preliminaries
Concept Guide
Concept
Preliminaries is the Chinese cost category (措施项目费) covering expenditure incurred before and during construction for works that do not form part of the permanent Works — site establishment, temporary works, scaffolding, vertical transport, and safety and environmental protection.
Under GB 50500 (GB 50500-2013; GB/T 50500-2024) preliminaries are scheduled in a separate bill and priced item by item, in two groups. Unit-rate preliminary items are measurable and take an all-in unit rate (scaffolding, vertical transport, major plant mobilisation). Lump-sum preliminary items are calculated at a prescribed percentage rate (mandatory health, safety and environmental (HSE) provisions, night work, double handling).
The decisive institutional feature is that the mandatory HSE provisions are non-competitive: a tenderer may not discount them or trade them away, and they must be assessed in full on the prescribed basis and rate. Safety, health and environmental spending is thereby ring-fenced from price competition. The remaining items are priced at the bidder's discretion, though certain rates carry mandatory floors. Settlement follows the contract form: under a re-measurable (unit-rate) contract the measured items adjust against actual measurement, while lump-sum preliminaries are generally taken as a fixed amount.
FIDIC Mapping
Related terms: bill of quantities (BOQ); all-in unit rate; re-measurable (unit-rate) contract.
The mapping is adjacent rather than equivalent, on three structural points. Infrastructure: the FIDIC Red Book defines the Bill of Quantities as the document so entitled included in the Schedules (Sub-Clause 1.1.5), prepared by the Employer's advisers from the Drawings and Specification and containing estimated quantities of the work; preliminaries normally sit inside that document as a packaged section, whereas China schedules and prices preliminary items as a separate bill. Decision-making: in FIDIC the preliminaries package is priced by the Contractor at its own discretion, while China imposes mandatory floors and removes the HSE element from competition altogether. Procedure: valuation under FIDIC runs through measurement and the Engineer's certification (Red Book Clause 12), whereas China applies scheduled item pricing at prescribed rates.
Usage note: because part of the Chinese category is separately scheduled and non-competitive, the English term preliminaries should always be qualified with that institutional note; it is not simply an open competitive package.
| Chinese Term | English Term | FIDIC Term | Relation | Notes |
|---|---|---|---|---|
| 措施项目费 | preliminaries | Bill of Quantities (红皮书 Sub-Clause 1.1.5;黄皮书 2017 主文不使用该词) | adjacent | FIDIC 无同名费用科目:preliminaries 打包列入工程量清单,由承包商整体自主报价;中国另设措施项目清单,分单价与总价两类计取,安全文明施工费不可竞争。 |
| 安全文明施工费 | mandatory health, safety and environmental (HSE) provisions | Contractor's priced preliminaries (no corresponding non-competitive item) | distinct | FIDIC 未设不可竞争费机制,安全与环保义务通常由承包商在 preliminaries 内自报并承担;中国以强制计价基础和费率下限将该费用隔离在价格竞争之外,制度性质不同。 |
| 措施项目 | preliminary items | preliminaries (priced within the Bill of Quantities) | adjacent | 国际工程量清单无与中国措施项目完全对应的科目,相关内容散入 preliminaries 各章节,故二者只宜视为近缘科目而非等同概念。 |
Updated 2026-09-13
- 01
Content and pricing methods of preliminaries: the 2024 definition (clause 2.0.3), the listing basis (GB/T 50854-2024 annex R table R.1.1 preliminary items, code 011601), the three pricing methods of unit rate / lump sum / percentage rate and their preferred use (clauses 2.0.10 to 2.0.12, 3.2.1), the completion rules of annex E tables E.3.1 to E.3.4, and the non-competitive rule for statutory safety provisions (clause 3.2.5)
Preliminaries are 'project costs incurred in taking the relevant measure…
GB/T 50500-2024 第 2.0.3 条(措施项目术语)GB/T 50500-2024 第 2.0.10~2.0.12 条(单价计价/总价计价/费率计价)GB/T 50500-2024 第 3.2.1 条(措施项目清单计价方式)2026-11-01 - 02
