Six-step labour-material-plant analysis for the all-in unit rate: apply quota line items -> take consumption and compilation-period unit prices -> add management fee and profit -> fill the all-in unit rate analysis sheet

Labour-material-plant analysis splits the all-in unit rate by "consumption x unit price" into three direct costs — labour cost, material cost, and plant and small tools cost — then superimposes management fee, profit, and the agreed risk cost; consumption is taken from quota line item factor values, unit prices from the report compilation-period market prices / published price information (government guidance prices), and fees per the matching norms for on-costs and expenses (GB/T 51095-2015 Clause 5.3.9). The analysis sheet must be fully consistent with the BOQ all-in unit rate (GB/T 50500-2024 Clause 3.1.7), in the form of Appendix E.2.2.

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准
  • GB/T 51095-2015 建设工程造价咨询规范
  • TB 10801-2024 铁路基本建设工程设计概(预)算编制办法

Topic Positioning

Labour-material-plant analysis (all-in unit rate analysis) is the general method of "unbundling" the BOQ all-in unit rate: decompose by "consumption x unit price" into the three direct costs of labour cost, material cost, and plant and small tools cost, then superimpose management fee, profit, and the agreed risk cost, and fill the all-in unit rate analysis sheet. Applies to BOQ-based pricing projects priced with budget/preliminary estimate quota norms.

Core Conclusions

Six-step rate build-up: (1) apply budget quota line items; (2) take the line item labour/material/plant consumption; (3) take compilation-period prices (labour per comprehensive labour rates / published price information (government guidance prices), materials per site comprehensive average prices including freight and handling charges and procurement-keeping costs, plant per plant rate per machine-shift) — per GB/T 51095-2015 Clause 5.3.9, use compilation-period market prices and never mix base-period prices; (4) labour-material-plant cost = sum of consumption x unit price; (5) compute management fee and profit per the matching norms for on-costs and expenses (the base to which percentage rates are applied may be direct cost, labour cost, or labour + plant cost); (6) summarize and fill the sheet. The analysis sheet must be fully consistent with the BOQ all-in unit rate (GB/T 50500-2024 Clause 3.1.7), in the form of Appendix E.2.2 (detailed/simplified versions); for the construction-drawing based budget (pre-tender estimate) basis see Appendix C.0.8.

Applicable Boundaries

Applies to BOQ-based pricing building/municipal projects (fully inclusive price excluding VAT basis, excluding VAT). Highways use the all-in basis (including statutory levies and fees and taxes and duties); railways follow the TB 10801-2024 compilation method (labour cost = sum of quota labour consumption x comprehensive labour rate; on-costs (indirect costs) = (base-period labour cost + base-period plant and small tools cost) x percentage rate) — confirm the industry standard when citing. Where no applicable quota line item exists, switch to market price enquiry rate build-up.

Further Reading

See GB/T 50500-2024 Clauses 2.0.9, 3.1.7, 3.2.2 and Appendix E.2.2; GB/T 51095-2015 Clauses 5.3.8, 5.3.9 and Appendix C.0.8; for railway rate build-up see TB 10801-2024 Clauses 3.1-3.3, 3.9 and the TB 10811-2024 norms for on-costs and expenses.