Attribution of demolition and restoration costs of temporary works: contractor minor/heavy temporary works included in preliminaries, employer's temporary works excluded (demolition cleanup belongs to site preparation costs)
The contractor's temporary works demolition and restoration costs are already within the preliminaries scope: minor temporary works are included in the minor temporary works cost (applied as a percentage-rate lump sum, TB 10801-2024 Clause 3.6.2), and the definitions of heavy temporary works and transition works costs already include 'construction and demolition/restoration' (Clauses 3.8.1/3.8.2) — they are neither separately billed items nor subject to double charging; employer temporary works and site establishment costs cover only construction, maintenance, rental and use, excluding demolition/restoration, with demolition cleanup under site preparation costs (e.g., SJG 86-2020 Clause 4.4.2); for rebuilding and expansion projects, generally only demolition cleanup is charged.
Applicable Codes
- TB 10801-2024 铁路基本建设工程设计概(预)算编制办法
- TB 10811-2024 铁路基本建设工程设计概(预)算费用定额
- SJG 86-2020 建筑和市政工程估算编制规程
Topic Positioning
This card answers 'should demolition and restoration costs of temporary works be included in preliminaries and listed as a separate item', giving the cost attribution of the three categories — contractor minor temporary works, contractor heavy temporary works, and employer temporary works and site establishment — under railway and building/municipal pricing bases, with points on preventing double charging.
Core Conclusions
- Contractor minor temporary works: demolition and restoration are already included in construction preliminaries. TB 10801-2024 Clause 3.6.2 places 'erection, relocation, maintenance, amortisation, and demolition/restoration of minor temporary works' within the minor temporary works cost, calculated as a percentage-rate lump sum on (base-period labour cost + base-period plant and small tools cost), not listed as a separate item. 2) Contractor heavy temporary works and transition works: the very definitions of heavy temporary works costs and transition works costs include 'construction and demolition/restoration' (Clauses 3.8.1, 3.8.2); applying quota items to quantities determined by the project execution plan already includes demolition and restoration — an extra 'demolition fee' must not be charged. 3) Employer temporary works and site establishment costs: cover only costs incurred or amortised for construction, maintenance, rental and use, excluding demolition/restoration; demolition cleanup costs belong to site preparation costs (SJG 86-2020 Clause 4.4.2), and rebuilding and expansion projects generally charge demolition cleanup only. 4) Practical warnings: no double billing under any of the three attribution bases; exceptions (employer-demanded changes to temporary works schemes, handover standards above normal such as reclamation or restoration to original greening) beyond the percentage-rate lump sum may be charged separately or made the subject of a claim.
Applicable Boundaries
Applies to railway estimates and budgets (China Railway system) (TB 10801-2024, TB 10811-2024) and to building/municipal pricing that charges temporary works and site establishment costs as a percentage-rate lump sum; the exact scope of temporary works and site establishment costs within building/municipal mandatory health, safety and environmental (HSE) provisions follows provincial norms for on-costs and expenses. Note 'excluding demolition/restoration' applies only to employer temporary works and site establishment costs — the contractor's demolition/restoration is already within percentage rates or quota norms. Demolition and restoration are compliance obligations (the site shall be cleaned and restored after completion) and must not be skipped just because rates include them.
Further Reading
See TB 10801-2024 Clause 3.6.2 (composition of construction preliminaries), Clauses 3.8.1~3.8.2 (definitions of heavy temporary works/transition works costs), TB 10811-2024 Section 2.8 (calculation procedures for heavy temporary works, construction loss of borrowed materials, annual usage percentage rates of construction plant and materials, quota norms for maintenance of diversion lines/haul roads); employer temporary works and site establishment cost attribution bases cross-checked against the engineering cost terminology standard and local estimate rules (e.g., SJG 86-2020 Clause 4.4.2 site preparation costs).
Keywords
- 临建拆除恢复费
- minor temporary works cost
- 大型临时设施费
- 过渡工程费
- 建设单位临时设施费
- 场地准备费
- preliminaries
- 拆除清理费