The charging base of the winter and rainy season construction addition (norm labour, or labour plus plant), deciding the winter construction season, rate-based lump-sum charging versus special measures (warm-shed method, steam curing) priced on approved schemes and records, and the no-double-count rule against the night-work addition
Under the building and municipal basis the winter / rainy season additio…
JGJ/T 104-2011 · Specification for Winter Construction of Building Engineering 第1.0.3条GB/T 50875-2013 · Standard glossary of project costs 第2.2.55条GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第3.3.7条、Ch. 82026-10-28 - 03
Quota application for the erection cost of vertical storage tanks (metal oil tanks) built by the reverse jack-up method with hydraulic lifting: line-item selection by construction form and capacity class, measurement by shell metal weight in t, lifting gear and temporary stiffening to preliminaries, and NDT and the water filling test charged separately
The reverse jack-up method has no standalone line item in the erection c…
DB11/T 2382-2024 · Standard for Construction Consumption of Construction Works (Beijing) 第 6.3 章 静置设备与工艺金属结构制作安装工程(6.3.1~6.3.7、6.3.23~6.3.29)及App. C.3(Table C.3.16-1、C.3.16-2、C.3.17-1、C.3.17-2、C.3.17-3)GB/T 50856-2024 · Standard for measurement of general mechanical, electrical, plumbing and fire services App. C Table C.2.1(编码 030302)金属油罐制作安装GB 50128-2014《立式圆筒形钢制焊接储罐施工规范》第 5.4.2 条、第 7.4.1 条2026-10-26 - 04
Contract price adjustment caused by missing items in the tender bill of quantities: the clause chains of the three entries of GB 50500-2013 section 9.5 (9.5.1 to 9.3.1, 9.5.2 / 9.5.3 to 9.3.2), the four-tier valuation of all-in unit rates for new divisional and sub-divisional works items, the three-tier determination of new preliminaries, the itemisation test between unit-rate and lump-sum preliminaries, and the distinction from the quantity-deviation preliminaries linkage trigger path of clause 9.6.3
GB 50500-2013 splits 'missing BOQ items' into three mutually non-substit…
GB 50500-2013 第9.5.1条GB 50500-2013 第9.5.2条GB 50500-2013 第9.5.3条2026-10-25 - 05
Effect of signed-off interim settlements by construction stage on the final account: the no-re-measurement and no-re-pricing principle, statutory exceptions that can overturn it, submission and deemed-approval rules for late response, and a clause comparison linking the two settlements (GB/T 50500-2024 + Cai Jian [2022] No. 183)
Except that preliminaries and main contractor's attendance and coordinat…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第7.1.5~7.1.8、8.11.22、10.2.3、10.2.4、10.2.7、10.2.8、10.3.1、10.3.3、10.3.5、10.3.8、10.3.12、10.3.16条《财政部 住房和城乡建设部关于完善建设工程价款结算有关办法的通知》(财建〔2022〕183号)第二条http://czj.pingliang.gov.cn/zfxxgk/fdzdgknr/lzyj/sjzc/art/2022/art_64fff948f92c4e7890840e739d50d0e9.html2026-10-25 - 06
Within preliminaries: the composition, charging method and calculation bases of mandatory HSE provisions (statutory safety provisions), temporary works and site establishment costs, and the additional cost of night work, compared; plus the clause basis of the non-competitive status of mandatory HSE provisions and the item listing rules
Mandatory HSE provisions comprise four heads - environmental protection…
GB/T 50500-2024 建设工程工程量清单计价标准 第2.0.4条、第3.2.5条GB 50722-2011 城市轨道交通建设项目管理规范 第5.2.9条GB/T 50875-2013 工程造价术语标准 第2.2.52条、第2.2.53条2026-10-25 - 07
Sources, bases and regional treatment of night-work additional cost rates: highways under JTG 3830-2018 Table 3.1.6-3 as a separate item; railways folded into the composite construction-measures rate of TB 10811-2024 Table 2.6.1 (16 works classes x regions 1-8); building and municipal works per provincial fee norms on base x rate
No unified national rate exists for night-work additional cost; the taki…
