pricing on a bill of quantities basis
Concept Guide
Concept
Pricing on a bill of quantities basis (gongchengliang qingdan jijia) is the principal pricing model used in China for tendering and contracting construction works. Under this model, the employer prepares a detailed bill listing work items — measured by unified rules of measurement — together with their estimated quantities, and each tenderer fills in an all-in unit rate for every item. The resulting rates form the tender price, the contract price and, ultimately, the settlement price.
The model is governed by the national Code of Bills of Quantities and Valuation for Construction Works. Under GB 50500-2013 its use was mandatory for projects funded wholly or mainly by state funds; the current GB/T 50500-2024 edition (in force from 1 September 2025, replacing the 2013 code) is recommendable, though state-funded projects remain subject to hard requirements through supporting rules. Four features define the mechanism. First, quantity and price are separated: the employer supplies the quantities and bears the primary responsibility for the completeness and accuracy of the bill, while the tenderer prices the items. The all-in unit rate covers labour, materials, plant, overheads, profit and an agreed range of risks, so competition focuses on rates rather than quantities. Second, standardisation: unified item codes, item names, item descriptions, units and measurement rules make tenders comparable and facilitate evaluation and audit. Third, risk allocation: deviations in quantities, errors and omissions in the BOQ, and mismatches in item descriptions are dealt with through the contract's measurement and price-adjustment provisions; quantity risk generally rests with the employer and price risk with the contractor. Fourth, measurement and settlement: during construction, payment is made for the actual quantities executed at the tendered all-in unit rates, closing the loop of bill–measurement–payment.
Unlike the traditional quota-based pricing system, which derived cost directly from government-issued quotas and fee schedules, pricing on a bill of quantities basis returns pricing power to the market, with quotas serving only as a reference for build-up.
FIDIC Mapping
In the FIDIC system, the closest analogue is the measurement-and-valuation arrangement based on a Bill of Quantities. Under FIDIC contracts, the Bill of Quantities (defined in Sub-Clause 1.1.5 of the Red Book; the 2017 Yellow Book does not use the term, quantities being carried in the Schedules) is prepared by the Employer's advisers on the basis of the Drawings and Specification and included in the tender dossier; it typically breaks the project down into trades and processes and contains estimated quantities of the work. Tenderers insert rates and prices against those items. The Contract Price is then calculated on the basis of measurement of the quantities of work executed and their valuation at the rates and prices in the Bill of Quantities (or other Schedule), subject to adjustments provided for in the Contract — a mechanism commonly called re-measurement. The method of measurement is as stated in the Contract Data or, if not so stated, in accordance with the Bill of Quantities or other applicable Schedule; except as otherwise stated, measurement is of the net actual quantity of each item of the Permanent Works, with no allowance for bulking, shrinkage or waste.
Similarities and differences: both systems rest on a bill of items, unit rates and measurement of actual quantities, and both separate quantity from price. Three differences matter. First, institutional character: Chinese BOQ pricing was, under the 2013 code, a mandatory national valuation system with unified coding and item-description requirements (the 2024 edition is recommendable), whereas under FIDIC the depth and breakdown of the bill are left to the employer, with no unified coding system. Second, allocation of quantity risk: under FIDIC the quantities in the Bill of Quantities are estimates only, and deviations are handled through the contractual valuation and adjustment mechanisms, including adjustment of rates where a change in quantity exceeds a stated threshold and affects unit cost (see the valuation and adjustment arrangements associated with 12.3), and the new-rate path under Red Book 12.3 for items with no applicable rate (Red Book 12.4 addresses omissions forming part of a Variation, not missing BOQ items); the Chinese code, by contrast, sets out explicit price-adjustment rules for quantity deviations and omissions, and places accuracy responsibility more squarely on the employer. Third, variation and valuation procedure: under FIDIC the Engineer values work under 12.3 and deals with variations under 13 in a highly procedural manner, while Chinese practice relies more on the contract and the adjustment rules of the BOQ code.
