochemical engineering" on flammable gas / liquid venting and cross operations around hot-work points, for hot-work safety control and site checks during petrochemical construction.

Core Conclusions

Per the original text of GB/T 50484-2019 Clause 3.3.4:

Before hot work, combustible and flammable materials shall be cleared from the site; no flammable gas may be vented within 30m of the hot-work point, no flammable liquid discharged within 15m, and simultaneous cross operations such as flammable-solvent cleaning or spray painting are prohibited within 10m.

The three distance parameters:

Range Prohibition
Within 30m of hot-work point No venting of flammable gas
Within 15m of hot-work point No discharge of flammable liquid
Within 10m of hot-work point No simultaneous cross operations (flammable-solvent cleaning, spray painting, etc.)

Companion requirement (Clause 3.3.5 of the same standard): before hot work, valve pits, sewer manholes, drainage facilities, and trenches around or below the hot-work point shall be inspected, with gas detection / analysis and sealing measures taken.

Applicable Boundaries

  • Applies to general hot-work safety provisions in petrochemical construction, not limited to particular units or operations.
  • Version difference: the old GB 50484-2008 "Code for construction safety technology of petrochemical engineering" Clause 3.3.4 only provided "fire shall not be used near combustible / flammable materials before measures are taken" without the 30m / 15m / 10m figures - the quantified limits are new in the 2019 edition; the current edition is GB/T 50484-2019 (changed from mandatory GB to recommended GB/T).
  • Town-gas facility emergency repair has GB/T 51474-2025 Clause 4.3.4: "flammable gas should not be vented within 30m of the hot-work point during operations" - consistent on gas distance; the flammable-liquid 15m remains per GB/T 50484-2019.

Further Reading

See Chapter 3 "general provisions", Section 3.3 hot-work clauses of GB/T 50484-2019 "Standard for construction safety technology of petrochemical engineering" (Clause 3.3.4 distance limits; Clause 3.3.5 inspection of valve pits, sewer manholes, drainage facilities, and trenches, gas detection / analysis, and sealing). Town-gas emergency-repair hot work: GB/T 51474-2025 Clause 4.3.4.