Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

GB/T 50500-2024 VAT pricing basis: all-in unit rates are fully inclusive prices excluding VAT, with VAT listed and assessed separately

BOQ item all-in unit rates and their totals are fully inclusive prices excluding VAT (labour cost + material cost + plant and small tools cost + management fee + profit + agreed risk costs + indispensable auxiliary work costs), with taxes and duties listed separately under VAT; the VAT base = the combined amounts of the bill of quantities for divisional and sub-divisional works + the bill of preliminaries + the bill of provisional sums and other charges (less provisional sums for nominated specialist subcontract works) x the prescribed rate; provisional sums for nominated specialist subcontract works are tax-inclusive provisional amounts, on which VAT is no longer assessed.

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准 第3.1.6条、第3.2.11条
  • GB/T 50875-2013 工程造价术语标准 第2.2.58条

Topic Positioning

The VAT pricing basis under GB/T 50500-2024, the China national pricing standard for BOQ: all-in unit rates as fully inclusive prices excluding VAT, taxes and duties listed separately, and the rules for determining the VAT base.

Core Conclusions

(1) BOQ item all-in unit rates and their totals, and amounts priced on a per-item basis, shall all be fully inclusive prices excluding VAT, composed of labour cost, material cost, plant and small tools cost, management fee and profit, and including agreed or reasonably scoped risk costs and indispensable auxiliary work costs; the corresponding taxes and duties shall be reflected in the VAT item and may not be embedded in the all-in unit rate. (2) The VAT base = the combined amounts of the bill of quantities for divisional and sub-divisional works + the bill of preliminaries + the bill of provisional sums and other charges (less provisional sums for nominated specialist subcontract works), multiplied by the VAT rate prescribed by the competent government authority. (3) Provisional sums for nominated specialist subcontract works within the bill of provisional sums and other charges are tax-inclusive provisional amounts, on which VAT shall no longer be assessed in the BOQ.

Applicable Boundaries

The 2024 edition removes the independent statutory levies and fees item (statutory levies and fees are absorbed into all-in unit rates/management fees), with only VAT listed separately — different from the 2013 edition and some local documents; confirm the applicable version before compiling or reviewing; highways and other industries may use fully inclusive bases that take in statutory levies and fees together with taxes; prime cost (PC) sums for materials and provisional sums for nominated specialist subcontract works differ in tax treatment — the former are pre-tax, the latter tax-inclusive.

Further Reading

GB/T 50500-2024, Clause 3.1.6 (all-in unit rates as fully inclusive prices excluding VAT), Clause 3.2.11 (VAT base); GB/T 50875-2013, Clause 2.2.58 (definition of all-in unit rate); use together with GB/T 50500-2024, Section 8.4 adjustment of provisional prices after procurement.