Caution: pricing on a bill of quantities basis should not be equated with the FIDIC Bill of Quantities. The former is a mandatory valuation-code system; the latter is a contract document and a measurement-and-valuation mechanism. In international projects using FIDIC conditions, the method of measurement and the allocation of risk for quantity errors and omissions should be expressly agreed rather than assumed from Chinese BOQ rules.
| Chinese Term | English Term | FIDIC Term | Relation | Notes |
|---|---|---|---|---|
| 工程量清单计价 | pricing on a bill of quantities basis | measurement and valuation based on the Bill of Quantities / re-measurement | adjacent | 中国清单计价在 GB 50500-2013 时代为强制性国标体系,现行 GB/T 50500-2024(2025-09-01 实施)转为推荐性(国有资金项目经配套规定仍受硬约束);FIDIC 的清单只是合同文件之一且由雇主自定深度,机制相近但制度属性与风险分配不同。 |
| 工程量清单 | bill of quantities (BOQ) | Bill of Quantities | adjacent | 红皮书以 Bill of Quantities 为定义术语(红皮书 1.1.5;黄皮书 2017 主文不使用 BOQ 一词,量价载体随 Schedules 约定),由雇主顾问编制纳入招标文件;中国清单须遵循统一编码与项目特征描述规范。 |
| 综合单价 | all-in unit rate | rate and price in the Bill of Quantities | adjacent | 中国综合单价含人工、材料、机械、管理费、利润及约定风险,FIDIC 单价的风险范围由合同与清单说明界定,二者涵盖口径需逐项核对。 |
| 工程量清单缺陷 | errors and omissions in the BOQ | omitted work / errors in the Bill of Quantities | adjacent | 清单缺项漏项在 FIDIC 走新单价路径:红皮书 12.3 规定无适用或类似单价时商定或确定新费率(变更侧另见 13.3.1(l));红皮书 12.4 处理的是构成变更的删项(Omissions),黄皮书 12 则是竣工后试验——均非中国式清单漏项补项组价。 |
Updated 2026-09-13
- 01
Tender BOQ versus priced BOQ - relationship and effect compared: preparing and pricing parties, document status, content differences, accuracy responsibility (2013 edition clause 4.1.2 versus 2024 edition clause 3.1.8 split by unit-rate and lump-sum contracts), benchmark role in settlement (quantity variance under 9.6.2, variation valuation under 9.3.1), effect of unilateral amendment, and the order of precedence of contract documents
The two bills are not two documents but two stages of one bill: the tend…
GB 50500-2013 建设工程工程量清单计价规范 第2.0.2、2.0.3、4.1.2、4.1.3、9.3.1、9.6.2条GB/T 50500-2024 建设工程工程量清单计价标准 第2.0.18、3.1.8、3.4.5、6.1.6、6.1.7、6.1.9、7.2.1条、第8.2节、第8.9节GF-2017-0201 建设工程施工合同(示范文本) 通用合同条款第1.5款2026-10-25 - 02
Whether the all-in unit rate includes statutory levies and taxes: comparison and determination between BOQ-based pricing (non-fully-loaded) and the fully loaded all-in rate
Whether the all-in unit rate includes statutory levies and taxes depends…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 50875-2013 工程造价术语标准GB/T 51095-2015 建设工程造价咨询规范2026-10-01 - 03
GB/T 50500-2024 VAT pricing basis: all-in unit rates are fully inclusive prices excluding VAT, with VAT listed and assessed separately
BOQ item all-in unit rates and their totals are fully inclusive prices e…
GB/T 50500-2024 建设工程工程量清单计价标准 第3.1.6条、第3.2.11条GB/T 50875-2013 工程造价术语标准 第2.2.58条2026-09-25 - 04
Definitions, cost composition and applicable conventions of the direct-cost rate, the all-in unit rate and the fully loaded all-in rate compared (Order No. 107 of the Ministry of Construction, GB/T 50500-2024, GB/T 51095-2015, etc.)
