Preliminaries is the Chinese cost category (措施项目费) covering expenditure incurred before and during construction for works that do not form part of the permanent Works — site establishment, temporary works, scaffolding, vertical transport, and safety and environmental protection.

Under GB 50500 (GB 50500-2013; GB/T 50500-2024) preliminaries are scheduled in a separate bill and priced item by item, in two groups. Unit-rate preliminary items are measurable and take an all-in unit rate (scaffolding, vertical transport, major plant mobilisation). Lump-sum preliminary items are calculated at a prescribed percentage rate (mandatory health, safety and environmental (HSE) provisions, night work, double handling).

The decisive institutional feature is that the mandatory HSE provisions are non-competitive: a tenderer may not discount them or trade them away, and they must be assessed in full on the prescribed basis and rate. Safety, health and environmental spending is thereby ring-fenced from price competition. The remaining items are priced at the bidder's discretion, though certain rates carry mandatory floors. Settlement follows the contract form: under a re-measurable (unit-rate) contract the measured items adjust against actual measurement, while lump-sum preliminaries are generally taken as a fixed amount.

FIDIC Mapping

Related terms: bill of quantities (BOQ); all-in unit rate; re-measurable (unit-rate) contract.

The mapping is adjacent rather than equivalent, on three structural points. Infrastructure: the FIDIC Red Book defines the Bill of Quantities as the document so entitled included in the Schedules (Sub-Clause 1.1.5), prepared by the Employer's advisers from the Drawings and Specification and containing estimated quantities of the work; preliminaries normally sit inside that document as a packaged section, whereas China schedules and prices preliminary items as a separate bill. Decision-making: in FIDIC the preliminaries package is priced by the Contractor at its own discretion, while China imposes mandatory floors and removes the HSE element from competition altogether. Procedure: valuation under FIDIC runs through measurement and the Engineer's certification (Red Book Clause 12), whereas China applies scheduled item pricing at prescribed rates.

Usage note: because part of the Chinese category is separately scheduled and non-competitive, the English term preliminaries should always be qualified with that institutional note; it is not simply an open competitive package.

Chinese TermEnglish TermFIDIC TermRelationNotes
措施项目费preliminariesBill of Quantities (红皮书 Sub-Clause 1.1.5;黄皮书 2017 主文不使用该词)adjacentFIDIC 无同名费用科目:preliminaries 打包列入工程量清单,由承包商整体自主报价;中国另设措施项目清单,分单价与总价两类计取,安全文明施工费不可竞争。
安全文明施工费mandatory health, safety and environmental (HSE) provisionsContractor's priced preliminaries (no corresponding non-competitive item)distinctFIDIC 未设不可竞争费机制,安全与环保义务通常由承包商在 preliminaries 内自报并承担;中国以强制计价基础和费率下限将该费用隔离在价格竞争之外,制度性质不同。
措施项目preliminary itemspreliminaries (priced within the Bill of Quantities)adjacent国际工程量清单无与中国措施项目完全对应的科目,相关内容散入 preliminaries 各章节,故二者只宜视为近缘科目而非等同概念。