TB 10801-2024 · Measures for Compilation of Design Estimates and Budgets of Railway Capital Construction Projects 第3.6.1~3.6.4条TB 10811-2024 · Fee schedule for design estimates and budgets of capital railway works 第2.6.1条、Table 2.6.1、App. BJTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第3.1.6条第3款、Table 3.1.6-32026-10-18 - 08
Composition differences between interim settlement by construction stage and the final account: stage settlement on three elements plus a five-item payment application, the final account on 13 listed items (GB/T 50500-2024 clauses 10.2 / 10.3)
Interim settlement by stage prices at settlement nodes: its composition…
GB/T 50500-2024 建设工程工程量清单计价标准 第2.0.13、2.0.34、2.0.35条GB/T 50500-2024 第10.2.1、10.2.3、10.2.5、10.2.6、10.2.7、10.2.10条GB/T 50500-2024 第10.3.1、10.3.2、10.3.3、10.3.4、10.3.15条2026-10-18 - 09
The non-adjustment boundary of material price adjustment: the eight cost classes never adjusted for price moves, the BOQ items outside routine adjustment, and the negotiated handling of abnormal fluctuation (GB/T 50500-2024 clauses 8.7.3 / 8.7.5 / 8.7.6)
GB/T 50500-2024 clause 8.7.6 lists eight classes never adjusted for pric…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第3.3.5条、第3.3.6条、第8.7.2条、第8.7.3条、第8.7.5条、第8.7.6条2026-10-18 - 10
The definition of preliminaries and its two charging bases: measurable preliminaries (priced like divisional-work costs) and comprehensively charged preliminaries (a rate on divisional-work costs plus measurable preliminaries)
Preliminaries defined (GB/T 50500-2024 clause 2.0.3): the costs of the t…
GB/T 50500-2024 第2.0.3条GB/T 50500-2024 第3.2.1条GB/T 50500-2024 第10.3.3条2026-09-30 - 11
Railway estimate/budget haul-road cost classification: the dividing standard between heavy temporary works and minor temporary works (preliminaries) (TB 10801-2024 Clause 3.6.2 vs. Clause 3.8.3)
Whether a railway temporary haul road is charged to heavy temporary work…
TB 10801-2024 · Measures for Compilation of Design Estimates and Budgets of Railway Capital Construction Projects 第3.6.2条、第3.6.3条、第3.8.3条、第3.8.4条、第3.8.7条、App. ATB 10811-2024 · Fee schedule for design estimates and budgets of capital railway works2026-09-25 - 12
Settlement where a design change reduces the quantities: adjustment rules for unit-rate and lump-sum contracts, compensation for outright cancellation of an item, and the linkage of preliminaries
The settlement principle for reduced quantities is "re-measure against t…
GB/T 50500-2024 建设工程工程量清单计价标准T/ZBD 100.5-2023 建设工程结算审核作业指引2026-09-25 - 13
Checking tender prices for omitted taxes and duties, statutory levies and fees, and preliminaries (edition basis → tax back-calculation → levy rates → preliminaries comparison)
Four-step check for omitted taxes and duties / statutory levies and fees…
GB/T 50500-2024 建设工程工程量清单计价标准GB 50722-2011 城市轨道交通建设项目管理规范DB37/T 5161-2020 建设工程造价数据交换及应用标准2026-09-25 - 14
Charging the cost of fine-decoration show flats (model rooms): classifying by nature to determine the cost-attribution path (process → measure costs / delivery → divisional works / display → other-item costs or separate award)
Show-flat costs are charged by first classifying nature, then setting th…
GB 50210-2018 建筑装饰装修工程质量验收标准GB/T 50500-2024 建设工程工程量清单计价标准GB/T 50875-2013 工程造价术语标准2026-09-25 - 15
Estimating and apportioning the protection-of-finished-work cost (protection cost of completed works and equipment): two paths — the percentage-rate method and the actual-cost method
The protection-of-finished-work cost belongs to preliminaries (GB/T 5050…
GB/T 50500-2024GB/T 50875-2013JGJ/T 427-20182026-09-25 - 16
Costing temporary access roads (temporary bridges) during road construction: preliminary items listing and three rate build-up paths
Temporary access roads are preliminaries: municipal works list them as "…
GB/T 50857-2024 市政工程工程量计算标准JTG/T 3832-2018 公路工程预算定额GB/T 50903-2013 市政工程施工组织设计规范2026-09-25 - 17