The three rate conventions widen in scope in turn: the direct-cost rate…
《建筑工程施工发包与承包计价管理办法》(建设部令第107号)第五条《建筑工程施工发包与承包计价管理办法》(住房和城乡建设部令第16号,2014年施行;建设部令第107号的现行替代版本)GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第2.0.9条、第3.1.6条、第3.1.7条2026-09-25 - 05
GB/T 50500-2024 charging scope of the main contractor's attendance and coordination provisions: charged on free-issue materials and the employer's specialist subcontracts, not on the contractor's own subcontracting
Per GB/T 50500-2024, free-issue materials (materials provided by the emp…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 50875-2013 工程造价术语标准2026-09-25 - 06
Maximum bid price (former tender price ceiling) compilation framework and cost composition under GB/T 50500-2024
State-funded projects must set a maximum bid price (the former tender pr…
GB/T 50500-2024 建设工程工程量清单计价标准GB 50500-2013 建设工程工程量清单计价规范招标投标法实施条例 第27条2026-09-25 - 07
Should the construction-installation cost in a design estimate carry provisional sums? — the stage division of provisional sums (BOQ/contract level) vs reserve funds (estimate level)
No. The construction-installation cost (works cost) in a design estimate…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第 2.0.13、1.0.2、8.3.1 条T/ZBD 100.3-2022 · Work Guideline for Compilation of Design Estimates of Construction Projects 第 4.1.1、4.5.1、4.5.4 条及App. A、App. ETB 10801-2024 · Measures for Compilation of Design Estimates and Budgets of Railway Capital Construction Projects 第 2.6 节2026-09-25 - 08
Why the all-in unit rate under GB/T 50500-2024 excludes VAT: price-exclusive tax character, separation of net price and VAT, the rationale for listing taxes and duties (VAT under the current standard) separately, and practical reasons
Under GB/T 50500-2024, the all-in unit rate = labour cost + material cos…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction worksGB/T 50875-2013 · Standard glossary of project costs2026-09-25 - 09
GB/T 50500-2024: definitions of the three pricing methods (unit rate / lump sum / rate-based) and their applicability to each BOQ category
GB/T 50500-2024 provides: work-section BOQ items and day-work items shou…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第2.0.10~2.0.12、3.1.5、3.2.1、3.2.7条2026-09-25 - 10
Six-step labour-material-plant analysis for the all-in unit rate: apply quota line items -> take consumption and compilation-period unit prices -> add management fee and profit -> fill the all-in unit rate analysis sheet
Labour-material-plant analysis splits the all-in unit rate by "consumpti…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 51095-2015 建设工程造价咨询规范TB 10801-2024 铁路基本建设工程设计概(预)算编制办法2026-09-25 - 11
Method for formulating bid pricing strategy: project features -> total price level -> unit-rate structure -> compliance floor
Bid pricing strategy = total price level (how much to bid) x unit-rate s…
GB/T 50500-2024 建设工程工程量清单计价标准建设部令第89号 房屋建筑和市政基础设施工程施工招标投标管理办法DBJ/T 15-115-2016 广东省建设工程交易规范2026-09-25 - 12
Measurement linkage between GB/T 50500-2024 and the nine measurement standards GB/T 50854-50862-2024: responsibilities, cycles, and the division of procedures (procedures to the pricing standard, quantity take-off to the measurement standards)
