Highway 2018 quota system profit: base = quota direct costs + measures + enterprise management, rate 7.42% (JTG 3830-2018 clause 3.1.9)

Per clause 3.1.9 of JTG 3830-2018 "Measures for compiling estimates and budgets of highway construction projects", highway profit is computed at 7.42% of "quota direct costs plus preliminaries and overheads" — a nationally uniform rate regardless of works class or region; profit enters the tax base (tax = (direct costs + permanent equipment procurement cost + preliminaries + overheads + statutory levies and fees + profit) x construction VAT rate, formula 3.1.10), so a wrong profit propagates into tax.

Applicable Codes

  • JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第 3.1.9 条、第 3.1.10 条

Topic Positioning

The base, rate and tax-base linkage of profit in the highway 2018 quota system (JTG 3830-2018 "Measures for compiling estimates and budgets of highway construction projects"), for correct fee-taking in highway estimate/budget compilation.

Core Conclusions

Standard text (clause 3.1.9): "Profit means the earnings of the contractor from completing the contracted works, computed at 7.42% of the sum of quota direct costs, preliminaries and overheads."

  • Base: quota direct costs + preliminaries + overheads (the three together). Quota direct costs = quota labor + quota materials + quota plant cost (quota base-price caliber); note the distinction from "direct costs" — the profit base takes the quota caliber.
  • Rate: 7.42%, a nationally uniform fixed value, no works-class or regional distinction, identical for estimates and budgets.
  • Status: profit is one of the 8 items of construction-installation costs (clause 3.1.1).
  • Relation to other bases: profit does not enter the statutory levies and fees base (statutory levies and fees are charged on the sum of labor costs of each works class, clause 3.1.8), but does enter the tax base.

Tax linkage (clause 3.1.10 verbatim): "Tax means the VAT output amount that state tax law requires to be included in the construction-installation works price. Tax = (direct costs + permanent equipment procurement cost + preliminaries + overheads + statutory levies and fees + profit) x the construction VAT rate" (3.1.10). A wrong profit thus also misstates tax.

Practice tip: in Form 03 (construction-installation cost calculation), profit is computed item by item — base column (quota direct costs + preliminaries + overheads), rate column 7.42%, amount = base x rate — not aggregated and charged once.

Applicable Boundaries

  • Applies to highway estimates/budgets under JTG 3830-2018 (2018 quota system).
  • Profit's base differs from other bases: within preliminaries, the winter/rainy/night additions, special-region additions, traffic-interference addition and works-transfer fee charge on (quota labor + quota plant cost); the construction-auxiliary fee and the five overheads items (including the basic fee) on quota direct costs (basic fee per Table 3.1.7-1); profit on (quota direct costs + preliminaries + overheads) — never swap them.
  • Not for other sectors: the railway TB 10801 system folds profit into indirect costs; building/municipal follows GB/T 50500 BOQ pricing; cross-sector comparison in the extension cards.
  • Mind old-new differences: the 1996 "Measures for compiling estimates and budgets of highway capital construction" used a different caliber (then "planned profit"); do not mix bases and rates across eras.

Further Reading

  • JTG 3830-2018 clause 3.1.9 (profit verbatim), clause 3.1.10 (tax and formula 3.1.10), clause 3.1.8 (statutory levies and fees), clause 3.1.11 (special costs: site construction fee, work-safety fee).
  • Same measures: clause 3.1.1 (8-item composition), clause 3.1.7 (overheads items and bases), clause 3.1.6 (preliminaries).
  • Related cards: the composition overview (card_60237eea), statutory levies and fees (card_2b86796d), overheads composition (card_fbc9eb80).