Preliminaries bid at zero - can an increase be claimed at final account? (principle-plus-exception framework, with clarification of Clause 10.3.3)
Ordinary preliminaries bid at zero constitute a lump-sum price and are n…
GB/T 50500-2024 建设工程工程量清单计价标准(第3.2.5、3.3.7、6.1.5、6.2.3、6.2.6、7.3.1、7.4.4、10.3.3条)TB 10801-2024(铁路口径安全生产费,第3.11.11条)2026-09-25 - 18
Railway estimate/budget preliminaries and on-costs (indirect costs): composition, calculation base, and percentage rates (TB 10801-2024 Clauses 3.6/3.9; TB 10811-2024 Table 2.9.1)
Preliminaries (7 items: winter (cold-weather) and rainy-season construct…
TB 10801-2024 · Measures for Compilation of Design Estimates and Budgets of Railway Capital Construction Projects 第2.6、3.6、3.9条TB 10811-2024 · Fee schedule for design estimates and budgets of capital railway works 第2.9节Table 2.9.12026-09-25 - 19
Attribution of demolition and restoration costs of temporary works: contractor minor/heavy temporary works included in preliminaries, employer's temporary works excluded (demolition cleanup belongs to site preparation costs)
The contractor's temporary works demolition and restoration costs are al…
TB 10801-2024 铁路基本建设工程设计概(预)算编制办法TB 10811-2024 铁路基本建设工程设计概(预)算费用定额SJG 86-2020 建筑和市政工程估算编制规程2026-09-25 - 20
Whether purchased materials enter the bases to which percentage rates are applied for preliminaries and overheads (company and site) in highway preliminary estimates (budgets): the ministry JTG 3830-2018 base system and local exclusion rules (Qinghai DB63/T 2011-2022, Beijing DB11/T 1509-2018)
The ministry JTG 3830-2018 does not itemize exclusions of purchased mate…
JTG 3830-2018 公路工程建设项目概算预算编制办法DB63/T 2011-2022 公路养护工程预算编制指南DB11/T 1509-2018 公路工程设计导则2026-09-25 - 21
Charging night-work and sectional-construction additional fees: percentage-rate and measured-quantity frameworks
Night-work additional fee = night-shift allowance + nighttime efficiency…
GB/T 50875-2013 工程造价术语标准SJG 84-2020 市政维修工程消耗量标准TB 10801-2024 铁路基本建设工程设计概(预)算编制办法2026-09-25 - 22
Highway 2018 quota system profit: base = quota direct costs + measures + enterprise management, rate 7.42% (JTG 3830-2018 clause 3.1.9)
Per clause 3.1.9 of JTG 3830-2018 "Measures for compiling estimates and…
JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第 3.1.9 条、第 3.1.10 条2026-09-25 - 23
Work safety levy for non-railway works (building / municipal / highway / water conservancy): accrual basis, non-competitive nature, and ring-fenced use rules
Building/municipal: the mandatory health, safety and environmental (HSE)…
JTG 3830-2018 公路工程建设项目概算预算编制办法GB/T 50500-2024 建设工程工程量清单计价标准GB 50722-2011 城市轨道交通建设项目管理规范2026-09-25 - 24
Cost attribution and estimation of temporary hoarding, gates, and wheel-wash facilities on site (basis of mandatory health, safety and environmental (HSE) provisions)
Hoarding, gates, and wheel-wash facilities belong respectively to the si…
TB 10801-2024 铁路基本建设工程设计概(预)算编制办法TB 10811-2024 铁路基本建设工程设计概(预)算费用定额DB64 680-2018 建筑工程安全管理规程2026-09-25 - 25
Railway construction-installation single-item estimate calculation program (TB 10801-2024 Table 2.6.2): 16-step accumulation and percentage-rate base rules — labor + machinery in the base; materials / out-of-price freight / price differences / fill material out; VAT separately listed
The single-item estimate for cost of works (construction and installatio…
TB 10801-2024 · Measures for Compilation of Design Estimates and Budgets of Railway Capital Construction Projects 第2.6节(图2.6.1、Table 2.6.2、Table 2.6.3)、第3.4节、第3.12条TB 10811-2024 · Fee schedule for design estimates and budgets of capital railway works2026-09-25 - 26
Risk allocation and adjustment rules for preliminaries (measure) costs: GB 50500-2013 vs GB/T 50500-2024 (omitted items, scheme changes, lump sum plus exceptions)
The 2024 edition restructures preliminaries as "lump sum plus exceptions…
GB 50500-2013 建设工程工程量清单计价规范(第4.1.2、9.3.1~9.3.2、9.5.3条,已废止)GB/T 50500-2024 建设工程工程量清单计价标准(第3.1.8、3.3.3、3.3.7、6.1.5、7.3.1、8.2.2~8.2.3、8.9.4~8.9.7条)2026-09-25 - 27
