pricing on a bill of quantities basis

20 knowledge cards · sorted by most recently updated

Concept Guide

Concept

Pricing on a bill of quantities basis (gongchengliang qingdan jijia) is the principal pricing model used in China for tendering and contracting construction works. Under this model, the employer prepares a detailed bill listing work items — measured by unified rules of measurement — together with their estimated quantities, and each tenderer fills in an all-in unit rate for every item. The resulting rates form the tender price, the contract price and, ultimately, the settlement price.

The model is governed by the national Code of Bills of Quantities and Valuation for Construction Works. Under GB 50500-2013 its use was mandatory for projects funded wholly or mainly by state funds; the current GB/T 50500-2024 edition (in force from 1 September 2025, replacing the 2013 code) is recommendable, though state-funded projects remain subject to hard requirements through supporting rules. Four features define the mechanism. First, quantity and price are separated: the employer supplies the quantities and bears the primary responsibility for the completeness and accuracy of the bill, while the tenderer prices the items. The all-in unit rate covers labour, materials, plant, overheads, profit and an agreed range of risks, so competition focuses on rates rather than quantities. Second, standardisation: unified item codes, item names, item descriptions, units and measurement rules make tenders comparable and facilitate evaluation and audit. Third, risk allocation: deviations in quantities, errors and omissions in the BOQ, and mismatches in item descriptions are dealt with through the contract's measurement and price-adjustment provisions; quantity risk generally rests with the employer and price risk with the contractor. Fourth, measurement and settlement: during construction, payment is made for the actual quantities executed at the tendered all-in unit rates, closing the loop of bill–measurement–payment.

Unlike the traditional quota-based pricing system, which derived cost directly from government-issued quotas and fee schedules, pricing on a bill of quantities basis returns pricing power to the market, with quotas serving only as a reference for build-up.

FIDIC Mapping

In the FIDIC system, the closest analogue is the measurement-and-valuation arrangement based on a Bill of Quantities. Under FIDIC contracts, the Bill of Quantities (defined in Sub-Clause 1.1.5 of the Red Book; the 2017 Yellow Book does not use the term, quantities being carried in the Schedules) is prepared by the Employer's advisers on the basis of the Drawings and Specification and included in the tender dossier; it typically breaks the project down into trades and processes and contains estimated quantities of the work. Tenderers insert rates and prices against those items. The Contract Price is then calculated on the basis of measurement of the quantities of work executed and their valuation at the rates and prices in the Bill of Quantities (or other Schedule), subject to adjustments provided for in the Contract — a mechanism commonly called re-measurement. The method of measurement is as stated in the Contract Data or, if not so stated, in accordance with the Bill of Quantities or other applicable Schedule; except as otherwise stated, measurement is of the net actual quantity of each item of the Permanent Works, with no allowance for bulking, shrinkage or waste.

Similarities and differences: both systems rest on a bill of items, unit rates and measurement of actual quantities, and both separate quantity from price. Three differences matter. First, institutional character: Chinese BOQ pricing was, under the 2013 code, a mandatory national valuation system with unified coding and item-description requirements (the 2024 edition is recommendable), whereas under FIDIC the depth and breakdown of the bill are left to the employer, with no unified coding system. Second, allocation of quantity risk: under FIDIC the quantities in the Bill of Quantities are estimates only, and deviations are handled through the contractual valuation and adjustment mechanisms, including adjustment of rates where a change in quantity exceeds a stated threshold and affects unit cost (see the valuation and adjustment arrangements associated with 12.3), and the new-rate path under Red Book 12.3 for items with no applicable rate (Red Book 12.4 addresses omissions forming part of a Variation, not missing BOQ items); the Chinese code, by contrast, sets out explicit price-adjustment rules for quantity deviations and omissions, and places accuracy responsibility more squarely on the employer. Third, variation and valuation procedure: under FIDIC the Engineer values work under 12.3 and deals with variations under 13 in a highly procedural manner, while Chinese practice relies more on the contract and the adjustment rules of the BOQ code.

Caution: pricing on a bill of quantities basis should not be equated with the FIDIC Bill of Quantities. The former is a mandatory valuation-code system; the latter is a contract document and a measurement-and-valuation mechanism. In international projects using FIDIC conditions, the method of measurement and the allocation of risk for quantity errors and omissions should be expressly agreed rather than assumed from Chinese BOQ rules.

Chinese TermEnglish TermFIDIC TermRelationNotes
工程量清单计价pricing on a bill of quantities basismeasurement and valuation based on the Bill of Quantities / re-measurementadjacent中国清单计价在 GB 50500-2013 时代为强制性国标体系,现行 GB/T 50500-2024(2025-09-01 实施)转为推荐性(国有资金项目经配套规定仍受硬约束);FIDIC 的清单只是合同文件之一且由雇主自定深度,机制相近但制度属性与风险分配不同。
工程量清单bill of quantities (BOQ)Bill of Quantitiesadjacent红皮书以 Bill of Quantities 为定义术语(红皮书 1.1.5;黄皮书 2017 主文不使用 BOQ 一词,量价载体随 Schedules 约定),由雇主顾问编制纳入招标文件;中国清单须遵循统一编码与项目特征描述规范。
综合单价all-in unit raterate and price in the Bill of Quantitiesadjacent中国综合单价含人工、材料、机械、管理费、利润及约定风险,FIDIC 单价的风险范围由合同与清单说明界定,二者涵盖口径需逐项核对。
工程量清单缺陷errors and omissions in the BOQomitted work / errors in the Bill of Quantitiesadjacent清单缺项漏项在 FIDIC 走新单价路径:红皮书 12.3 规定无适用或类似单价时商定或确定新费率(变更侧另见 13.3.1(l));红皮书 12.4 处理的是构成变更的删项(Omissions),黄皮书 12 则是竣工后试验——均非中国式清单漏项补项组价。