GB/T 50500-2024 and the nine measurement standards (GB/T 50854-50862-202…
GB/T 50500-2024 建设工程工程量清单计价标准(Ch. 7、第9.4节、第3.3.8条)GB/T 50854-2024 房屋建筑与装饰工程工程量计算标准(第1.0.2、3.0.2、3.0.4、4.1.1、4.2.6条)GB/T 50860-2024 构筑物工程工程量计算标准(第3.0.4条)2026-09-25 - 13
Scope of GB/T 50500-2024: state-funded works shall use BOQ pricing (compulsion now carried by MOHURD Order No. 16), others should/may choose freely, compared with GB 50500-2013
Per GB/T 50500-2024 Clause 3.1.1: works invested with fiscal or state-ow…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第3.1.1条、第3.1.5条GB 50500-2013 · Code of Valuation with Bill Quantity of Construction Works 第3.1.1~3.1.3条(已废止)《建筑工程施工发包与承包计价管理办法》(住房和城乡建设部令第16号)第六条2026-09-25 - 14
Three bases for the composition of the construction price: cost elements, BOQ-based pricing, and final-account listing
The construction price (cost of works (construction and installation)) h…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 50875-2013 工程造价术语标准2026-09-25 - 15
GB/T 50500-2024 vs GB 50500-2013 edition change: all-in unit rate composition changes and the repositioning of statutory levies and fees and taxes and duties in the BOQ-based pricing system
The 2024 edition removes "statutory levies and fees" entirely from the B…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works (住房城乡建设部公告 2024 年第 212 号,2025-09-01 实施)GB 50500-2013 · Code of Valuation with Bill Quantity of Construction Works (已废止)2026-09-25 - 16
GB/T 50500-2024 replacing GB 50500-2013: what GB becoming GB/T means, expiry of the 2013 mandatory provisions, and the 2025-09-01 effective date
MOHURD Announcement (No. 212 of 2024, issued 2024-11-26) approved the "S…
GB/T 50500-2024 建设工程工程量清单计价标准(住建部公告 2024 年第 212 号,2025-09-01 实施)GB 50500-2013 建设工程工程量清单计价规范(已废止)中华人民共和国标准化法(2017 修订,主席令第 78 号)第二条2026-09-25 - 17
Framework for distinguishing quantity risk from price risk in contracts: risk objects, responsible parties, and quantified trigger lines (GB/T 50500-2024)
Quantity risk governs "how much is built" (BOQ defects, quantity changes…
GB/T 50500-2024 建设工程工程量清单计价标准 第3.3.1~3.3.3条GB/T 50500-2024 第8.7.1~8.7.6条GB/T 50500-2024 第8.9.1~8.9.2条2026-09-25 - 18
GB 50500-2013 -> GB/T 50500-2024: changes to the clauses on statutory levies and fees, taxes and the mandatory health, safety and environmental (HSE) provisions — mandatory provisions withdrawn, the bills restructured into four parts, and the item renamed statutory safety provisions
2013 Clause 3.1.6, “statutory levies and fees and taxes must be calculat…
GB 50500-2013 第3.1.5、3.1.6条(强制性条文)GB/T 50500-2024 第3.1.2、3.2.5、3.2.11、2.0.9、3.1.6条建办〔2005〕89号《建筑工程安全防护、文明施工措施费及使用管理规定》2026-09-25 - 19
Definition and cost composition of the all-in unit rate (GB/T 50500-2024 Clause 2.0.9, GB/T 50875-2013 Clause 2.2.58)
All-in unit rate = labour cost + material cost (including engineering eq…
GB/T 50500-2024 建设工程工程量清单计价标准 第2.0.9条GB/T 50875-2013 工程造价术语标准 第2.2.58条2026-09-25 - 20
GB/T 50500-2024, China's BOQ pricing standard: positioning, 2024-vs-2013 changes, chapter map and card-group navigation
GB/T 50500-2024, the China national pricing standard for BOQ-based prici…
GB/T 50500-2024 建设工程工程量清单计价标准(住建部公告 2024 年第 212 号;第1.0.1~1.0.3条、Ch. 8、App. A~G、前言)GB 50500-2013 建设工程工程量清单计价规范(已废止,对照)GB/T 50854-2024~GB/T 50862-2024 各专业工程量计算标准(配套计量体系)2026-09-25