Three bases for the composition of the construction price: cost elements, BOQ-based pricing, and final-account listing
The construction price (cost of works (construction and installation)) h…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 50875-2013 工程造价术语标准2026-09-25 - 28
Overheads (company and site) within the all-in unit rate vs. site management fee within lump-sum preliminaries: distinction and prevention of duplicate charging
Overheads (company and site) are on-costs (indirect costs) in nature and…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 50875-2013 工程造价术语标准TB 10801-2024 铁路基本建设工程设计概(预)算编制办法2026-09-25 - 29
In-process settlement linked to final account: preliminaries and main-contract service fees are interim payments that must be recalculated at final settlement (GB/T 50500-2024 Clauses 10.2.3/10.2.7/10.3.3)
For projects with in-process settlement, preliminaries costs (and main-c…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第10.2.3、10.2.7、10.3.3、7.3.1条GB 50500-2013 · Code of Valuation with Bill Quantity of Construction Works (已废止,仅对照)第11.2.2、11.2.3条2026-09-25 - 30
Highway JTG 3830-2018 plateau-region construction addition: from 2000 m elevation, base quota labor + quota plant cost, stepped rates in Table 3.1.6-4
Per clause 3.1.6 item 4 of JTG 3830-2018 "Measures for compiling estimat…
JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第 3.1.6 条第 4 款、Table 3.1.6-42026-09-25 - 31
Sizing and cost estimating of project temporary works: the three-way split of minor temporary works / heavy temporary works / employer's temporary works, plus the headcount-index method, capacity back-calculation, and itemized listing
First split temporary works by cost category: minor temporary works are…
TB 10801-2024 铁路基本建设工程设计概(预)算编制办法TB 10811-2024 铁路基本建设工程设计概(预)算费用定额GB 51114-2015 露天煤矿施工组织设计规范2026-09-25 - 32
Pooling and allocating temporary works costs of office/living/production zones: externally merged into preliminaries percentage rates, internally allocated by drivers
External pricing does not "allocate": office, living and small productio…
TB 10801-2024 第3.6节、第3.8节TB 10811-2024 第2.8节SJG 86-2020 第4.4.2条2026-09-25 - 33
Methods and liability basis for ensuring completeness of the bill of preliminaries at construction main (general) contracting tender stage (GB/T 50500-2024)
Per GB/T 50500-2024 clause 6.1.5, whether a re-measurable (unit-rate) or…
GB/T 50500-2024 建设工程工程量清单计价标准 第3.2.5条、第3.2.6条、第3.5.4条、第4.2.5条、第6.1.5条2026-09-25 - 34
Definition of winter construction and calculation of the winter construction cost increment
Winter construction begins when the outdoor daily mean temperature stays…
JGJ 104-97 建筑工程冬期施工规程GB/T 50875-2013 工程造价术语标准TB 10811-2024 铁路基本建设工程设计概(预)算费用定额2026-09-25 - 35
Highway estimate/budget construction-auxiliary fee base: quota direct costs x Table 3.1.6-8 rates (JTG 3830-2018 clause 3.1.6 item 6)
The highway construction-auxiliary fee is charged on the base "quota dir…
JTG 3830—2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第3.1.1条、第3.1.6条第6款、Table 3.1.6-8JTG/T 3832—2018 · Budget Quota of Highway Engineering 附录四JTG/T 3833 · Quota for Shift Costs of Highway Engineering Machinery2026-09-25 - 36
Estimating traffic diversion (traffic relief) costs of municipal works: pricing attribution and two estimation paths
Traffic diversion cost is a preliminary item charged in the bill of prel…
GB/T 50857-2024 市政工程工程量计算标准 App. M 措施项目GB 50861-2013 城市轨道交通工程工程量计算规范 Table N.10GB/T 50903-2013 市政工程施工组织设计规范 6.7.12026-09-25 - 37
Estimating rainy-season construction inputs: rate-based charging basis vs quantity-based scheme configuration
The rainy-season construction increment is charged as (quota labor cost…
JTG 3830-2018 公路工程建设项目概算预算编制办法 第3.1.6条、App. EJTG 3820-2018 公路工程建设项目投资估算编制办法 App. FTB 10801-2024 铁路基本建设工程设计概(预)算编制办法 第3.6条2026-09-25