Determining overheads (company and site) and profit within the all-in unit rate: the dual track of the percentage-rate method and independent market-level measurement (including railway on-costs percentage rates)
Overheads (company and site) and profit are determined on the dual track of fee standards/percentage-rate method + market-level correction: estimates/budgets and tender price ceilings (employer's maximum acceptable price) are computed per the percentage rates in the norms for on-costs and expenses (railway merges the two into on-costs (indirect costs) = (base-period labour cost + base-period plant and small tools cost) × on-costs percentage rate, TB 10811-2024 Table 2.9.1, 16 categories, 14.3%–58.6%); tenders (priced offers) are independently measured by the enterprise; profit is a competitive cost but bidding below enterprise cost is prohibited. Price adjustment for cost fluctuation carries value added tax (VAT) only, with no overheads or profit.
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准 第2.0.9条、第6.1.3条
- GB/T 51095-2015 建设工程造价咨询规范 第5.3.9条
- TB 10811-2024 铁路基本建设工程设计概(预)算费用定额 第2.9.1条及Table 2.9.1
- JTG 3830-2018 公路工程建设项目概算预算编制办法
Topic Positioning
This card answers how overheads (company and site) and profit within the all-in unit rate are determined: the dual-track determination principle, competition boundaries, and a railway rate example.
Core Conclusions
- Dual-track principle (GB/T 51095-2015 Clause 5.3.9): overheads (company and site) and profit are computed per the norms for on-costs and expenses or fee standards, and determined in combination with the project's actual conditions and the market level in the compilation period.
- Overheads (company and site) = expenses incurred in organizing construction production and operating management (GB/T 50875-2013 Clause 2.2.20), including salaries of management personnel, office expenses, travel and transportation, use of fixed assets and tools and instruments, inspection and testing, property insurance, taxes and duties, entry/exit and site-transfer costs, financial expenses, etc. (TB 10801-2024 Clause 3.9.2).
- Determination paths: (1) percentage-rate method — railway merges overheads and profit into on-costs (indirect costs) = (base-period labour cost + base-period plant and small tools cost) × on-costs percentage rate (TB 10811-2024 Table 2.9.1, 16 categories, 14.3%–58.6%); (2) independent measurement — comprehensive fee rates published by others should not be adopted (T/ZBD 100.1-2022 Clause 6.4.4).
- Profit is a competitive cost (T/CSCS 035-2023 Appendix A.3.2), independently priced in tendering; tendering below enterprise cost is prohibited (MOHURD Order No. 47, Article 31).
Applicable Boundaries
The percentage-rate method is used for estimates/budgets and tender price ceilings (employer's maximum acceptable price); at the tender stage competitive independent pricing applies; railway rates apply only to railway estimates/budgets. Overheads (company and site) and profit exclude tax; adjustment for cost fluctuation carries value added tax (VAT) only, with no overheads or profit; the 2024 edition abolished the independent item for statutory levies and fees — the former statutory levies and fees are amortized into labour unit prices and the overheads percentage rate.
Further Reading
GB/T 51095-2015 Clause 5.3.9; GB/T 50500-2024 Clauses 2.0.9/3.3.5/8.7.2; TB 10801-2024 Section 3.9; TB 10811-2024 Table 2.9.1; T/ZBD 100.1-2022 Clause 6.4.4; MOHURD Order No. 47 Article 31.